Virginia data center researcher: how each of 133 counties and cities approves one, and who pays for the grid. Independent, and updated as the record changes.
Data centers in Charles City County, Virginia
What the public record holds for this locality: how a data center gets approved, who is building, what has been filed and decided, and what to read.
Approval On the record Who is building What to read
How a data center gets approved here
A data center is allowed by right in M-1, M-2 and PD-IP. No such use or definition was found before April 23, 2024, when the county adopted it. Each data center line in the county's PDF carries an amendment note of that date, and earlier text was not read.
A county staff slide in the Planning Commission packet of Nov. 12, 2026 records that the Board adopted resolutions on Oct. 27, 2026 starting Comprehensive Plan and zoning text amendments. Under them, by-right approval in M-1, M-2 and PD-IP would become a special use permit. The vote was not read; the Board minutes had not been posted as of Nov. 15, 2026. The Planning Commission's Nov. 12, 2026 agenda carries a data center work session and scheduling, and no public hearing has been set on the records read. The amendments have been initiated and not adopted.
- State site assessment
- Not triggered on at least one route. A data center can be approved here, in at least one district or set of parcels, with no rezoning, special exception or special use permit. Other routes in the same locality may require one.
The register entry this is drawn from, in the dataset's own shorthand
- Position
- BY RIGHT
- Where
- M-1, M-2, PD-IP
- What the ordinance calls the use
- Data center
- Provision
- §§11-2(11),12-2(14),13-2(6); stds §20-3
- If the use is not listed
- Not read
- Adopted
- ZTA-02-2024, 4-23-2024
- Changes and status
- No use or definition found before 4-23-2024 (each data center line in the county PDF carries 'Amended 4-23-2024'; earlier text not read). A county staff slide in the Planning Commission packet of 11-12-2026 records Board resolutions 'adopted October 27, 2026' initiating Comprehensive Plan and zoning text amendments under which by-right becomes SUP in M-1, M-2 and PD-IP; the vote was not read (Board minutes of 10-27-2026 not posted on 11-15-2026). The Planning Commission's 11-12-2026 agenda carries 'Data Center Work Session and scheduling'; no public hearing set on the records read. Initiated, not adopted
- Route before the change
- not addressed
- Date of the change
- 2024-04-23
- Still to read
- Board minutes of 4-23-2024 adopting ZTA-02-2024 (not read)
- Confidence in this reading
- Medium. The position is established but one element is unresolved: the adopting ordinance, the scope, how current the text is, or the type of source.
- Source as read
- County PDF: Amendments through August 1, 2024. Read Nov. 4, 2026.
By right means the ordinance permits the use with no rezoning and no special permit. The state site assessment is the one in Va. Code § 15.2-2209.5. It applies to a new facility expected to need 100 megawatts or more when the approval is a rezoning, special exception or special use permit. This is a dated reading, current through Nov. 19, 2026. Ordinances change; read the cited provision before relying on it. From the dataset Virginia Data Center Entitlement Route Register, version 1.1, a record of how each of Virginia's 133 counties and independent cities, and five of its towns, approve a data center.
On the record
Primary documents read for the Data Center Ledger, newest first. Each title links to the official copy.
- Agenda, Charles City County Planning Commission regular meeting, November 12, 2026. The agenda lists a data center work session and its scheduling under the Community Development Director's report, and no public hearings. As read on November 13, 2026, the county's Agenda Center lists no minutes for the Board of Supervisors meeting of October 27. In the Ledger
Who is building here: the public record
1 data center site in the permit record for Charles City County, grouped by site only where the records themselves link them, so one campus can appear as more than one site.
Data center sites found in the free state and federal records searched for Charles City County, and utility filings placed in the same locality, current through Nov. 22, 2026. Records are grouped under one site only where their own text links them: a site code, street address, project or campus name, notice number or named company. A record with no such link is listed on its own. Names are as each record prints them. A site missing here may still be planned: these sources miss projects that have no permit yet and code names no record ties to a company. From the dataset Who Is Building It: Virginia Data Center Sites in the Public Permit Record, which has every record, the grouping rules and what the sources do not show.
Sources: DEQ's active construction stormwater list, EPA ECHO (water and air), Virginia Permit Transparency, Corps of Engineers Norfolk District public notices, State Corporation Commission dockets and VEDP incentive reports.
What to read
- Report: Who Showed Up. A census of the organizations around data center siting in Virginia, 2014 to 2026.
This page covers only what these sources contain. A locality with little here may still have data center activity.