What the public record holds for this locality: how a data center gets approved, who is building, and what has been filed and decided.

Approval On the record Who is building

How a data center gets approved here

Permit requiredA discretionary permit is required: a conditional or special use permit, a special exception or a provisional use permit.

A data center needs a special exception in the M-1 Industrial district. It was a by-right use there until Aug. 18, 2026, when the Board of Supervisors voted 3-2 to reclassify it (Ord. 2026-6). The Planning Commission had recommended the change 6-0 on July 16, 2026.

No later amendment to the data center sections was found in Board and Planning Commission agendas and packets through Oct. 20, 2026. Some scanned minutes in that period were not read. Ord. 2026-7, adopted 5-0 on Oct. 20, 2026 according to the draft Board minutes, amends other sections and not the data center sections.

State site assessment
Triggered. Approval here generates a rezoning, special exception or special use permit.
The register entry this is drawn from, in the dataset's own shorthand
Position
SPECIAL EXCEPTION
Where
M-1 Industrial
What the ordinance calls the use
Data centers
Provision
App. A §708.03(10) "Data Centers as provided in Section 927" (M-1 special exceptions); development standards §927; data centers removed from §708.02 by Ord. 2026-6; special exception procedure §410
If the use is not listed
SPECIAL-EXCEPTION ROUTE (Sec. 410); in M-1, §708.03(11): an unlisted use the zoning administrator finds "of the same general character as special exception uses in this district" is a special exception, not by right; by-right similar-use only in V-1, B-2, NOT M-1 (V-1/B-2 part not re-read 11-4-2026)
Adopted
Ord. 2026-6, adopted 8-18-2026, BOS 3-2 (aye Martin, Pugh, Campbell; nay Adams, Tucker; from OCR of scanned minutes); PC recommended 6-0 on 7-16-2026; §708 history note ends "Ord. No. 2026-6, 8-18-26"
Changes and status
Ord. 2026-6 purpose (BOS packet 8-18-2026): "reclassify data centers from a by-right use to a special exception use in the M-1, Industrial District". Adopted 8-18-2026, 3-2, after a motion to table to 9-22-2026 failed 2-3 (BOS minutes 8-18-2026). Codified: Municode "Codified through Ordinance No. 2026-6, adopted August 18, 2026. (Supp. No. 65, Update 1)". No later amendment to §708 or §927 in BOS and PC agendas and packets through 10-20-2026 (text layer; scanned minutes of 9-1, 10-6, PC 8-20 and 9-17 not OCR'd); Ord. 2026-7 (amending §§302, 601, 703, 711, 712, 919, 1402; not §708 or §927) adopted 10-20-2026, 5-0 (draft Board minutes of 10-20-2026, on the 11-17-2026 consent agenda).
Route before the change
By right
Date of the change
2026-08-18
Still to read
BOS minutes of 8-18-2026, p. 6 (tally read by OCR of a scan, not checked against the page image)
Confidence in this reading
High. Ordinance text read directly, citation verified, the position unambiguous.
Source as read
Municode Supp. 65 Update 1, codified through Ord. No. 2026-6 (8-18-2026); online content updated 10-23-2026. Read Nov. 4, 2026.

By right means the ordinance permits the use with no rezoning and no special permit. The state site assessment is the one in Va. Code § 15.2-2209.5. It applies to a new facility expected to need 100 megawatts or more when the approval is a rezoning, special exception or special use permit. This is a dated reading, current through Nov. 19, 2026. Ordinances change; read the cited provision before relying on it. From the dataset Virginia Data Center Entitlement Route Register, version 1.1, a record of how each of Virginia's 133 counties and independent cities, and five of its towns, approve a data center.

On the record

Primary documents read for the Data Center Ledger, newest first. Each title links to the official copy.

Who is building here: the public record

1 data center site in the permit record for Amherst County, grouped by site only where the records themselves link them, so one campus can appear as more than one site.

Data center sites found in the free state and federal records searched for Amherst County, and utility filings placed in the same locality, current through Nov. 22, 2026. Records are grouped under one site only where their own text links them: a site code, street address, project or campus name, notice number or named company. A record with no such link is listed on its own. Names are as each record prints them. A site missing here may still be planned: these sources miss projects that have no permit yet and code names no record ties to a company. From the dataset Who Is Building It: Virginia Data Center Sites in the Public Permit Record, which has every record, the grouping rules and what the sources do not show.

Sources: DEQ's active construction stormwater list, EPA ECHO (water and air), Virginia Permit Transparency, Corps of Engineers Norfolk District public notices, State Corporation Commission dockets and VEDP incentive reports.

This page covers only what these sources contain. A locality with little here may still have data center activity.