Virginia data center researcher: how each of 133 counties and cities approves one, and who pays for the grid. Independent, and updated as the record changes.
Data centers in Henrico County, Virginia
What the public record holds for this locality: how a data center gets approved, who is building, and what to read.
Case study: Henrico County, read from local packets, minutes, ordinances and agreements.
Approval Who is building What to read
How a data center gets approved here
A data center needs a provisional use permit in O-1, O-2, O-3, O/S, B-1, B-2, B-3, M-1, M-2, M-3 and Highway Edge. In LI-PD it is allowed through a planned development master plan. It is not allowed in other districts.
The use was by right in M-1, M-2 and M-3 until the Board voted 5-0 on June 10, 2025 to change it. The QTS campus of about 8 million square feet is grandfathered. The Board of Zoning Appeals denied a vested-rights claim by Centra on Feb. 26, 2026.
On July 28, 2026 the Board added, 5-0, a requirement for any rezoning, provisional use permit or conditional use permit for a facility needing 100 megawatts or more: the applicant must submit a sound assessment for homes and schools within 500 feet and name its utility. Expansions of up to 100 megawatts are exempt. That text was read from the county's consolidated chapter; the enrolled ordinance was not read.
- State site assessment
- Triggered. Approval here generates a rezoning, special exception or special use permit.
The register entry this is drawn from, in the dataset's own shorthand
- Position
- PROVISIONAL USE PERMIT
- Where
- PUP ('P') in O-1, O-2, O-3, O/S, B-1, B-2, B-3, M-1, M-2, M-3 and Highway Edge; 'A' (PD Master Plan) in LI-PD; '-' (not allowed) in the other columns of Table 4205 (row read cell by cell)
- What the ordinance calls the use
- Data Center
- Provision
- §24-4328.B; §24-4326.C (High Energy Use Facilities, added by Ord. No. 1356); §24-4438
- If the use is not listed
- ADMIN DETERMINATION, else prohibited (Sec. 24-4203)
- Adopted
- Ord. 143-25 (codified Ord. No. 1342), 6-10-2025, 5-0; Ord. No. 1356 (Board paper 158A-26), 7-28-2026, 5-0
- Changes and status
- Was by right in M-1,M-2,M-3. QTS ~8M sf grandfathered. BZA denied Centra vested-rights claim 2-26-2026. Ord. No. 1356 (7-28-2026) added Sec. 24-4326.C: an applicant for a rezoning, provisional use permit or conditional use permit for a facility needing 100 MW or more must submit a sound assessment for homes and schools within 500 ft and name its utility; expansions of up to 100 MW exempt. Use-table districts unchanged. Read from the county consolidated Chapter 24 "Last Amended July 28, 2026"; enrolled ordinance not read; Municode not yet codified
- Route before the change
- By right
- Date of the change
- 2025-06-10
- Still to read
- Ord. No. 1342 (Board paper 143-25) of 6-10-2025 (not read; adoption known from the codifier history note)
- Confidence in this reading
- Medium. The position is established but one element is unresolved: the adopting ordinance, the scope, how current the text is, or the type of source.
- Source as read
- Ordinance No. 1355, enacted June 23, 2026 (Supp. No. 1, Rev.); Ord. No. 1356 (7-28-2026) uncodified; read in the county consolidated Chapter 24 'Last Amended July 28, 2026', enrolled text not read. Read Nov. 4, 2026.
By right means the ordinance permits the use with no rezoning and no special permit. The state site assessment is the one in Va. Code § 15.2-2209.5. It applies to a new facility expected to need 100 megawatts or more when the approval is a rezoning, special exception or special use permit. This is a dated reading, current through Nov. 19, 2026. Ordinances change; read the cited provision before relying on it. From the dataset Virginia Data Center Entitlement Route Register, version 1.1, a record of how each of Virginia's 133 counties and independent cities, and five of its towns, approve a data center.
Who is building here: the public record
10 data center sites in the permit record for Henrico County, grouped by site only where the records themselves link them, so one campus can appear as more than one site.
Data center sites found in the free state and federal records searched for Henrico County, and utility filings placed in the same locality, current through Nov. 22, 2026. Records are grouped under one site only where their own text links them: a site code, street address, project or campus name, notice number or named company. A record with no such link is listed on its own. Names are as each record prints them. A site missing here may still be planned: these sources miss projects that have no permit yet and code names no record ties to a company. From the dataset Who Is Building It: Virginia Data Center Sites in the Public Permit Record, which has every record, the grouping rules and what the sources do not show.
QTS Richmond, 6000 Technology Boulevard 7 records
- Air permit VA0000005108700210 · QTS RICHMOND DATA CENTER
- Public notice (wetlands and streams) NAO-2016-01624 · NAO-2016-01624 QTS, Henrico County, Virginia
- Construction stormwater permit VAR10Q648 · QTS East Expansion · Quality Investment Properties Richmond, LLC
- Construction stormwater permit VAR10O831 · QTS Project Interchange - Red Route · Team Fishel
- Permit filing, DEQ Air Permits 51232-17 · QTS Richmond Data Center · Quality Investment Properties Richmond LLC
- Stormwater coverage, EPA record VAR10R602 · QTS RIC1-DC3 · Quality Investment Properties Richmond, LLC
- Permit filing, DEQ Air Permits 51232-19 · QTS Richmond Data Center · Quality Investment Properties Richmond LLC
QTS RIC4 6 records
- Construction stormwater permit VAR10W816 · QTS RIC4 - Substation Saltwood & Graybark · QTS Richmond IV LLC
- Construction stormwater permit VAR10X248 · QTS RIC4 Phase 1 · QTS Richmond IV LLC
- Permit filing, VDOT Land Development POD-2025-102186 · QTS RIC4, Phase 1 · Townes Engineering
- Permit filing, VDOT Land Development POD-2025-102258 · QTS RIC4 - Thicket Substation · Townes
- Stormwater coverage, EPA record VAR10V408 · QTS RIC 4 - PARKING LOT · QTS Datacenters, LP
- Permit filing, VDOT Land Development POD-2026-101451 · QTS RIC 4, Phase 1 · Townes Engineering
QTS RIC5 5 records
- Construction stormwater permit VAR10W432 · QTS RIC5 - Phase 1 · QTS Richmond V, LLC
- Permit filing, VDOT Land Development POD-2025-102108 · QTS RIC5 Temporary Parking Lot · Townes Engineering
- Permit filing, VDOT Land Development POD-2025-101899 · QTS RIC 5, Phase 1 · Townes
- Permit filing, DEQ VWPP 26-0426 · QTS RIC 5 · QTS Richmond V, LLC
- Public notice (wetlands and streams) NAO-2021-02695 · NAO-2021-02695 (QTS RIC 5, Henrico, Virginia)
DC Blox 1 record
- Construction stormwater permit VAR10W650 · DC Blox · DCB Richmond, LLC
IMDC RICH4 1 record
- Permit filing, DEQ VWPP WP4-26-2084 · IMDC RICH4 · Iron Mountain Data Centers, LLC
IMDC-RCH1 1 record
- Construction stormwater permit VAR10V888 · IMDC-RCH1 · Iron Mountain Data Centers LLC
Project Tropical Phase 2 - Data Center and Substation 1 record
- Construction stormwater permit VAR10W563 · Project Tropical Phase 2 - Data Center and Substation · DPR Construction, A General Partnership
QTS TRACT 9 CLEARING & GRADING 1 record
- Stormwater coverage, EPA record VAR10S699 · QTS TRACT 9 CLEARING & GRADING · QTS Datacenters, LP
BANK OF AMERICA - VILLA PARK DATA CENTER 1 record
- Air permit VA0000005108700566 · BANK OF AMERICA - VILLA PARK DATA CENTER
Iron Mountain Data Center 1 record
- Construction stormwater permit VAR10X856 · Iron Mountain Data Center · Virginia Electric and Power Company dba Dominion energy Virginia
County-wide records
Filings that name no site, state grants, and State Corporation Commission cases placed in this locality.
- Permit filing, VDOT Land Use 428:61308 · Iron Mountain Data Centers, LLC
Sources: DEQ's active construction stormwater list, EPA ECHO (water and air), Virginia Permit Transparency, Corps of Engineers Norfolk District public notices, State Corporation Commission dockets and VEDP incentive reports.
What to read
- Case study: Henrico County. Henrico County, Virginia spent fifteen years recruiting the data center industry and less than two years learning to govern it.
- Dataset: Henrico zoning reform: replication materials. The records behind a study of Henrico County's June 10, 2025 ordinance ending by-right approval of data centers.
- Report: Who Showed Up. A census of the organizations around data center siting in Virginia, 2014 to 2026.
- Book: Governing the Demand Shock. A comparison of how Virginia localities handled the arrival of data centers.
- Report: Chesterfield County case study. Chesterfield built its data-center strategy on a single number: the equipment tax rate set at $0.24/$100 in April 2019 — a deliberate undercut of Henrico's $0.40 and the lowest in Virginia. Google assembled roughly 1,640 acres, Chirisa committed $2 billion, and Commonwealth Fusion Systems selected Battery Brooke for the world's first grid-scale commercial fusion plant. The rate is locked for thirty years.
- Report: Two Systems, One Drought. Virginia's coastal aquifer is capacity-bound; its river system is drought-stressed. The Commonwealth is solving a problem in one by adding to the other, and the data-center buildout is arriving before that trade has been priced.
- Case study: Hanover County case study. The county's data center applications and the proffers offered in them.
- Report: Governing the Demand Shock. Virginia hosts the largest concentration of data centers in the world, and between roughly 2018 and 2026 the industry moved out of its Northern Virginia core into more than two dozen counties and independent cities.
- Case study: Prince William County case study. The county's data center decisions and the litigation over the Digital Gateway.
- Report: Orange County and Town of Orange case study. In the spring of 2026, two governments whose chambers sit blocks apart in the same small town regulated the same industry in the same season, with different instruments, on different timelines, and…
This page covers only what these sources contain. A locality with little here may still have data center activity.