Data Centers · By locality

Data centers in the City of Chesapeake, Virginia

What the public record holds for this locality: how a data center gets approved and what to read.

Approval What to read

How a data center gets approved here

Permit requiredA discretionary permit is required: a conditional or special use permit, a special exception or a provisional use permit.

A data center needs a conditional use permit and is allowed only in M-1 and M-2. City Council adopted the change on Aug. 18, 2026 by a 9-0 roll call, according to the Council minutes. Before that, according to the city, data centers could be built by right in O&I, M-1, M-2, B-1 and B-2.

A resolution of July 21, 2026 pauses hearings on data center applications for eight months. Council has asked the Attorney General whether it may ban data centers outright. The use-table cells did not extract cleanly, so the districts rest on the ordinance title and the city's own timeline.

State site assessment
Triggered. Approval here generates a rezoning, special exception or special use permit.
The register entry this is drawn from, in the dataset's own shorthand
Position
CONDITIONAL USE PERMIT
Where
M-1, M-2
What the ordinance calls the use
Data Centers (use table); Data Center (definition)
Provision
App. A (Zoning) Sec. 8-602 industrial use table (Data Centers = C, condition 41) and Sec. 13-3400 (special requirements; 13-3400(C)(1) CUP under Art. 17; HEUF site assessment and utility form; public water and sewer required, private groundwater prohibited); SIC 737 rows in Secs. 7-602 and 9-502 now read 'except Data Centers'
If the use is not listed
not read
Adopted
PLN-TXT-2026-001 (#26-O-081), version dated August 18, 2026 (3rd option), ADOPTED by Council 8-18-2026, 9-0 roll call (Council minutes of 8-18-2026); the adopted ordinance carries the clerk signature block
Changes and status
City: before 8-18-2026 data centers could be built by right in O&I, M-1, M-2, B-1, B-2. Adopted ordinance makes data centers a conditional use in only M-1 and M-2. 7-21-2026 resolution pauses data center application hearings for eight months; the pause suspends hearings and creates no approval route. Council has asked the Attorney General whether it may ban data centers outright. Industrial use-table cells did not extract cleanly; districts rest on the ordinance title and the City's own timeline board.
Route before the change
by right (form not established)
Date of the change
2026-08-18
Confidence in this reading
High. Ordinance text read directly, citation verified, the position unambiguous.
Source as read
n/a (adopting ordinance read directly). Read Nov. 4, 2026.

By right means the ordinance permits the use with no rezoning and no special permit. The state site assessment is the one in Va. Code § 15.2-2209.5. It applies to a new facility expected to need 100 megawatts or more when the approval is a rezoning, special exception or special use permit. This is a dated reading, current through Nov. 19, 2026. Ordinances change; read the cited provision before relying on it. From the dataset Virginia Data Center Entitlement Route Register, version 1.1, a record of how each of Virginia's 133 counties and independent cities, and five of its towns, approve a data center.

What to read

This page covers only what these sources contain. A locality with little here may still have data center activity.