Virginia Data Center Entitlement Route Register: how every Virginia county and independent city, and five towns, approve a data center, and whether the approval engages Va. Code § 15.2-2209.5
How every Virginia county and independent city, and five towns, approves a data center, and whether that approval is a rezoning, special exception or special use permit, the three that engage the site assessment in Va. Code § 15.2-2209.5.
Short guides: For county and city officials and staff · Working with the approval-route register
The short answer: How does a data center get approved in a Virginia county?
This register records, for every Virginia county and independent city and for five towns, the route by which a data center is approved under the local zoning ordinance, and whether that route requires a rezoning, special exception or special use permit. Those are the three approvals that trigger the site assessment in Va. Code § 15.2-2209.5, which applies to a new facility the applicant expects to need 100 megawatts or more and exempts an expansion of an approved facility that "does not exceed an additional 100 megawatts." A data center approved by any other route proceeds without the statutory assessment.
Current through: November 19, 2026. Rows were read between November 4 and November 17, 2026, and rows resting on a locality's answer were updated through November 19. The "Retrieved" date in the sources file is the date of each row's main reading; later reads and written answers are dated in the row's own cells. The last full source audit, a currency check on November 15, 2026, looked for changes adopted since the rows then on hand were read. Meetings set or proposed for November 18 and 19 are recorded as set or proposed; their outcomes were not read.
Of Virginia's 133 counties and independent cities, 44 have at least one route by which a data center is approved without any of the three; seven of those are coded as having no zoning ordinance, and in one, Albemarle County, the route applies only up to a size cap. Of the 133, the register finds a by-right route in some form, in at least one district or set of parcels, in 47. In four of them that route depends on the zoning administrator finding the use similar to a listed one, and in ten, those four among them, it rests on a reading the locality has not confirmed on the record read. Another 38 require a special permit of some kind, three require a rezoning, 38 have no approval route, and seven are coded as having no zoning ordinance, one of them (Buchanan County) at low confidence. In several localities other districts or larger projects still require one of the three; each row records both. The workbook's Summary sheet computes the route, assessment, change and confidence counts by formula, separately for the counties and cities, the towns, the 48 localities of the original sample and the 33 in the region covered by The Roanoke Times.
The counts are of local ordinances, not of land, sites or projects. A locality counts as by right if any district or parcel set allows a data center by right, however small; the District(s) column says where. The five towns were carried from earlier versions and are not a sample of Virginia's towns.
Each row names its source, the provision relied on where one decides the row, and, where the source prints one, its codified-through line. Where a locality's own record shows how it administers a provision, the row follows that practice; otherwise it follows the text and says so. One row, Highland County's, follows the author's notes of a telephone interview with its zoning administrator, at low confidence. Every code and fourteen coding rules are defined in the workbook's Codes sheet.
Open rows. Of all 138 rows, eleven are coded UNRESOLVED on whether approval triggers the assessment. Sixteen localities that have adopted no change have one drafted, initiated or set for hearing; a few that have adopted a change have another under way, which their rows record.
Changes from version 1.0. Between November 14 and 17, 2026, the author asked 43 localities in writing how their ordinance treats a data center, and 21 answered between November 15 and 19. This version records those answers, each in its row with the official's office and the date, along with further document reads. The route changed in four. The City of Fairfax, the City of Falls Church and Alleghany County are now coded as having no approval route on each zoning administrator's written statement. Highland County is coded the same way at low confidence, on the author's telephone interview with its zoning administrator; the row says so. Apart from those route changes, whether approval triggers the site assessment is now coded in six rows that version 1.0 left open: Bath County, the City of Alexandria and the City of Bristol trigger it, as does the City of Salem on the register's reading of the state code's definition of a special exception, and Wise County and Dickenson County do not. The City of Buena Vista is no longer coded as capped, because its General Manufacturing district carries no size limit. The City of Hopewell now carries a pending amendment. The file va_entitlement_register_v1_1_changes_from_v1_0.csv lists every cell that differs from version 1.0, with both values.
A companion report, How a Data Center Gets Approved in Virginia, reads the register statewide and maps it.
The register is a dated observation. Ordinances change; re-read the cited provision before relying on a row.