Virginia data center researcher: how each of 133 counties and cities approves one, and who pays for the grid. Independent, and updated as the record changes.
Data centers in Goochland County, Virginia
What the public record holds for this locality: how a data center gets approved, what has been filed and decided, and what to read.
Case study: Goochland County, read from local packets, minutes, ordinances and agreements.
Approval Coming up On the record What to read
How a data center gets approved here
A data center is allowed by right in the M-1 and M-2 industrial districts, where the text sets no geographic limit, and inside the county's Technology Overlay District on any base zoning. In TOD West it needs a conditional use permit. The overlay is about 4,400 acres and TOD West about 900; both figures are approximate and were not measured from the county's map. The Board created the overlay on Nov. 6, 2025 by a 4-1 vote (Ord. 6471).
A lawsuit was filed Dec. 4, 2025. A demurrer was argued Oct. 20, 2026, the plaintiffs dropped four more claims, and no ruling had issued.
The county has drafted amendments that would prohibit data centers outside the overlay, ending by-right approval in M-1 and M-2 there. The drafts would also re-adopt the overlay as TOD-N, TOD-C and TOD-W and add high energy use facility standards. Which M-1 and M-2 parcels lie outside the overlay was not mapped. A community meeting was held Nov. 10, 2026. The county's presentation for that meeting, posted Nov. 12, 2026, gives a Planning Commission public hearing on Dec. 16, 2026 and an anticipated Board public hearing and vote in February 2027. The Planning Commission's deadline is Jan. 22, 2027. The amendments have not been adopted.
- State site assessment
- Not triggered on at least one route. A data center can be approved here, in at least one district or set of parcels, with no rezoning, special exception or special use permit. Other routes in the same locality may require one.
The register entry this is drawn from, in the dataset's own shorthand
- Position
- BY RIGHT in M-1 and M-2 (base zoning, no geographic limit in the text) and inside the TOD on any base zoning; CUP in TOD West
- Where
- M-1 (Sec. 15-262); M-2 (Sec. 15-272, by reference to M-1); TOD ~4,400 ac overlay; CUP only in TOD West ~900 ac (approximate acreages; not measured from the Figure 10a map)
- What the ordinance calls the use
- Data center
- Provision
- Sec. 15-262; Sec. 15-272; Art. 27A Secs. 15-448 to 15-450; Sec. 15-500
- If the use is not listed
- Not read
- Adopted
- ZOA-2025-00001 / Ord. 6471, 11-6-2025, 4-1; M-1 line under Sec. 15-262, history note Ord. Nos. 3875 (2-2-21), 4108 (6-1-21), 5703 (5-2-23), 5970 (7-2-24)
- Changes and status
- District created Nov 2025. Litigation filed 12-4-2025; demurrer argued 10-20-2026, plaintiffs dropped 4 more claims, no ruling (written opinion pending). County-initiated amendments drafted (prohibit data centers outside TOD; re-adopt TOD as TOD-N/C/W; HEUF standards): community meeting held 11-10-2026; the county's presentation for that meeting (posted 11-12-2026) gives a Planning Commission public hearing on 12-16-2026 and an anticipated Board public hearing and vote in February 2027, PC deadline 1-22-2027; not adopted. The draft would end by-right approval in M-1 and M-2 outside the TOD. Which M-1 and M-2 parcels lie outside the TOD was not mapped
- Route before the change
- by right (form not established)
- Date of the change
- 2025-11-06
- Still to read
- Ord. No. 6471 of 11-6-2025 (listed on Municode, not opened)
- Confidence in this reading
- Medium. The position is established but one element is unresolved: the adopting ordinance, the scope, how current the text is, or the type of source.
- Source as read
- Municode 'VERSION: SEP 14, 2026 (CURRENT)'; Supplement History Table through Supp. No. 128 (last ordinance listed 4-14-26, 6637); Ord. 6471 included in Supp. No. 127. Read Nov. 4, 2026.
By right means the ordinance permits the use with no rezoning and no special permit. The state site assessment is the one in Va. Code § 15.2-2209.5. It applies to a new facility expected to need 100 megawatts or more when the approval is a rezoning, special exception or special use permit. This is a dated reading, current through Nov. 19, 2026. Ordinances change; read the cited provision before relying on it. From the dataset Virginia Data Center Entitlement Route Register, version 1.1, a record of how each of Virginia's 133 counties and independent cities, and five of its towns, approve a data center.
Coming up
- Planning Commission's deadline to recommend on the county's proposed data center amendments. Source: Board resolution of October 6, 2026, as cited in the Goochland County case study. Last checked Nov. 9, 2026.
On the record
Primary documents read for the Data Center Ledger, newest first. Each title links to the official copy.
- 2026 Ordinance Update: November 10, 2026 community meeting. The county reports that the community meeting on the draft data center amendments was held November 10 at Goochland High School, and it has posted the presentation and a recording. The page lists the proposed revisions, among them three overlay districts within the Technology Overlay District. As read on November 13, 2026, the page's calendar lists no published events for November and the page gives no Planning Commission or Board of Supervisors hearing date. In the Ledger
- Technology Overlay District litigation: county update of October 21, 2026. The county reports that the judge heard its demurrer for almost three hours on October 20 and did not rule at the hearing. Three of the nine original claims remain. As read on November 13, 2026, this page carries no update dated after October 21. In the Ledger
What to read
- Case study: Goochland County. Hanover, documented in a companion study, decided its data center campuses one rezoning at a time.
- Report: Who Showed Up. A census of the organizations around data center siting in Virginia, 2014 to 2026.
- Book: Governing the Demand Shock. A comparison of how Virginia localities handled the arrival of data centers.
This page covers only what these sources contain. A locality with little here may still have data center activity.