Virginia data center researcher: how each of 133 counties and cities approves one, and who pays for the grid. Independent, and updated as the record changes.
Data centers in Cumberland County, Virginia
What the public record holds for this locality: how a data center gets approved and what to read.
How a data center gets approved here
The ordinance does not name data centers. A use not provided for goes to the Planning Commission, and if the Board of Supervisors approves, the ordinance is amended to list it. The register treats that as a text amendment, so there is no route under the ordinance as it stands. The M-1 and M-2 lists are closed, with no catch-all category.
The county's zoning administrator was asked whether a data center would be handled under Sec. 74-7 and whether a conditional use permit is available for a use no district lists. The administrator wrote in an email of Nov. 17, 2026: "Technically, yes. If there is a use that is proposed, that is not listed as a permitted use, either by-right, or with a conditional use permit, an applicant may request the use under section 74-7." The register follows that statement. Sussex County administered nearly the same wording with a special use permit. No record of how Cumberland would handle a data center was found in Board minutes from July 8, 2025 to Oct. 20, 2026 or Planning Commission minutes from Jan. 12 to Aug. 31, 2026. The register rates this entry medium confidence.
- State site assessment
- Does not arise. No approval route currently exists.
The register entry this is drawn from, in the dataset's own shorthand
- Position
- TEXT AMENDMENT REQUIRED (use not named; a use listed neither by right nor by conditional use permit is requested under Sec. 74-7, Zoning Administrator, email of 11-17-2026)
- Where
- n/a
- What the ordinance calls the use
- (none)
- Provision
- Ch.74: no data center term in any of 25 articles; Sec. 74-7 'Uses not provided for'; M-1 Secs. 74-542, 74-543 and M-2 Sec. 74-582 are enumerated lists with no residual category
- If the use is not listed
- TEXT-AMENDMENT ROUTE (Sec. 74-7(a): unlisted use referred to PC; if approved by BOS 'this chapter shall be amended to list the use as a permitted use in that district')
- Adopted
- Sec. 74-7: Ord. No. 11-05, § c, 7-12-2011
- Changes and status
- No data center use or definition in Ch.74. Sec. 74-7 is nearly the same wording as the Prince George Co. and Sussex Co. provisions; Sussex Co. administered its wording with an SUP. No record of how Cumberland would process a data center found: BOS minutes 7-8-2025 to 10-20-2026 and PC minutes 1-12-2026 to 8-31-2026 carry no data center zoning item; PC agenda 10-19-2026: 'Potential Code Amendments – N/A'. BOS 10-20-2026 approved CUP 26-03 Cumberland Energy Center (3 aye, 1 nay, 1 absent): an electric generating facility, not a data center. Zoning Administrator, email of 11-17-2026, asked whether a data center would be handled under Sec. 74-7 and whether a conditional use permit is available for a use no district lists: 'Technically, yes. If there is a use that is proposed, that is not listed as a permitted use, either by-right, or with a conditional use permit, an applicant may request the use under section 74-7.' The row follows that statement (codebook rule 5).
- Confidence in this reading
- Medium. The position is established but one element is unresolved: the adopting ordinance, the scope, how current the text is, or the type of source.
- Source as read
- Municode version Oct 5, 2026; Supplement History Table through Supp. No. 29 (latest ordinance 7-8-2025); no Ch.74 data center amendment found in BOS minutes 7-8-2025 to 10-20-2026. Read Nov. 14, 2026.
By right means the ordinance permits the use with no rezoning and no special permit. The state site assessment is the one in Va. Code § 15.2-2209.5. It applies to a new facility expected to need 100 megawatts or more when the approval is a rezoning, special exception or special use permit. This is a dated reading, current through Nov. 19, 2026. Ordinances change; read the cited provision before relying on it. From the dataset Virginia Data Center Entitlement Route Register, version 1.1, a record of how each of Virginia's 133 counties and independent cities, and five of its towns, approve a data center.
What to read
- Report: Built for Someone Else. An account of the four ways generation is built to serve Virginia data centers and the review each one gets.
This page covers only what these sources contain. A locality with little here may still have data center activity.