Virginia data center researcher: how each of 133 counties and cities approves one, and who pays for the grid. Independent, and updated as the record changes.
Data centers in Wise County, Virginia
What the public record holds for this locality: how a data center gets approved and what to read.
How a data center gets approved here
"Data processing and computer centers" are allowed by right in M-1 and M-2, and the county's zoning administrator says the same language applies in PD-BT. The administrator wrote in an email of Nov. 17, 2026: "The board amended the zoning ordinance to include M-1 and M-2 District for Data centers. The PD-BT district already had that language in it." The reply cites Section 4.11.3(5), which was not read, and does not give the ordinance number or date. The amendment found in the Board minutes is Ord. 1-2025, adopted June 12, 2025. The approved Planning Commission minutes of the June 12, 2025 joint hearing describe it as adding "data processing, computer centers" among office uses in M-1 and M-2. The register reads approval here as needing no rezoning, special exception or special use permit, and rates this entry medium confidence.
The ordinance prohibits unlisted uses by default, but this use is expressly listed. The text of Ord. 1-2025 is on file in the County Administrator's Office, is not posted, and was not read. Municode was not read for this row; it is reported to omit the M-1 and M-2 data center use, which was not checked.
Cardinal News quoted Brian Falin on Feb. 25, 2026 as saying that a project in the technology park would not require local rezoning because the park is already zoned for industrial use.
- State site assessment
- Not triggered on at least one route. A data center can be approved here, in at least one district or set of parcels, with no rezoning, special exception or special use permit. Other routes in the same locality may require one.
The register entry this is drawn from, in the dataset's own shorthand
- Position
- BY RIGHT in M-1 and M-2 ('data processing and computer centers'), which the Zoning Administrator says the Board amended the ordinance to include for data centers, and in PD-BT, which he says 'already had that language in it' (Sec. 4.11.3(5), not read) (email of 11-17-2026). The approved Planning Commission minutes of the 6-12-2025 joint hearing describe the amendment as adding 'data processing, computer centers' among office uses in M-1 and M-2
- Where
- M-1, M-2; PD-BT (per Zoning Administrator, Sec. 4.11.3(5), not read)
- What the ordinance calls the use
- data processing and computer centers
- Provision
- §4-6.2(31); §4-7.2(20); §4.11.3(5) (cited by the Zoning Administrator, not read)
- If the use is not listed
- DEFAULT PROHIBITION (Sec. 1-4.3); use expressly listed, rule not reached
- Adopted
- Ord. 1-2025, 6-12-2025
- Changes and status
- Cardinal News 2-25-2026, quoting Brian Falin: "Because the technology park already is zoned for industrial use, the project will not require local rezoning." Sec. 1-4.3 default prohibition, but the use is expressly listed. Municode not read for this row (reported to omit the M-1/M-2 data center use; not checked). Zoning Administrator, email of 11-17-2026: 'The board amended the zoning ordinance to include M-1 and M-2 District for Data centers. The PD-BT district already had that language in it. Section 4.11.3 (5)'. The reply does not give the ordinance number or date; Ord. 1-2025 of 6-12-2025 is the amendment found in the Board minutes
- Route before the change
- By right under a general use
- Date of the change
- 2025-06-12
- Still to read
- Ord. 1-2025 of 6-12-2025 (text on file in the County Administrator's Office; not posted) and Sec. 4.11.3(5) (not read)
- Confidence in this reading
- Medium. The position is established but one element is unresolved: the adopting ordinance, the scope, how current the text is, or the type of source.
- Source as read
- Not determinable: Ord. 1-2025 text "on file in the County Administrator's Office" (BOS minutes 6-12-2025); Municode not read. Read Nov. 4, 2026.
By right means the ordinance permits the use with no rezoning and no special permit. The state site assessment is the one in Va. Code § 15.2-2209.5. It applies to a new facility expected to need 100 megawatts or more when the approval is a rezoning, special exception or special use permit. This is a dated reading, current through Nov. 19, 2026. Ordinances change; read the cited provision before relying on it. From the dataset Virginia Data Center Entitlement Route Register, version 1.1, a record of how each of Virginia's 133 counties and independent cities, and five of its towns, approve a data center.
What to read
- Report: Who Showed Up. A census of the organizations around data center siting in Virginia, 2014 to 2026.
This page covers only what these sources contain. A locality with little here may still have data center activity.