Tommy N. Turner

Virginia data center researcher: how each of 133 counties and cities approves one, and who pays for the grid. Independent, and updated as the record changes.

Portrait of Tommy N. Turner
Data Center LedgerFilings, minutes, orders and transcripts, logged as they are readLatest, Nov. 25: new report version →

Data Centers · By locality

Data centers in Smyth County, Virginia

What the public record holds for this locality: how a data center gets approved.

Approval

How a data center gets approved here

Permit requiredA discretionary permit is required: a conditional or special use permit, a special exception or a provisional use permit.

A data center needs a special use permit in the Industrial, Commercial, Agricultural and Agricultural/Rural districts. The Board adopted the data center section on Sept. 10, 2026 with 4 ayes, 0 nays, 2 abstaining and 1 absent.

On July 9, 2026 the Board had repealed, 6-0, an older by-right use called "Call center and/or data processing facility," defined as office space for telephone calls and computer data records.

The online code, in a version dated Aug. 28, 2026, still shows the old by-right line and neither 2026 action. The adopted text as amended by the Planning Commission on Aug. 27, 2026 was not read; the district list rests on the packet draft.

State site assessment
Triggered. Approval here generates a rezoning, special exception or special use permit.
The register entry this is drawn from, in the dataset's own shorthand
Position
SPECIAL USE PERMIT
Where
Industrial 3-5.2(hh); Commercial 3-4.2(oo); Agricultural 3-1.2(bbb); Agricultural/Rural 3-2.2(iii)
What the ordinance calls the use
Data Center
Provision
App. A Zoning § 4-19 Data Centers; district SUP entries per Sept. 10, 2026 packet Att. 7; def. Art. X 'Data Center'
If the use is not listed
DEFAULT PROHIBITION by closed lists ('Uses permitted by right are limited to one or more of the following uses', e.g. § 3-5.1); County Attorney 7-9-2026: repeal leaves no pathway 'unless the zoning ordinance is amended'
Adopted
BOS 9-10-2026 adopted § 4-19 (4 ayes, 0 nays, 2 abstaining, 1 absent); BOS 7-9-2026 repealed 'data processing facility' from §§ 3-4(z), 3-5(u), 4-10.6 and Art. X (6-0, 1 absent)
Changes and status
Before 7-9-2026 'Call center and/or data processing facility' was listed BY RIGHT in C (§ 3-4.1(z)) and I (§ 3-5.1(u)), defined as office space for telephone calls and computer data records (BPO-type). Municode (version Aug. 28, 2026) still shows that by-right line and neither 2026 action: codifier lag. Adopted text as amended by PC 8-27-2026 not read; district entries rest on the packet draft
Route before the change
not established
Date of the change
2026-07-09
Still to read
Adopted Sec. 4-19 text as amended by the PC on 8-27-2026 (not read)
Confidence in this reading
Medium. The position is established but one element is unresolved: the adopting ordinance, the scope, how current the text is, or the type of source.
Source as read
Municode 'VERSION: AUG 28, 2026 (CURRENT)'; does not carry the 7-9-2026 or 9-10-2026 actions. Read Nov. 4, 2026.

By right means the ordinance permits the use with no rezoning and no special permit. The state site assessment is the one in Va. Code § 15.2-2209.5. It applies to a new facility expected to need 100 megawatts or more when the approval is a rezoning, special exception or special use permit. This is a dated reading, current through Nov. 19, 2026. Ordinances change; read the cited provision before relying on it. From the dataset Virginia Data Center Entitlement Route Register, version 1.1, a record of how each of Virginia's 133 counties and independent cities, and five of its towns, approve a data center.

This page covers only what these sources contain. A locality with little here may still have data center activity.