Virginia data center researcher: how each of 133 counties and cities approves one, and who pays for the grid. Independent, and updated as the record changes.
Data centers in the Town of Christiansburg, Virginia
What the public record holds for this locality: how a data center gets approved.
How a data center gets approved here
A data center needs a conditional use permit in the I-2 General Industrial district. The I-1 and I-2 articles and Article I were searched for the use; the other district articles were not opened. It was by right in I-2 until Town Council adopted Ord. 2026-3 on Sept. 22, 2026, effective on adoption. The Council public hearing was Sept. 8, 2026, and the Planning Commission heard and recommended it on Aug. 17, 2026.
The online code still shows the old by-right line. The signed ordinance is a scan read by OCR; it shows all six members voting aye.
- State site assessment
- Triggered. Approval here generates a rezoning, special exception or special use permit.
The register entry this is drawn from, in the dataset's own shorthand
- Position
- CONDITIONAL USE PERMIT
- Where
- I-2 General Industrial only (I-1, I-2 and Art. I searched; other district articles not opened)
- What the ordinance calls the use
- Data center
- Provision
- Ch.42 Sec.42-397(b)(14) as amended by Ord. 2026-3; def. Ch.42 Art.I: "Data center means a facility where computer and network server equipment is located for the purpose of data and application storage, access, management, and distribution."
- If the use is not listed
- DEFAULT PROHIBITION with PC classification referral or text amendment (Sec. 42-2) - use expressly listed, rule not reached
- Adopted
- Ord. 2026-3, adopted 9-22-2026 per signed ordinance (Council public hearing 9-8-2026; PC hearing and recommendation 8-17-2026); effective on adoption
- Changes and status
- By right in I-2 (former Sec.42-397(a)(16) "Data center") -> CUP in I-2 (Sec.42-397(b)(14)). Municode still shows the by-right line (not yet codified). Cardinal News reports a 6-0 vote at the 9-8-2026 meeting; the signed ordinance recites 9-8 as the hearing and 9-22-2026 as adoption; tally 6-0 (all six members AYE) per OCR word positions on the signed ordinance, 9-22-2026. Signed ordinance is a scan read by OCR
- Route before the change
- By right
- Date of the change
- 2026-09-22
- Still to read
- Council minutes of 9-22-2026 (not retrieved)
- Confidence in this reading
- Medium. The position is established but one element is unresolved: the adopting ordinance, the scope, how current the text is, or the type of source.
- Source as read
- Municode does not yet carry Ord. 2026-3 (still shows by right); adopted ordinance on Town site governs. Read Nov. 4, 2026.
By right means the ordinance permits the use with no rezoning and no special permit. The state site assessment is the one in Va. Code § 15.2-2209.5. It applies to a new facility expected to need 100 megawatts or more when the approval is a rezoning, special exception or special use permit. This is a dated reading, current through Nov. 19, 2026. Ordinances change; read the cited provision before relying on it. From the dataset Virginia Data Center Entitlement Route Register, version 1.1, a record of how each of Virginia's 133 counties and independent cities, and five of its towns, approve a data center.
This page covers only what these sources contain. A locality with little here may still have data center activity.