Virginia data center researcher: how each of 133 counties and cities approves one, and who pays for the grid. Independent, and updated as the record changes.
Data centers in the City of Charlottesville, Virginia
What the public record holds for this locality: how a data center gets approved, who is building, and what to read.
Approval Who is building What to read
How a data center gets approved here
A data center is allowed by right in IX-5, IX-8 and CM. It is also allowed by right in CX-3, CX-5, CX-8, NX-3, NX-5, NX-8, NX-10 and DX, limited to 50% of the floor area on a lot and set 30 feet back from street facades. It is not allowed in R-A, RN-A, R-B, R-C, RX-3, RX-5 or CV. The city's administrator decides development review. In historic and entrance corridor districts new construction also needs a certificate of appropriateness, which does not trigger the state site assessment.
The development code was adopted Dec. 18, 2023 and amended Feb. 17, 2026 by a 4-1 Council vote, effective March 23, 2026. The data center provisions are the same in both texts. In a lawsuit, White v. Charlottesville City Council (Case No. CL24-25), Council voted 5-0 on Oct. 20, 2025 to authorize a settlement in exchange for the plaintiffs' agreement to file a motion to non-suit. The nonsuit order was not seen, and the agreement as presented lets the claimants re-file if the city does not perform within one year.
- State site assessment
- Not triggered on at least one route. A data center can be approved here, in at least one district or set of parcels, with no rezoning, special exception or special use permit. Other routes in the same locality may require one.
The register entry this is drawn from, in the dataset's own shorthand
- Position
- BY RIGHT
- Where
- IX-5, IX-8, CM (P, no use standard); CX-3, CX-5, CX-8, NX-3, NX-5, NX-8, NX-10, DX (P*: max 50% of floor area on a lot, 30 ft back from street facades); not allowed in R-A, RN-A, R-B, R-C, RX-3, RX-5, CV
- What the ordinance calls the use
- Data center
- Provision
- Ch. 34 Development Code: use table Div. 3.2 (printed p. 3-7); def Div. 3.3 (p. 3-18); stds Sec. 3.4.5.A.2 (p. 3-33); unlisted Sec. 3.3.1.B-C; Development Review Sec. 5.2.9; Certificates of Appropriateness Secs. 5.2.6 to 5.2.8
- If the use is not listed
- ADMIN DETERMINATION, else not allowed (Sec. 3.3.1.B-C: Administrator decides similarity; if not similar 'the use is not allowed'); use named, rule not reached
- Adopted
- Development Code adopted 12-18-2023, effective 2-19-2024 (City zoning page). Amended and re-enacted 2-17-2026 by 'ORDINANCE AMENDING AND RE-ENACTING CHAPTER 34 (CHARLOTTESVILLE DEVELOPMENT CODE) ...' (Tier 1 and Tier 2 text amendments; Council 4-1; effective 3-23-2026). Ordinance numbers not printed in the minutes or packet read
- Changes and status
- No change found: Data center row, definition, standards and Sec. 3.3.1 are identical in the as-adopted (12-18-2023) and amended (2-17-2026) City texts; the 2-17-2026 ordinance amends Sec. 3.4.5.A.1.a, A.3.c and A.4.a and Sec. 5.2.9, not item A.2 (Data Center) or the use table row. Council and Planning Commission record 1-1-2025 to 11-14-2026 (meeting portal full-text search for 'data center'; hits in files from 20 meetings; 19 files from 17 of those meetings read): no data center amendment, moratorium, directive or application; the mentions are a state legislative priority, the University's Fontaine research data center, Albemarle County's work and the City's IT room. Litigation, White v. Charlottesville City Council (Case No. CL24-25): default judgment of 6-30-2025 set aside by order of 9-2-2025; Council on 10-20-2025 (5-0) authorized a settlement in exchange for the plaintiffs' agreement 'to file a motion to non-suit'; Council amended and re-enacted Ch. 34 on 2-17-2026. Nonsuit order and the City's VDOT submission not seen; the agreement as presented lets the claimants re-file if the City does not perform within one year. No acreage, total square footage or MW threshold in the Data Center standards (Sec. 3.4.5.A.2); 'megawatt' 0 hits in the 438-page text. Development Review decided by the Administrator (Sec. 5.2.9.D). In ADC and HC districts and for individually protected properties new construction also needs a Certificate of Appropriateness from the Board of Architectural Review (Sec. 5.2.7); in the Entrance Corridor district, from the Administrator or, on referral, on request of two members or on appeal, the Entrance Corridor Review Board, which is the Planning Commission (Sec. 5.2.8). A Certificate of Appropriateness is not a rezoning, special exception or SUP
- Still to read
- nonsuit order in White v. Charlottesville City Council, Case No. CL24-25 (not seen)
- Confidence in this reading
- High. Ordinance text read directly, citation verified, the position unambiguous.
- Source as read
- City PDF 'Charlottesville-Development-Code-PDF-Updated-March-23-2026', cover 'ADOPTED | DECEMBER 18, 2023 ... AMENDED | FEBRUARY 17, 2026' (the 2-17-2026 ordinance took effect 3-23-2026); Municode (Supp. No. 64, Update 2, codified through Ordinance No. O-26-137, 9-21-2026) carries only a pointer for Ch. 34. Read Nov. 14, 2026.
By right means the ordinance permits the use with no rezoning and no special permit. The state site assessment is the one in Va. Code § 15.2-2209.5. It applies to a new facility expected to need 100 megawatts or more when the approval is a rezoning, special exception or special use permit. This is a dated reading, current through Nov. 19, 2026. Ordinances change; read the cited provision before relying on it. From the dataset Virginia Data Center Entitlement Route Register, version 1.1, a record of how each of Virginia's 133 counties and independent cities, and five of its towns, approve a data center.
Who is building here: the public record
No data center site appears for the City of Charlottesville in the free state and federal records searched. The records below are placed in this locality but name no data center site, current through Nov. 22, 2026. Records are grouped under one site only where their own text links them: a site code, street address, project or campus name, notice number or named company. A record with no such link is listed on its own. Names are as each record prints them. A site missing here may still be planned: these sources miss projects that have no permit yet and code names no record ties to a company. From the dataset Who Is Building It: Virginia Data Center Sites in the Public Permit Record, which has every record, the grouping rules and what the sources do not show.
City-wide records
Filings that name no site, state grants, and State Corporation Commission cases placed in this locality.
- SCC case PUR-2026-00050 · Virginia Electric and Power Company - For Approval and Certification of Electric Transmission Facilities: Charlottesville-Gordonsville 230 kV Rebuild Project · VIRGINIA ELECTRIC AND POWER CO
- SCC case PUR-2025-00189 · Virginia Electric and Power Company - For an approval and certification of electric transmission facilities: Charlottesville-Dooms Lines 233 and 291 rebuild · VIRGINIA ELECTRIC AND POWER CO
Sources: DEQ's active construction stormwater list, EPA ECHO (water and air), Virginia Permit Transparency, Corps of Engineers Norfolk District public notices, State Corporation Commission dockets and VEDP incentive reports.
What to read
- Report: Orange County and Town of Orange case study. In the spring of 2026, two governments whose chambers sit blocks apart in the same small town regulated the same industry in the same season, with different instruments, on different timelines, and…
This page covers only what these sources contain. A locality with little here may still have data center activity.