Data Centers · Questions

Who pays for the power lines built to serve data centers in Virginia?

It depends on which line. For a data center's own connection to the grid, Virginia's utility regulator, the State Corporation Commission, has directed Dominion Energy Virginia to propose a charge on the large customer that needs it. The cost of the local upgrades a data center's arrival makes necessary reaches every Dominion customer through a transmission charge. The cost of a long high-voltage line is split among the utility zones of PJM, the regional grid operator, and Dominion's zone pays about 45 percent of the Joshua Falls to Yeat line, the one examined here.

This answer covers Dominion Energy Virginia's zone of PJM. Current through Nov. 26, 2026.

Who pays, by kind of line
The lineWho paysWhat the record shows
A data center's own connectionThe large customer that needs it, under a charge that is proposed and not yet in force.The commission's final order of July 31, 2026, in Case No. PUR-2026-00056 directed Dominion to file amendments to its line extension policy that would require a mandatory contribution from new or expanding large-load customers for the substations and lines that connect them to the bulk transmission system. Dominion filed its application on Oct. 29, 2026 (Case No. PUR-2026-00131). It sets the large-load customer size at 100 megawatts or greater. The commission issued an order for notice and comment on Nov. 24, 2026, and has not ruled.
Local upgrades a data center's arrival makes necessaryEvery Dominion customer, through a transmission charge.PJM calls these supplemental projects. The July 31 order left who pays for them to be considered later.
Regional lines of 500 kilovolts and aboveThe utility zones of PJM, under PJM's formula. Within Dominion's zone the cost is spread by customer class.PJM allocates the Joshua Falls to Yeat 765-kilovolt line half by each zone's share of load and half by a flow-tracing analysis PJM calls a distribution factor. Dominion's combined share is 44.96 percent as filed in February 2025 and 45.29 percent on the 2026 load figures.

Unless another source is named, the findings below are from the report Concentrated Benefit, Dispersed Burden, version 1.3, Oct. 10, 2026.

Why the cost is shared

On Feb. 26, 2025, PJM's board approved the Joshua Falls to Yeat high-voltage line. PJM attributes the load growth behind it primarily to data centers. The tax benefit of a data center goes to the locality that hosts it. Dominion's share of the line's cost, about 45 percent, is spread across its whole zone by customer class.

Where the line runs

No rule the report examined takes account of where the towers stand. Measured against the published route, 80.99 percent of the Joshua Falls to Yeat line runs through counties with no operating data center. A randomly placed line would do much the same: tested against 2,000 random corridors drawn within Virginia, that figure falls inside the random range.

What the lines now cost

The developer of Joshua Falls to Yeat is Valley Link Transmission. In November 2026 PJM's board authorized new costs and dates for Valley Link: about $5.1 billion in 2026 dollars, up from about $3 billion in 2024 dollars, with in-service dates from January 2030 through May 2031. Joshua Falls to Yeat, whose required in-service date is June 1, 2029, now shows a projected in-service date of Jan. 17, 2031, in PJM's project database.

On PJM's current figures, Dominion's zone would pay about $732 million of the $1.56 billion cost of the line and its Yeat substation. The substation carries a higher Dominion share than the line.

Appalachian Power and the cooperatives

Appalachian Power sits in the zone of American Electric Power, which pays a share of Joshua Falls to Yeat based on its load alone. The report located no source showing any of the four electric cooperatives that serve the line's corridor taking part in the PJM process that allocated its cost.

JLARC, the General Assembly's audit agency, projects that about 60 percent of Virginia's data center growth will land in the territory of the state's 13 electric cooperatives. The State Corporation Commission has let Rappahannock Electric Cooperative, then Mecklenburg Electric Cooperative, set the financial security required of large customers at the cooperative's discretion. Both points are from the companion reference Thirteen Cooperatives.

What is still open

The July 31 order addressed the connection and left who pays for the upgrades to be considered later. Dominion's proposed connection charge is pending in Case No. PUR-2026-00131.

In a notice of Oct. 9, 2026, PJM's transmission owners proposed that whoever buys transmission service for a data center sign on for 10 to 20 years and promise a minimum payment. The notice did not ask whether that payment covers the local lines and substations the data center requires. A footnote kept those costs in the rate shared by everyone in the owner's zone. The owners filed tariff changes with the Federal Energy Regulatory Commission on Nov. 16, 2026, in Docket No. ER27-520. The terms of that filing are not reflected here.

How PJM splits the cost of a regional line among its zones is before the same commission in Maryland Office of People's Counsel v. PJM, Docket No. EL26-63. It had not ruled as of Nov. 26, 2026.

Read the record

Dominion's Oct. 29, 2026, line extension application is logged in the Data Center Ledger, linked to the commission's own copy.