Virginia data center researcher: how each of 133 counties and cities approves one, and who pays for the grid. Independent, and updated as the record changes.

Portrait of Tommy N. Turner
Data Center LedgerFilings, minutes, orders and transcripts, logged as they are readLatest, Nov. 25: new report version →

All works · Georgia and Tennessee

What Georgia Is Spending, What Georgia Is Getting: A Statewide Data Center Report

Plain-English summary

This statewide report weighs what data centers cost Georgia against what they return. Its lead finding, from a 2025 evaluation done for the state: the sales-tax break for data center equipment loses the state money in every year the study modeled, even counting the taxes the activity brings in.

The study's estimate implies about 70 percent of the investment would have come anyway. The legislature passed a pause on new exemptions in 2024; the governor vetoed it. The break runs until 2033.

That left the Public Service Commission, Georgia Power's regulator, making the state's most consequential data center policy. A 2025 rule bills the utility's largest customers for the power capacity their demand requires.

With no statewide siting law, local governments decide where data centers go. By June 2026, 32 counties and 21 cities had adopted, drafted or were drafting data center ordinances or moratoria.

Summary of version 1.1, September 2026. The full report carries the record behind each point.

Full abstract

Georgia built the second-largest data center market in the United States without ever deciding to. No statewide siting law governs where the facilities go; no statewide assessment weighs their water or power draw; the one bill that would have paused the central subsidy passed both chambers in 2024 and was vetoed. This report assembles the fiscal, grid, and local records into a single account of what the build-out costs Georgia and what it returns. The sales-and-use tax exemption (O.C.G.A. § 48-8-3(68.1)) waived an estimated $450.6 million in 2024, rising toward $866.7 million by 2030, and the state's own Carl Vinson Institute evaluation found the program's net fiscal impact negative every year and revised the share of activity actually caused by the exemption from 90 percent down to 30 percent. Georgia Power's projected new-generation need rose from about 400 MW (2022) to 8,500 MW (2025), overwhelmingly attributed to data centers; the Public Service Commission certified 9,885 MW in December 2025, about 80 percent tied to data center demand and most of it gas, while residential customers absorbed six rate increases totaling about $43 a month. With the state silent, local government became the siting authority by default: by June 2026, 32 counties and 21 cities had adopted or drafted data center ordinances or moratoria. The volume tests the industry's case on its own terms and sets Georgia against Virginia and the national field. Independent and built entirely from public sources; every figure traced to a primary document.

Cite this work

BibTeX
@misc{turner2026whatgeorgiaisspendingwha,
  author = {Turner, Tommy N.},
  title = {What Georgia Is Spending, What Georgia Is Getting: A Statewide Data Center Report},
  year = {2026},
  publisher = {Zenodo},
  version = {1.1},
  doi = {10.5281/zenodo.20717372},
  url = {https://doi.org/10.5281/zenodo.20717372}
}
APA
Turner, T. N. (2026). What Georgia Is Spending, What Georgia Is Getting: A Statewide Data Center Report (Version 1.1). Zenodo. https://doi.org/10.5281/zenodo.20717372
Chicago
Turner, Tommy N. 2026. “What Georgia Is Spending, What Georgia Is Getting: A Statewide Data Center Report.” Version 1.1. Zenodo. https://doi.org/10.5281/zenodo.20717372.