Tommy N. Turner

Virginia data center researcher: how each of 133 counties and cities approves one, and who pays for the grid. Independent, and updated as the record changes.

Portrait of Tommy N. Turner
Data Center LedgerFilings, minutes, orders and transcripts, logged as they are readLatest, Nov. 25: new report version →

Data Centers · By locality

Data centers in Loudoun County, Virginia

What the public record holds for this locality: how a data center gets approved, who is building, what has been filed and decided, and what to read.

Case study: Loudoun County, read from local packets, minutes, ordinances and agreements.

Approval On the record Who is building What to read

How a data center gets approved here

By right in an overlayBy right inside an overlay or a defined set of parcels laid on land already zoned.

A data center is allowed by right only on Route 28 property in the CB and CI districts whose owner recorded an election before Dec. 13, 2023. The register counts six such elections covering 39.0 acres, inside a legacy overlay map of 7,971 acres, and has not established that the county map layer behind that count is complete. A special exception is required in PD-RDP, CLI, OP, IP, GI and MR-HI, and in CO for elected property. Data centers are prohibited in every other district. The Board ended by-right approval outside the elected Route 28 property on March 18, 2025 (ZOAM-2024-0001).

Of the six elected parcels, three carry no data center record in LOLA: two churches and one business center. A data center site plan on Thayer Road is in review. One question is open: whether land still under the 1972 zoning ordinance that made no election keeps by-right status under Va. Code § 15.2-4603(C). A county presentation of Sept. 24, 2026 says data centers are not permitted as a principal use under the 1972 ordinance, and a county case on the question (ZCOR-2026-0246, Bridgefield) is in review. A zoning administrator advisory opinion (ZCOR-2026-0210) was not read.

A resolution on the Board's Nov. 17, 2026 agenda would pause Board consideration of legislative applications for data centers and substations for up to 12 months from Planning Commission submission, effective Sept. 15, 2026. It has not been adopted. A separate amendment, ZOAM-2026-0002, with map amendments ZMAP-2026-0004 and ZMAP-2026-0005, is set for a Planning Commission public hearing on Nov. 19, 2026. It would delete the Route 28 Corridor (Legacy) section, § 5.09, and eliminate the Route 28 Corridor District and its three optional overlay districts, rezoning their land to the equivalent current districts. What that remap would do to data center permissions on the land was not read. A second-phase amendment (ZOAM-2025-0002) is pending. The register rates this entry low confidence.

State site assessment
Not triggered on at least one route. A data center can be approved here, in at least one district or set of parcels, with no rezoning, special exception or special use permit. Other routes in the same locality may require one.
The register entry this is drawn from, in the dataset's own shorthand
Position
BY RIGHT in Route 28 CB/CI only on property that recorded an election before 12-13-2023 (§ 5.09.01.A, § 5.09.07.01); SPEX elsewhere
Where
P in CB and CI, S in CO (Tbl 5.09.06-2), for elected property only: six recorded CB/CI elections, 39.0 ac, inside the 7,971-ac legacy overlay map (county GIS layer 13; completeness of that layer not established); SPEX in PD-RDP, CLI, OP, IP, GI, MR-HI; prohibited in all other districts of Tables 3.02.01-1 to 3.02.05-1
What the ordinance calls the use
Data Center
Provision
ZOAM-2024-0001; Tbl 3.02.02-1, 3.02.05-1; stds §4.06.02; Route 28 optional overlay §5.09.01, §5.09.07.01, Tbl 5.09.06-2
If the use is not listed
Administrator determination, else text amendment, §3.01.G
Adopted
Board 3-18-2025
Changes and status
By-right ended outside elected Route 28 CB/CI property (ZOAM-2024-0001, 3-18-2025). An election waives the Route 28 Tax District protections (§ 5.09.01.F, § 5.09.07.01.B), so the pocket does not rest on Va. Code § 15.2-4603(C). Of the six elected CB/CI parcels, three carry no data center record in LOLA (two churches, one business center); Thayer Rd data center site plan in review. Open: whether unelected 1972-ordinance land keeps by-right under § 15.2-4603(C) (ZCOR-2026-0246, Bridgefield, in review; county 9-24-2026 deck: data centers "not permitted as a principal use under the 1972 ZO"); Zoning Administrator advisory opinion ZCOR-2026-0210 (approved) not read. Legislative pause resolution (to pause Board consideration of legislative applications for data centers and substations for up to 12 months from Planning Commission submission, effective 9-15-2026) on the 11-17-2026 agenda, not adopted. ZOAM-2026-0002 with ZMAP-2026-0004 and ZMAP-2026-0005 set for Planning Commission public hearing 11-19-2026: it would delete § 5.09 Route 28 Corridor (Legacy) and § 1.02.K and eliminate the Route 28 Corridor District and its three optional overlay districts, rezoning their land to the equivalent current districts; scheduled, not adopted; what the remap would do to data center permissions on that land not read; Phase 2 ZOAM-2025-0002 pending
Route before the change
by right (form not established)
Date of the change
2025-03-18
Still to read
Zoning Administrator advisory opinion ZCOR-2026-0210 (approved; not read)
Confidence in this reading
Low. An interpretive question is unanswered on the record.
Source as read
enCodePlus viewer carries no current-through line; no data center ZOAM adopted 9-15 to 10-20-2026 per Action Reports. Read Nov. 4, 2026.

By right means the ordinance permits the use with no rezoning and no special permit. The state site assessment is the one in Va. Code § 15.2-2209.5. It applies to a new facility expected to need 100 megawatts or more when the approval is a rezoning, special exception or special use permit. This is a dated reading, current through Nov. 19, 2026. Ordinances change; read the cited provision before relying on it. From the dataset Virginia Data Center Entitlement Route Register, version 1.1, a record of how each of Virginia's 133 counties and independent cities, and five of its towns, approve a data center.

On the record

Primary documents read for the Data Center Ledger, newest first. Each title links to the official copy.

Who is building here: the public record

95 data center sites in the permit record for Loudoun County, grouped by site only where the records themselves link them, so one campus can appear as more than one site.

Data center sites found in the free state and federal records searched for Loudoun County, and utility filings placed in the same locality, current through Nov. 22, 2026. Records are grouped under one site only where their own text links them: a site code, street address, project or campus name, notice number or named company. A record with no such link is listed on its own. Names are as each record prints them. A site missing here may still be planned: these sources miss projects that have no permit yet and code names no record ties to a company. From the dataset Who Is Building It: Virginia Data Center Sites in the Public Permit Record, which has every record, the grouping rules and what the sources do not show.

County-wide records

Filings that name no site, state grants, and State Corporation Commission cases placed in this locality.

Sources: DEQ's active construction stormwater list, EPA ECHO (water and air), Virginia Permit Transparency, Corps of Engineers Norfolk District public notices, State Corporation Commission dockets and VEDP incentive reports.

What to read

This page covers only what these sources contain. A locality with little here may still have data center activity.