Virginia data center researcher: how each of 133 counties and cities approves one, and who pays for the grid. Independent, and updated as the record changes.
Data centers in the City of Virginia Beach, Virginia
What the public record holds for this locality: how a data center gets approved and what to read.
How a data center gets approved here
The zoning ordinance does not name data centers. They fall under wholesaling, warehousing, storage or distribution, which is by right in I-1 and I-2. John Coston told Council so on May 6, 2026; the document recording that statement is not identified.
Sabo said in August 2026 that the city was working toward an ordinance requiring a conditional use permit; the source document for that statement is not identified either. On Aug. 18, 2026 Council adopted, 10-0 on its consent agenda, a moratorium on issuing permits related to new data centers for 12 months or until it takes final action on a regulating ordinance. The moratorium creates no discretionary approval, so the register's reading of the route is unchanged.
- State site assessment
- Not triggered on at least one route. A data center can be approved here, in at least one district or set of parcels, with no rezoning, special exception or special use permit. Other routes in the same locality may require one.
The register entry this is drawn from, in the dataset's own shorthand
- Position
- SILENT BY-RIGHT
- Where
- I-1, I-2
- What the ordinance calls the use
- wholesaling, warehousing, storage or distribution
- Provision
- CZO Sec. 1001(a) closed chart: "No uses or structures other than as specified shall be permitted." Similar-use provision exists ONLY at Secs. 2203 and 2403 (neither industrial). By right via the ENUMERATED "wholesaling, warehousing, storage or distribution" row
- If the use is not listed
- DEFAULT PROHIBITION (Sec. 1001(a)); similar-use only at Secs. 2203, 2403
- Adopted
- Current thru Ord. 3856, 5-19-2026
- Changes and status
- John Coston to Council 5-6-2026 (source document not identified): data centers "are not specified in the zoning ordinance and are allowed in industrial districts," falling under wholesaling/warehousing. Sabo, Aug 2026 (source document not identified): working toward an ordinance requiring a CUP. Resolution to establish a moratorium "on the issuance of permits related to any new data centers for twelve (12) months" or until Council takes final action on an ordinance regulating data centers, adopted by consent 10-0, 8-18-2026 (City Summary of Council Actions, item I.3). It creates no discretionary approval, so the route and the fires coding are unchanged
- Still to read
- Record of the 5-6-2026 statement to Council on industrial districts (source document not identified)
- Confidence in this reading
- Medium. The position is established but one element is unresolved: the adopting ordinance, the scope, how current the text is, or the type of source.
- Source as read
- Municode Code of Ordinances: Codified through Ordinance No. 3872, adopted September 1, 2026 (Supp. No. 170); CZO placement in that code not confirmed. Read Nov. 4, 2026.
By right means the ordinance permits the use with no rezoning and no special permit. The state site assessment is the one in Va. Code § 15.2-2209.5. It applies to a new facility expected to need 100 megawatts or more when the approval is a rezoning, special exception or special use permit. This is a dated reading, current through Nov. 19, 2026. Ordinances change; read the cited provision before relying on it. From the dataset Virginia Data Center Entitlement Route Register, version 1.1, a record of how each of Virginia's 133 counties and independent cities, and five of its towns, approve a data center.
What to read
- Report: Who Showed Up. A census of the organizations around data center siting in Virginia, 2014 to 2026.
- Report: Henrico County case study. Henrico County, Virginia spent fifteen years recruiting the data center industry and less than two years learning to govern it.
- Statewide report: What Virginia Is Spending, What Virginia Is Getting. The statewide reference on data center development in Virginia.
- Book: Governing the Demand Shock. A comparison of how Virginia localities handled the arrival of data centers.
- Report: Governing the Demand Shock. Virginia hosts the largest concentration of data centers in the world, and between roughly 2018 and 2026 the industry moved out of its Northern Virginia core into more than two dozen counties and independent cities.
- Report: Below the Curve. A census of local noise rules in Virginia and what they measure.
This page covers only what these sources contain. A locality with little here may still have data center activity.