What the Record Does Not Say: Interstate gas supply for Virginia generation, and a question no forum wrote down
Plain-English summary
On November 25, 2025, Virginia's State Corporation Commission approved Dominion Energy Virginia's 944-megawatt Chesterfield Energy Reliability Center, a gas plant. After reconsidering, it reaffirmed that on February 12, 2026.
Intervenors' experts asked how the plant would get its gas; one said guaranteed fuel could add about $300 million. Dominion said no new pipeline contract was needed, since its existing contracts would serve the plant. The final order does not mention that exchange.
On October 16, 2025, after the hearing closed, a Dominion fuel subsidiary signed a 20-year contract for new Mountain Valley Pipeline capacity, tied in a federal filing to the utility's existing generation. The report finds that no order it read states what that capacity costs.
An appeal to the Supreme Court of Virginia, pending as of September 14, 2026, faults the Commission for not requiring a reliable fuel cost estimate.
Summary of version 1.1, October 2026. The full report carries the record behind each point.
Full abstract
Virginia's State Corporation Commission spent nearly nine months deciding whether the Commonwealth needed a 944 megawatt gas plant, then suspended that decision and took another two months to reconsider it. A Sierra Club witness told it that the Company's own resource plan places its gas-fired fleet in a fully subscribed pipeline corridor, and an Advanced Energy United witness told it that the omitted cost of firm fuel could add roughly $300 million to a project the Commission priced at $1.47 billion. The Company answered in rebuttal that CERC carries no pipeline transportation or storage contract costs and will be served from its existing contract portfolio. Its resource plan, filed the year before, says combustion turbines can use firm capacity not needed by its combined-cycle units and, when available, interruptible service, and in setting their capacity factor limits assumed oil-only operation in the winter. Company analyses and intervenor modelling put at least four different capacity factors on the plant, ranging from 2.7 to 20 percent, and an intervenor told the Commission the figure kept changing between analyses. The twenty-seven page final order does not mention the exchange, names no pipeline company, and does not use the phrase "capacity factor." Asked on reconsideration whether it had ignored evidence it did not discuss, the Commission answered that the allegation is "incorrect as a matter of both fact and law," relying on the presumption that a Commission decision considered all of the evidence of record. Twenty days after the hearing closed, an indirect subsidiary of the applicant signed a twenty-year contract for 200,000 dekatherms a day of new interstate transportation capacity, filed for certification with a federal agency that has said, in a neighbouring Virginia certificate, that it "does not weigh end uses differently for the purpose of determining need for a project." This paper traces what each forum wrote down and finds that no Virginia order read for it states what the capacity costs.
Corpus. Nineteen filings from State Corporation Commission Case No. PUR-2025-00037, including all four hearing transcripts and the whole reconsideration phase; three FERC certificate and rehearing orders, with one certificate application and its precedent agreements; an integrated resource plan appendix; the Utility Facilities Act and two orders construing it; and the fuel cost recovery statute. Evidence snapshot 14 September 2026.
Disclosure: The author serves on the advisory board of an Alfred P. Sloan Foundation-funded study at Emory University on data centers and the Southern energy buildout. The study had no role in this paper.
Version 1.1 (October 2026) supersedes version 1.0. Corrections and updates for the items dated in the text, through October 24, 2026. Cite all versions: 10.5281/zenodo.22754150.