Virginia data center researcher: how each of 133 counties and cities approves one, and who pays for the grid. Independent, and updated as the record changes.

Portrait of Tommy N. Turner
Data Center LedgerFilings, minutes, orders and transcripts, logged as they are readLatest, Nov. 25: new report version →

Data Centers · By locality

Data centers in Grayson County, Virginia

What the public record holds for this locality: how a data center gets approved and what has been filed and decided.

Approval On the record

How a data center gets approved here

By right under a general useBy right, under a general use category that is not called a data center.

The ordinance allows "Call Centers and Data Processing/Storage Facilities" by right in the IND Industrial district only. About 13 areas are zoned IND. Two are vacant, in the county/IDA Industrial Park. The joint Board and Planning Commission minutes of Aug. 18, 2026 record that the use line was added in the early 2000s.

The same minutes record a speaker saying a data center could currently be built by right with no Board approval. The Board that day directed a special use permit for a "digital data center" and removal of the by-right language. A draft data center policy was on the Board's Oct. 8, 2026 agenda. The minutes of that meeting record a 5-0 vote on a motion to require a special use permit for anyone interested in an industrial site for a data center, with the Planning Commission to work with the Berkley Group on the policy. There was no public hearing that night.

No text amendment had been adopted on the record read, which covers Board minutes through Oct. 8, 2026, the Nov. 12, 2026 Board agenda and Planning Commission minutes, posted only through April 21, 2026. The ordinance text still allows the use by right in IND.

State site assessment
Not triggered on at least one route. A data center can be approved here, in at least one district or set of parcels, with no rezoning, special exception or special use permit. Other routes in the same locality may require one.
The register entry this is drawn from, in the dataset's own shorthand
Position
BY RIGHT (generic data processing line)
Where
IND Industrial only (approx. 13 areas zoned IND; 2 vacant, in county/IDA Industrial Park)
What the ordinance calls the use
Call Centers and Data Processing/Storage Facilities
Provision
Zoning Ord. ('September 2024'; adopted 12-8-1998, latest amendment printed on cover 9-12-2024; file uploaded 1-6-2025) Sec. 4-10.1(i), read in the county PDF by OCR (scanned); matches staff printout in BOS/PC minutes 8-18-2026
If the use is not listed
SPECIAL USE PERMIT ROUTE (Sec. 3-5: SUP required where a use 'is not listed ... and the proposed use can be considered a Special Use'; Sec. 5-11 frames SUPs as listed uses), OCR; use expressly listed, rule not reached
Adopted
Use line added 'in the early 2000's' per the joint BOS/PC minutes of 8-18-2026; cover lists amendments of 02/13/2001, 10/09/2001, 02/09/2004 among others; which one added it UNVERIFIED
Changes and status
Planning Dir. memo (Berkley Group, 9-3-2026, BOS packet 10-8-2026): 'The use is permitted by right only in the Industrial District (IND).' Joint BOS/PC minutes of 8-18-2026 record a speaker: 'currently it could be done by-right without requiring any approval by the Board.' BOS direction 8-18-2026: SUP for digital data center; remove by-right language. Draft Data Center Policy on BOS agenda 10-8-2026. Board minutes of 10-8-2026 (posted by 11-15-2026): motion 'to require special use permit for anyone interested in an industrial site for data center', carried 5-0, with the Planning Commission to work with the Berkley Group on the policy; no public hearing that night. No text amendment adopted on the record read (Board minutes through 10-8-2026; the 11-12-2026 Board agenda carries no data center item; Planning Commission minutes posted only through 4-21-2026); by right in IND remains the text
Still to read
Planning Commission minutes after 4-21-2026 (not posted on 11-15-2026), for any draft following the Board direction of 10-8-2026
Confidence in this reading
Medium. The position is established but one element is unresolved: the adopting ordinance, the scope, how current the text is, or the type of source.
Source as read
County PDF (DocumentCenter/View/257, uploaded Jan 06, 2025): footer 'September 2024'; cover 'Amended: 09/12/2024' (last listed); scanned, read by OCR. Read Nov. 4, 2026.

By right means the ordinance permits the use with no rezoning and no special permit. The state site assessment is the one in Va. Code § 15.2-2209.5. It applies to a new facility expected to need 100 megawatts or more when the approval is a rezoning, special exception or special use permit. This is a dated reading, current through Nov. 19, 2026. Ordinances change; read the cited provision before relying on it. From the dataset Virginia Data Center Entitlement Route Register, version 1.1, a record of how each of Virginia's 133 counties and independent cities, and five of its towns, approve a data center.

On the record

Primary documents read for the Data Center Ledger, newest first. Each title links to the official copy.

This page covers only what these sources contain. A locality with little here may still have data center activity.