Virginia data center researcher: how each of 133 counties and cities approves one, and who pays for the grid. Independent, and updated as the record changes.
Data centers in Rockingham County, Virginia
What the public record holds for this locality: how a data center gets approved and what to read.
How a data center gets approved here
A data center needs a special use permit and is allowed only in I-1 and PID. The Board adopted the change 5-0 on Sept. 10, 2025.
Before that the use was called "Electronic Data Storage or Processing Center" and was by right in PMR, I-1, I-2 and PID. The amendment renamed it "Data Center" and removed it from PMR and I-2. A later amendment, OA26-1153, adopted 4-0 on Oct. 28, 2026 according to draft minutes in the Nov. 12, 2026 Board packet, concerns a public service facility used by a public entity and is not a data center provision.
- State site assessment
- Triggered. Approval here generates a rezoning, special exception or special use permit.
The register entry this is drawn from, in the dataset's own shorthand
- Position
- SPECIAL USE PERMIT
- Where
- I-1, PID
- What the ordinance calls the use
- Electronic Data Storage or Processing Center -> renamed Data Center
- Provision
- Ord. PCO 25-10
- If the use is not listed
- not read
- Adopted
- Adopted 9-10-2025, 5-0 (adopting ordinance and minutes not read 11-4-2026)
- Changes and status
- Was BY RIGHT in PMR, I-1, I-2, PID. Now SUP in I-1/PID only; removed from PMR and I-2. OA26-1153 ('public service facility', defined as a facility 'used by a public entity') adopted 10-28-2026, 4-0, per the draft minutes in the 11-12-2026 Board packet; not a data center provision
- Route before the change
- By right
- Date of the change
- 2025-09-10
- Still to read
- Ord. PCO 25-10 of 9-10-2025 and its minutes (not read 11-4-2026)
- Confidence in this reading
- Medium. The position is established but one element is unresolved: the adopting ordinance, the scope, how current the text is, or the type of source.
- Source as read
- Not read today (Municode not opened); county agendas searched through 11-4-2026. Read Nov. 4, 2026.
By right means the ordinance permits the use with no rezoning and no special permit. The state site assessment is the one in Va. Code § 15.2-2209.5. It applies to a new facility expected to need 100 megawatts or more when the approval is a rezoning, special exception or special use permit. This is a dated reading, current through Nov. 19, 2026. Ordinances change; read the cited provision before relying on it. From the dataset Virginia Data Center Entitlement Route Register, version 1.1, a record of how each of Virginia's 133 counties and independent cities, and five of its towns, approve a data center.
What to read
- Report: Below the Curve. A census of local noise rules in Virginia and what they measure.
This page covers only what these sources contain. A locality with little here may still have data center activity.