Data Centers · By locality

Data centers in Fairfax County, Virginia

What the public record holds for this locality: how a data center gets approved, who is building, and what to read.

Approval Who is building What to read

How a data center gets approved here

By rightThe ordinance names the use and permits it by right.

A data center is allowed by right in I-5 and I-6 with no size cap, so it can be approved there without a rezoning, special exception or special use permit. In C-3 and C-4 it is by right up to 40,000 square feet and in I-2, I-3 and I-4 up to 80,000 square feet; going over the cap takes a special exception.

The rules come from an ordinance adopted Sept. 10, 2024. It added the I-4 cap, moved the PDC and PTC districts from permitted to special exception, and removed data centers from PRC. The county's adopted-amendment list runs through 112.2-2026-22, adopted Oct. 27, 2026 and effective Oct. 28, 2026. That amendment revises what rezoning and special exception applications for data centers must submit under Va. Code § 15.2-2209.5 and does not change the data center permissions or use standards. The list shows no change to those permissions or standards after Sept. 10, 2024.

State site assessment
Not triggered on at least one route. A data center can be approved here, in at least one district or set of parcels, with no rezoning, special exception or special use permit. Other routes in the same locality may require one.
The register entry this is drawn from, in the dataset's own shorthand
Position
BY RIGHT under size caps; SE to exceed
Where
C-3,C-4 (40k sf); I-2,I-3,I-4 (80k sf); I-5,I-6 (no cap)
What the ordinance calls the use
Data center
Provision
§4101.3 Tbl 4101.1; stds §4102.6.A
If the use is not listed
Not read
Adopted
Ord. 112.2-2024-8, 9-10-2024
Changes and status
PDC/PTC P->SE; I-4 cap added; PRC removed.
Route before the change
By right
Date of the change
2024-09-10
Still to read
Ord. 112.2-2024-8 of 9-10-2024 (not read; adoption known from the county adopted-amendment list)
Confidence in this reading
Medium. The position is established but one element is unresolved: the adopting ordinance, the scope, how current the text is, or the type of source.
Source as read
County adopted-amendment list through 112.2-2026-22 (2026 Code of Virginia Updates, adopted 10-27-2026, effective 10-28-2026), which revises data center submission requirements for rezoning (subsection 8101.2.E(13)) and special exception (subsection 8101.3.D(9)) applications under Va. Code § 15.2-2209.5 and does not amend the Table 4101.1 data center permissions or subsection 4102.6.A; no change to data center permissions or use standards after 9-10-2024. Read Nov. 4, 2026.

By right means the ordinance permits the use with no rezoning and no special permit. The state site assessment is the one in Va. Code § 15.2-2209.5. It applies to a new facility expected to need 100 megawatts or more when the approval is a rezoning, special exception or special use permit. This is a dated reading, current through Nov. 19, 2026. Ordinances change; read the cited provision before relying on it. From the dataset Virginia Data Center Entitlement Route Register, version 1.1, a record of how each of Virginia's 133 counties and independent cities, and five of its towns, approve a data center.

Who is building here: the public record

16 data center sites in the permit record for Fairfax County, grouped by site only where the records themselves link them, so one campus can appear as more than one site.

Data center sites found in the free state and federal records searched for Fairfax County, and utility filings placed in the same locality, current through Nov. 22, 2026. Records are grouped under one site only where their own text links them: a site code, street address, project or campus name, notice number or named company. A record with no such link is listed on its own. Names are as each record prints them. A site missing here may still be planned: these sources miss projects that have no permit yet and code names no record ties to a company. From the dataset Who Is Building It: Virginia Data Center Sites in the Public Permit Record, which has every record, the grouping rules and what the sources do not show.

County-wide records

Filings that name no site, state grants, and State Corporation Commission cases placed in this locality.

Sources: DEQ's active construction stormwater list, EPA ECHO (water and air), Virginia Permit Transparency, Corps of Engineers Norfolk District public notices, State Corporation Commission dockets and VEDP incentive reports.

What to read

This page covers only what these sources contain. A locality with little here may still have data center activity.