Virginia data center researcher: how each of 133 counties and cities approves one, and who pays for the grid. Independent, and updated as the record changes.
Data centers in Buckingham County, Virginia
What the public record holds for this locality: how a data center gets approved.
How a data center gets approved here
County staff read a data center as allowed by right in M-1 and M-2. The ordinance line is "Data processing centers," which is undefined, and M-2 takes in all M-1 permitted uses. The NC-1 district separately lists an undefined "Data/Technology Center" that the staff document does not mention. Staff say M-1 and M-2 barely exist on the ground.
A staff discussion document for a Planning Commission work session on Nov. 16, 2026 says data centers are by right in M-1 and M-2 and that nothing in the ordinance governs their noise, height, setbacks, buffers, water use or decommissioning. It reports no pending or approved application. Staff ask the Commission to direct drafts and options, and no overlay text exists in the documents read. The work session had not been held when the register was retrieved, and its minutes are the open item.
- State site assessment
- Not triggered on at least one route. A data center can be approved here, in at least one district or set of parcels, with no rezoning, special exception or special use permit. Other routes in the same locality may require one.
The register entry this is drawn from, in the dataset's own shorthand
- Position
- BY RIGHT in M-1 and M-2 on the county staff's own reading; the ordinance line is 'Data processing centers', not 'data center'
- Where
- M-1 (permitted uses list 'Data processing centers'); M-2 (takes all M-1 permitted uses). NC-1 permitted uses list 'Data/Technology Center' (undefined; not mentioned in the staff document). B-1 permitted and special use lists read in full: no data, technology or computing line. Other districts covered by a whole-document term search (118 pages, every 'data' and 'technolog' occurrence read), not line by line. Staff: M-1 and M-2 'barely exist on the ground'
- What the ordinance calls the use
- Data processing centers (M-1; undefined); Data/Technology Center (NC-1; undefined)
- Provision
- Zoning Ord. ('Updated by Board of Supervisors 06/22/2026'), Art. 2: M-1 Permitted Uses (p.34 to 35), M-2 Permitted Uses (p.36), NC-1 Permitted Uses (p.24); Art. 4 Zoning Permits and Uses Not Provided For (pp. 49 to 50). The district articles carry no section numbers
- If the use is not listed
- TEXT-AMENDMENT ROUTE (Art. 4 'Uses Not Provided For', p.50: referral to PC; if the governing body approves, 'the ordinance shall be amended to list the use as a permitted use in that district'). M-1 list is open-ended ('permitted but not limited to the following'); M-2 reads 'as follows but not limited to'. Rule not reached on the county's reading
- Adopted
- NOT LOCATED: the ordinance prints no history note for the 'Data processing centers' or 'Data/Technology Center' lines (the M-1 section ends 'Approved 4/18/2016'; what that date covers is not stated). The 06/22/2026 update is the solar and battery storage amendment (BOS special meeting 6-22-2026, unanimous), not a data center amendment
- Changes and status
- Staff discussion document for the PC work session of 11-16-2026 (scheduled, not yet held on 11-14-2026): 'Data centers are a by-right use in M-1 and M-2'; 'Nothing in the ordinance governs their noise, height, setbacks, buffers, water use, or decommissioning'; 'No applications Nothing is pending or approved.' PC minutes 7-27-2026: a commissioner said of the M-2 land at Arvonia, 'It's will allow data centers by right.' PC on 8-24-2026 voted to hold a work session on 9-21-2026 on a technology overlay; no record of that session found in the documents read. No overlay text exists in the documents read; staff ask the PC to 'Direct staff to develop drafts & options'. BOS minutes 8-10 and 9-14-2026: data center and overlay mentions fall in the public comment sections (pattern search of headings and motions; comments sampled, not read through). BOS minutes 6-8-2026 (pp. 18, 20, 22) and 7-13-2026 (p.2) carry the term; context not recorded. BOS minutes 5-11 and 10-13-2026: no hit; BOS agenda 11-10-2026: no public hearing, no zoning case. BOS records before May 2026 not read. No size, acreage or megawatt figure in the M-1, M-2 or NC-1 use lists or in the staff document. Staff practice is documented in a discussion document and in commission minutes. No written determination was found in the documents read (none was searched for)
- Still to read
- minutes of the Planning Commission work session of 11-16-2026 (scheduled; not held on 11-14-2026)
- Confidence in this reading
- Medium. The position is established but one element is unresolved: the adopting ordinance, the scope, how current the text is, or the type of source.
- Source as read
- County PDF 'Zoning Ordinance - 6-22-2026.pdf', cover: 'Article 9 changes Approved by Board of Supervisors 5-14-2018 Updated by Board of Supervisors 06/22/2026'. Read Nov. 14, 2026.
By right means the ordinance permits the use with no rezoning and no special permit. The state site assessment is the one in Va. Code § 15.2-2209.5. It applies to a new facility expected to need 100 megawatts or more when the approval is a rezoning, special exception or special use permit. This is a dated reading, current through Nov. 19, 2026. Ordinances change; read the cited provision before relying on it. From the dataset Virginia Data Center Entitlement Route Register, version 1.1, a record of how each of Virginia's 133 counties and independent cities, and five of its towns, approve a data center.
This page covers only what these sources contain. A locality with little here may still have data center activity.