A data center needs a special use permit and is allowed only in the EO, IL and IG districts. Because approval takes a special use permit, it triggers the state site assessment. The Board of Supervisors adopted the use on June 17, 2025, 4-0 with one member absent (Ord. No. 25-16(R)). Before that the county had no regulations for a data center, according to staff in the Board minutes of that date.
On May 19, 2026 the Board amended the standards 5-0 (Ord. No. 26-12). The height limit rose from 35 to 75 feet, the 200-foot setback from all lines became 100 feet from non-residential lines, and a 65 dBC noise limit was added to the 55 dBA limit. Any increase in electricity or water use now needs Board approval after a public hearing. The districts and the permit route did not change. The standards set no megawatt, square-footage or acreage cap; the applicant's utility letter states energy use and the Board holds it to that figure.
- State site assessment
- Triggered. Approval here generates a rezoning, special exception or special use permit.
The register entry this is drawn from, in the dataset's own shorthand
- Position
- SPECIAL USE PERMIT
- Where
- EO, IL, IG ('S'); row blank in RC, RR, R33, R20, R13, R7, RMF, NB, LB, GB, WCI
- What the ordinance calls the use
- Data Center
- Provision
- Ch. 24.1 Sec. 24.1-306 Table of land uses, Category 15, No. 15; stds Sec. 24.1-489.1; def Sec. 24.1-104
- If the use is not listed
- ADMIN DETERMINATION (Sec. 24.1-302: an unlisted use 'shall not be permitted unless the zoning administrator shall determine whether a materially similar use exists'; if none, referred to the planning commission for a text amendment); use named, rule not reached
- Adopted
- Ord. No. 25-16(R) (Application ZT-200-24), 6-17-2025, 4-0 (one member absent); standards amended by Ord. No. 26-12 (ZT-216-25), 5-19-2026, 5-0 (OCR of scanned Board minutes)
- Changes and status
- Before 6-17-2025 the use was not addressed (staff, Board minutes 6-17-2025: no regulations for a data center). Ord. No. 26-12 changed Sec. 24.1-489.1 only: height 35 ft to 75 ft; setback 200 ft from all lines to 100 ft from non-residential lines (500 ft kept, now from residential property lines instead of residential dwellings); 65 dBC limit added to 55 dBA; any increase in electricity or water use needs Board approval after a public hearing (was a 25 percent allowance); districts and SUP route unchanged. No megawatt, square-footage or acreage cap or trigger in Sec. 24.1-489.1 (read in full): the applicant's utility letter states energy use and the Board holds it to that figure. Public water required; wells prohibited. Board and Planning Commission agenda sheets 5-19 to 11-17-2026 that have a text layer (13): no later data center item; 4 agenda sheets, all Board minutes and the Planning Commission minutes of 8-12 and 10-14-2026 returned no text and were not read. Agendas 6-18-2025 to 5-18-2026 not read
- Route before the change
- not addressed
- Date of the change
- 2025-06-17
- Confidence in this reading
- High. Ordinance text read directly, citation verified, the position unambiguous.
- Source as read
- Municode version Jun 15, 2026; adopted-not-codified list through Ord. No. 26-23 (10-20-2026), none on data centers. Read Nov. 14, 2026.
By right means the ordinance permits the use with no rezoning and no special permit. The state site assessment is the one in Va. Code § 15.2-2209.5. It applies to a new facility expected to need 100 megawatts or more when the approval is a rezoning, special exception or special use permit. This is a dated reading, current through Nov. 19, 2026. Ordinances change; read the cited provision before relying on it. From the dataset Virginia Data Center Entitlement Route Register, version 1.1, a record of how each of Virginia's 133 counties and independent cities, and five of its towns, approve a data center.