Virginia data center researcher: how each of 133 counties and cities approves one, and who pays for the grid. Independent, and updated as the record changes.
Data centers in Amherst County, Virginia
What the public record holds for this locality: how a data center gets approved, who is building, and what has been filed and decided.
Approval On the record Who is building
How a data center gets approved here
A data center needs a special exception in the M-1 Industrial district. It was a by-right use there until Aug. 18, 2026, when the Board of Supervisors voted 3-2 to reclassify it (Ord. 2026-6). The Planning Commission had recommended the change 6-0 on July 16, 2026.
No later amendment to the data center sections was found in Board and Planning Commission agendas and packets through Oct. 20, 2026. Some scanned minutes in that period were not read. Ord. 2026-7, adopted 5-0 on Oct. 20, 2026 according to the draft Board minutes, amends other sections and not the data center sections.
- State site assessment
- Triggered. Approval here generates a rezoning, special exception or special use permit.
The register entry this is drawn from, in the dataset's own shorthand
- Position
- SPECIAL EXCEPTION
- Where
- M-1 Industrial
- What the ordinance calls the use
- Data centers
- Provision
- App. A §708.03(10) "Data Centers as provided in Section 927" (M-1 special exceptions); development standards §927; data centers removed from §708.02 by Ord. 2026-6; special exception procedure §410
- If the use is not listed
- SPECIAL-EXCEPTION ROUTE (Sec. 410); in M-1, §708.03(11): an unlisted use the zoning administrator finds "of the same general character as special exception uses in this district" is a special exception, not by right; by-right similar-use only in V-1, B-2, NOT M-1 (V-1/B-2 part not re-read 11-4-2026)
- Adopted
- Ord. 2026-6, adopted 8-18-2026, BOS 3-2 (aye Martin, Pugh, Campbell; nay Adams, Tucker; from OCR of scanned minutes); PC recommended 6-0 on 7-16-2026; §708 history note ends "Ord. No. 2026-6, 8-18-26"
- Changes and status
- Ord. 2026-6 purpose (BOS packet 8-18-2026): "reclassify data centers from a by-right use to a special exception use in the M-1, Industrial District". Adopted 8-18-2026, 3-2, after a motion to table to 9-22-2026 failed 2-3 (BOS minutes 8-18-2026). Codified: Municode "Codified through Ordinance No. 2026-6, adopted August 18, 2026. (Supp. No. 65, Update 1)". No later amendment to §708 or §927 in BOS and PC agendas and packets through 10-20-2026 (text layer; scanned minutes of 9-1, 10-6, PC 8-20 and 9-17 not OCR'd); Ord. 2026-7 (amending §§302, 601, 703, 711, 712, 919, 1402; not §708 or §927) adopted 10-20-2026, 5-0 (draft Board minutes of 10-20-2026, on the 11-17-2026 consent agenda).
- Route before the change
- By right
- Date of the change
- 2026-08-18
- Still to read
- BOS minutes of 8-18-2026, p. 6 (tally read by OCR of a scan, not checked against the page image)
- Confidence in this reading
- High. Ordinance text read directly, citation verified, the position unambiguous.
- Source as read
- Municode Supp. 65 Update 1, codified through Ord. No. 2026-6 (8-18-2026); online content updated 10-23-2026. Read Nov. 4, 2026.
By right means the ordinance permits the use with no rezoning and no special permit. The state site assessment is the one in Va. Code § 15.2-2209.5. It applies to a new facility expected to need 100 megawatts or more when the approval is a rezoning, special exception or special use permit. This is a dated reading, current through Nov. 19, 2026. Ordinances change; read the cited provision before relying on it. From the dataset Virginia Data Center Entitlement Route Register, version 1.1, a record of how each of Virginia's 133 counties and independent cities, and five of its towns, approve a data center.
On the record
Primary documents read for the Data Center Ledger, newest first. Each title links to the official copy.
- Minutes, Amherst County Board of Supervisors, October 20, 2026 (in the November 17, 2026 agenda packet). After a public hearing with no speakers, the Board adopted Ordinance 2026-7 as presented, with all five members voting aye. The minutes describe the ordinance as amending Sections 302, 601, 703, 711, 712, 919 and 1402 of the zoning ordinance. Sections 708 and 927, where the county code places data centers, are not among them. In the Ledger
Who is building here: the public record
1 data center site in the permit record for Amherst County, grouped by site only where the records themselves link them, so one campus can appear as more than one site.
Data center sites found in the free state and federal records searched for Amherst County, and utility filings placed in the same locality, current through Nov. 22, 2026. Records are grouped under one site only where their own text links them: a site code, street address, project or campus name, notice number or named company. A record with no such link is listed on its own. Names are as each record prints them. A site missing here may still be planned: these sources miss projects that have no permit yet and code names no record ties to a company. From the dataset Who Is Building It: Virginia Data Center Sites in the Public Permit Record, which has every record, the grouping rules and what the sources do not show.
Site Plan for Madison Heights Data Center 1 record
- Permit filing, DEQ Stormwater Plan Review 2026-0256 · Site Plan for Madison Heights Data Center · Old Dominion Capital Partners, LLC
Sources: DEQ's active construction stormwater list, EPA ECHO (water and air), Virginia Permit Transparency, Corps of Engineers Norfolk District public notices, State Corporation Commission dockets and VEDP incentive reports.
This page covers only what these sources contain. A locality with little here may still have data center activity.