Data Center LedgerFilings, minutes, orders and transcripts, logged as they are readLatest, Nov. 25: new report version →

All works · Virginia data center series — county case studies

Case Study: Pittsylvania County — The County Turned Down One Data Center Plan, Then Rezoned for a Bigger One

Plain-English summary

On April 15, 2025, Pittsylvania County's Board of Supervisors voted 6-1 to deny a rezoning of 763 acres for a private gas power plant and data centers. It had first refused the applicant's request to withdraw.

Nine months later, on January 15, 2026, the same board rezoned 3,500 acres at the Berry Hill megasite at its own request. Data centers there are now allowed by right, without a public hearing. A regional authority the county shares with Danville owns the land.

On March 9, 2026, that authority approved a sale contract defining the buyer's project as a data center of no less than 3,300 megawatts, with onsite gas generation.

The report finds the district weaker on noise than both the county's own 2024 data center standard and the refused applicant's offer. It calls the sequence refusal, then entitlement by ordinance, on the county's own motion.

Summary of version 1.1, November 2026. The full report carries the record behind each point.

Locality page: Pittsylvania County, with how a data center gets approved there and what else is on the record.

Full abstract

In April 2025 Pittsylvania County, Virginia refused to rezone 763 acres for a private gas plant and data centers. Nine months later the same Board of Supervisors made data centers by right on 3,500 acres at the Berry Hill megasite that already permitted private power plants, in a district whose text says the county's own data center standard does not apply there. Within eight weeks the county's regional industrial authority had approved a sale contract defining the buyer's project as no less than 3,300 megawatts of data center capacity with onsite gas generation.

The case study follows both decisions through the primary record: county packets, minutes and ordinances, the regional industrial facility authority's resolutions, purchase agreement form and executed performance agreement, Danville's council and utility commission minutes, State Corporation Commission dockets, and meeting video. It sets the district's substitute standard against the county's 2024 data center section and against the refused applicant's proffers, including noise (52 dBA offered, 77 dBA adopted, and that only beside residential zoning), and documents the August 2026 site assessment for large electricity users that exempts the megasite district from most of its requirements. On the utility side it traces the Berry Hill loop and substation, built by Appalachian Power and recovered through a rate clause under the 2019 business park pilot statute, which deemed their cost reasonable and prudent and since July 2023 also deems a park's need met once the state's economic development agency approves it; the company's flat forecasts against 24,881 megawatts of load in inquiry; and the four utilities whose territories divide the county's two sites. It closes by placing the sequence, refusal and then entitlement by ordinance on the county's own motion, against the five-posture typology of Governing the Demand Shock.

Version 1.1 carries the record from 25 September to 10 November 2026: the authority's October approval of the form of an early access agreement that lets the buyer grade about 376 acres before any closing, the state water protection permit application filed in the authority's name, Appalachian Power's October 2026 rate case stipulation, to which STACK is a party, and the 2016 letters in which Danville gave up electric service to the park. It also corrects version 1.0's account of the statute: the clause deeming a park's need met dates from July 2023, after the park was wired.

Version 1.1 (November 2026) supersedes version 1.0. Current through November 10, 2026; last full source audit September 25, 2026. Cite all versions: 10.5281/zenodo.22968398.

Disclosure: The author serves on the advisory board of an Alfred P. Sloan Foundation-funded study at Emory University on data centers and the Southern energy buildout. The study had no role in this case study.

Refusal, then entitlement by ordinance on the county's own motion. Traces the Berry Hill loop and substation built by Appalachian Power under the business-park pilot statute. isPartOf the Commonwealth Reference (20679292). Evidence snapshot 25 September 2026.

Cite this work

BibTeX
@misc{turner2026casestudypittsylvaniacou,
  author = {Turner, Tommy N.},
  title = {Case Study: Pittsylvania County — The County Turned Down One Data Center Plan, Then Rezoned for a Bigger One},
  year = {2026},
  publisher = {Zenodo},
  version = {1.1},
  doi = {10.5281/zenodo.22968398},
  url = {https://doi.org/10.5281/zenodo.22968398}
}
APA
Turner, T. N. (2026). Case Study: Pittsylvania County — The County Turned Down One Data Center Plan, Then Rezoned for a Bigger One (Version 1.1). Zenodo. https://doi.org/10.5281/zenodo.22968398
Chicago
Turner, Tommy N. 2026. “Case Study: Pittsylvania County — The County Turned Down One Data Center Plan, Then Rezoned for a Bigger One.” Version 1.1. Zenodo. https://doi.org/10.5281/zenodo.22968398.