Who Is Building It: A Report on Virginia Data Center Sites in the Public Permit Record
Reads the state and federal permit record for every Virginia county and independent city and finds 247 data center sites in it, in 26 counties and cities, 168 of them in Northern Virginia. Of the 131 active construction stormwater permits on those sites, 50 name a construction company as the operator, so a search of the state's list for the company that will run a campus misses more than a third of them. The count is not a census of data centers.
A data center leaves a record well before it runs: a state stormwater permit for the grading, an air permit for its generators, in some cases a Corps of Engineers notice for wetland fill, and a utility case for the line that will serve it. This report reads those records for every Virginia county and independent city, from the companion dataset current through November 22, 2026.
It finds 247 data center sites in the permit record, in 26 counties and cities, 168 of them in Northern Virginia. Of the 131 active construction stormwater permits on those sites in DEQ's list, 50 name a construction company as the operator and 60 a data center company or affiliate, so a reader who searches the state's list for the company that will run a campus misses more than a third of the permits. EPA records the holder when a coverage was issued; for eight permits issued in 2019, that holder differs from the operator DEQ lists today, and no source tested gives the date of the change. As of November 22, 2026, no source tested showed the acreage to be disturbed as stated on a stormwater registration statement.
The count is not a census of data centers. It does not measure power or water, and it does not rank localities.
Current through: November 22, 2026. Last full source audit: November 22, 2026.
Updates. The author checks every agency source monthly. When a check finds new or changed records, a new version is deposited with a new "Current through" date, no more than once a month. When it finds none, the "Current through" date moves forward in the Zenodo record's notes and the files keep the date of their own build. A full source audit, re-pulling every agency source in full, runs at least once a quarter. This report is revised with each quarterly audit, or sooner when a finding it states changes.
Companion dataset: Who Is Building It: Virginia Data Center Sites in the Public Permit Record (dataset) , https://doi.org/10.5281/zenodo.24447222.