Logged this week
Goochland County · County web page
The county reports that the community meeting on the draft data center amendments was held November 10 at Goochland High School, and it has posted the presentation and a recording. The page lists the proposed revisions, among them three overlay districts within the Technology Overlay District. As read on November 13, 2026, the page's calendar lists no published events for November and the page gives no Planning Commission or Board of Supervisors hearing date.
“Data centers are prohibited outside the TOD boundaries” (M1 M2 highlights)
Official copy
Background: the case study Goochland County, the county's technology overlay district and the lawsuit over it.
Loudoun County · Board action report · dated Sept. 15, 2026
The Board directed staff to prepare a resolution pausing its consideration of legislative applications for data centers and substations for up to 12 months from the date an application first went to the Planning Commission. The motion passed 7-1-0-1, with Supervisor Umstattd opposed and Supervisor Kershner abstaining.
“direct staff to prepare a resolution to pause Board of Supervisors consideration of legislative applications for data centers and substations for a period not to exceed 12 months from the date on which the application was first submitted to the Planning Commission” (p. 20)
Official copy
Background: the case study Loudoun County, Virginia — The Endgame Case: What It Costs to Change the Rules After the Industry Is Load-Bearing; the dataset Virginia Data Center Entitlement Route Register, a record of how each Virginia county and independent city, and five towns, approve a data center (Loudoun County row).
Loudoun County · Board action report · dated Oct. 20, 2026
The chair announced that the pause resolution, item 14p on that agenda, was deferred to the November 17, 2026 business meeting.
“Item 14p, Resolution to Pause Board of Supervisors Consideration of Legislative Applications for Data Centers and Substations was deferred to the November 17, 2026, Board Business Meeting.” (p. 1, item 3)
Official copy
Background: the case study Loudoun County, Virginia — The Endgame Case: What It Costs to Change the Rules After the Industry Is Load-Bearing; the dataset Virginia Data Center Entitlement Route Register, a record of how each Virginia county and independent city, and five towns, approve a data center (Loudoun County row).
Loudoun County · Board agenda
Item 14.m is the Resolution to Pause Board of Supervisors Consideration of Legislative Applications for Data Centers and Substations. The stated purpose is a pause of up to 12 months from the date an application was first submitted to the Planning Commission, so that the Board can apply Phase 2 of the Data Centers Standards and Locations amendments to it.
“The resolution shall be effective September 15, 2026, and the pause shall not cause an application to become inactive.” (Item 14.m, Purpose)
Official copy
Background: the case study Loudoun County, Virginia — The Endgame Case: What It Costs to Change the Rules After the Industry Is Load-Bearing; the dataset Virginia Data Center Entitlement Route Register, a record of how each Virginia county and independent city, and five towns, approve a data center (Loudoun County row).
Charles City County · Planning Commission agenda
The agenda lists a data center work session and its scheduling under the Community Development Director's report, and no public hearings. As read on November 13, 2026, the county's Agenda Center lists no minutes for the Board of Supervisors meeting of October 27.
“Data Center Work Session and scheduling” (Item VII.2)
Official copy
Background: the dataset Virginia Data Center Entitlement Route Register, a record of how each Virginia county and independent city, and five towns, approve a data center (Charles City County row).
State Corporation Commission · SCC filing · dated Oct. 29, 2026
Virginia Electric and Power Company (Dominion Energy Virginia) filed its amended line extension policy on October 29, 2026. The application sets the large-load customer size at 100 MW or greater. It says a contribution in aid of construction is not required when the customer's request is not the "but for" requirement for the new transmission facilities.
“for large-load customer size, the Company selected 100 MW or greater to be consistent with the large-load queue definition of a large-load customer” (Application p. 5, para. 9)
Official copy
Background: the report Concentrated Benefit, Dispersed Burden, a study of who carries the cost of the transmission built for Virginia's data centers.
Amherst County · Board minutes · dated Oct. 20, 2026
After a public hearing with no speakers, the Board adopted Ordinance 2026-7 as presented, with all five members voting aye. The minutes describe the ordinance as amending Sections 302, 601, 703, 711, 712, 919 and 1402 of the zoning ordinance. Sections 708 and 927, where the county code places data centers, are not among them.
“the Board adopted Ordinance 2026-7 as presented.” (Packet p. 26)
Official copy
Background: the dataset Virginia Data Center Entitlement Route Register, a record of how each Virginia county and independent city, and five towns, approve a data center (Amherst County row).
Augusta County · Board minutes · dated Oct. 26, 2026
A county planner discussed a Data Center Ordinance draft with the Board. The Board directed staff to make the changes discussed and bring the draft back to its November 23, 2026 staff briefing.
“The Board directed Staff to make changes as discussed during the Staff Briefing and bring it back to the November 23, 2026 Staff Briefing meeting for further discussion.” (Packet p. 32)
Official copy
Background: the dataset Virginia Data Center Entitlement Route Register, a record of how each Virginia county and independent city, and five towns, approve a data center (Augusta County row).
Frederick County · Board minutes · dated Oct. 28, 2026
The Board denied Conditional Use Permit #03-26, Winchester Gateway LLC's request for a data center campus on M1 land. All seven members voted aye on the motion to deny. The minutes are in the November 12 packet for approval on the consent agenda, and that packet's agenda lists the removal of the TM zoning district as item 13.A.
“Supervisor Orndorff moved to deny CONDITIONAL USE PERMIT #03-26 FOR WINCHESTER GATEWAY LLC. Vice Chairman Wells seconded the motion.” (Minutes p. 7, packet p. 13)
Official copy
Background: the dataset Virginia Data Center Entitlement Route Register, a record of how each Virginia county and independent city, and five towns, approve a data center (Frederick County row).
Grayson County · Board minutes · dated Oct. 8, 2026
Under the Data Center Draft Policy item, the Board voted 5-0 to require a special use permit for a data center on an industrial site. The minutes say the Planning Commission will work with the Berkley Group on the policy.
“Supervisor Tomlinson made the motion to require special use permit for anyone interested in an industrial site for data center; duly seconded by Supervisor Cunningham. Motion carried 5-0.” (PDF p. 24)
Official copy
Background: the dataset Virginia Data Center Entitlement Route Register, a record of how each Virginia county and independent city, and five towns, approve a data center (Grayson County row).
City of Radford · Meeting notice · dated Nov. 12, 2026
The city's Agenda Center lists no Planning Commission meeting for November 16, 2026, in an entry posted November 12 at 2:51 p.m.
“No Planning Commission Meeting, November 16, 2026”
Official copy
Background: the dataset Virginia Data Center Entitlement Route Register, a record of how each Virginia county and independent city, and five towns, approve a data center (City of Radford row).
Hanover County · Deferral request · dated Oct. 27, 2026
The applicant's representative asks for a two-month deferral of the Tradeport / Iron Horse cases, to the January 2027 Board of Supervisors meeting. As read on November 13, 2026, the county's case page shows this request under the Board of Supervisors public hearing and lists no hearing date there.
“I hereby request a two month deferral (to the January 2027 Board of Supervisors meeting) in order to: better prepare the matters.”
Official copy
Background: the case study Hanover County, the county's data center applications and the proffers offered in them.
Goochland County · County web page · dated Oct. 21, 2026
The county reports that the judge heard its demurrer for almost three hours on October 20 and did not rule at the hearing. Three of the nine original claims remain. As read on November 13, 2026, this page carries no update dated after October 21.
“This now leaves only 3 of the 9 original claims for consideration by the Court.”
Official copy
Background: the case study Goochland County, the county's technology overlay district and the lawsuit over it.
Virginia General Assembly · Session calendar
The legislature's calendar sets November 16, 2026 as the last day to act on legislation continued from the 2026 session. Prefiling for the 2027 session opened July 20, 2026.
“Last day to act on continued legislation is November 16, 2026.”
Official copy
Background: the statewide report What Virginia Is Spending, What Virginia Is Getting, the statewide reference on data center development in Virginia.
New report version
Version 0.8, dated Nov. 11, 2026, is posted. How each of 73 Virginia localities approves a data center, and whether that approval is a rezoning, special exception or special use permit, the three that engage the site assessment in Va. Code § 15.2-2209.5.
New report version
Version 1.1, dated Nov. 9, 2026, is posted. This case study follows two governments in one Virginia county through the data center entitlements they granted and the restrictions they adopted afterward, from the county's 2013 zoning amendment…
New report version
Version 1.1, dated Nov. 9, 2026, is posted. On March 18, 2025, the Loudoun Board of Supervisors voted 7–2 to require a special exception before a data center could be built in the districts where the use had been permitted by right. The reform never reached the Route 28 corridor, where commercial and industrial zoning is frozen by state statute until 2037, on a reading of that statute no court has construed. A point-geometry join puts 51 percent of Loudoun's built data-center square footage inside that district, a constraint the county publishes on its own website.
New report version
Version 1.1, dated Nov. 10, 2026, is posted. In April 2025 Pittsylvania County refused to rezone 763 acres for a private gas plant and data centers. Nine months later the same board made data centers by right on 3,500 acres at the Berry Hill megasite, in a district whose text says the county's own data-center standard does not apply there. Within eight weeks the regional industrial authority had approved a sale contract defining the buyer's project as no less than 3,300 megawatts with onsite gas generation. Noise: 52 dBA offered by the refused applicant, 77 dBA adopted, and that only beside residential zoning.
New report version
Version 1.2, dated Nov. 9, 2026, is posted. Hanover, documented in a companion study, decided its data center campuses one rezoning at a time.
New report version
Version 3.9, dated Nov. 9, 2026, is posted. Henrico County, Virginia spent fifteen years recruiting the data center industry and less than two years learning to govern it.
New report version
Version 1.2, dated Nov. 9, 2026, is posted. Louisa County, Virginia adopted a by-right technology overlay district in April 2023 and walked away from its central feature sixteen months later, about a year before Goochland County published a…
New report version
Version 1.2, dated Nov. 9, 2026, is posted. Every other county case study in this series documents a Virginia county deciding on promises.