Tommy N. Turner

Virginia data center researcher: how each of 133 counties and cities approves one, and who pays for the grid. Independent, and updated as the record changes.

Portrait of Tommy N. Turner
Data Center LedgerFilings, minutes, orders and transcripts, logged as they are readLatest, Nov. 25: new report version →

Data Centers · By locality

Data centers in Wythe County, Virginia

What the public record holds for this locality: how a data center gets approved, what has been filed and decided, and what to read.

Approval Coming up What to read

How a data center gets approved here

No zoning ordinanceThere is no general zoning ordinance in the area this row covers.

Wythe County does not currently have a zoning ordinance, according to the county's FAQ, so the unincorporated county has no zoning districts and no county use regulation. Progress Park is governed by private covenants of the Joint Industrial Development Authority. A Fluidstack site plan there was cleared under those covenants on July 28, 2026 by a 5-1 vote.

A land use ordinance is pending. Draft 4.02, dated August 2026, lists "Call center and/or data processing facility," undefined, as a special use permit use in Commercial and Industrial districts. A search of the draft's full text found no "data center" term, and the draft preserves vested rights. The Planning Commission held a public hearing Oct. 26, 2026 and reviewed the draft Nov. 2, 2026. A Board hearing is tentatively set for Dec. 3, 2026.

The Board's Nov. 12, 2026 agenda listed scheduling a public hearing on the ordinance, with discussion. The outcome was not read, and the minutes had not been posted as of Nov. 15, 2026. The same packet carries a draft new Sec. 4-1.3, "Transitional Protection for Previously Permitted Projects." Under it, a project holding a county land-disturbance, erosion and sediment or building permit, a DEQ construction stormwater authorization or a mining permit issued before the effective date would need no zoning permit, rezoning, special use permit or special exception within its protected scope. It is a draft and has not been adopted.

State site assessment
Not triggered on at least one route. A data center can be approved here, in at least one district or set of parcels, with no rezoning, special exception or special use permit. Other routes in the same locality may require one.
The register entry this is drawn from, in the dataset's own shorthand
Position
NO ZONING ORDINANCE (no county use regulation)
Where
n/a: unincorporated county has no zoning districts; Progress Park governed by private covenants of the Joint IDA
What the ordinance calls the use
(none)
Provision
County Code Ch. 42 ZONING '(RESERVED)'; county FAQ: 'Wythe County does not currently have a zoning ordinance.' Subdivision Ch. 32, E&S/stormwater Ch. 16 and building Ch. 8 carry no rezoning, special exception or SUP
If the use is not listed
n/a (no zoning ordinance). PENDING draft § 4.20.1: 'Uses not contemplated by this ordinance shall be treated as special exceptions upon application.'
Adopted
No zoning ordinance in force (county FAQ: 'Wythe County does not currently have a zoning ordinance.'). County Code adopted 6-9-2026 (6-0, eff. 7-1-2026), Ch. 42 reserved
Changes and status
PENDING: Land Use Classification Ordinance Draft 4.02 (Aug. 2026) lists 'Call center and/or data processing facility' (undefined) as SUP in Commercial (§ 3-4.2(e)) and Industrial (§ 3-5.2(c)); no 'data center' term found in the draft (Draft 4.02 full text searched). PC public hearing held 10-26-2026; PC review 11-2-2026 (minutes not posted); BOS hearing tentatively 12-3-2026. Draft § 1-4.4 preserves vested rights. Fluidstack (Progress Park) site plan cleared under covenants 7-28-2026 (5-1). BOS agenda 11-12-2026, Old Business: 'Land Use Classification (Zoning) 1. Schedule Public Hearing 2. Discussion'; outcome not read (minutes not posted on 11-15-2026). The same packet carries a draft new Sec. 4-1.3, 'Transitional Protection for Previously Permitted Projects': a project holding a county land-disturbance, erosion and sediment or building permit, a DEQ construction stormwater authorization or a mining permit issued before the effective date would need no zoning permit, rezoning, special use permit or special exception within its protected scope; draft, not adopted
Still to read
PC minutes of 11-2-2026 (not posted on 11-4-2026)
Confidence in this reading
Medium. The position is established but one element is unresolved: the adopting ordinance, the scope, how current the text is, or the type of source.
Source as read
Municode: 'codified through Ordinance No. 2025-5, adopted September 9, 2025'. Read Nov. 4, 2026.

By right means the ordinance permits the use with no rezoning and no special permit. The state site assessment is the one in Va. Code § 15.2-2209.5. It applies to a new facility expected to need 100 megawatts or more when the approval is a rezoning, special exception or special use permit. This is a dated reading, current through Nov. 19, 2026. Ordinances change; read the cited provision before relying on it. From the dataset Virginia Data Center Entitlement Route Register, version 1.1, a record of how each of Virginia's 133 counties and independent cities, and five of its towns, approve a data center.

Coming up

What to read

This page covers only what these sources contain. A locality with little here may still have data center activity.