How a data center gets approved here
A data center needs a special use permit from the Board of Supervisors, after Planning Commission review and a public hearing, in the M-1 General Industrial and M-2 Limited Industrial districts. Standards include noise limits at the closest nonparticipating property line and a 200-foot setback from residential, agriculture or conservation lines. Because approval takes a special use permit, it triggers the state site assessment. Staff said less than one percent of county land is zoned industrial, and a data center elsewhere would first need a rezoning.
The Board adopted the ordinance on June 23, 2026 with six ayes on a roll call (Zoning Text Amendment 26-06-01). Before that, an M-2 by-right line for "Data processing and computer service" carried into M-1, and county staff and counsel said data centers could be interpreted under it. Planning Commission minutes of March 5, 2026 record the answer "yes, by right" to whether a data center could be built on industrial land.
A further amendment, Zoning Text Amendment 26-11-01, is pending. It covers data center, energy and decommissioning revisions and would require on-site power generation to have its own special use permit authorization. It was on the Nov. 5, 2026 joint hearing agenda, and the outcome is not in any record read.
- State site assessment
- Triggered. Approval here generates a rezoning, special exception or special use permit.
The register entry this is drawn from, in the dataset's own shorthand
- Position
- SPECIAL USE PERMIT (Board of Supervisors, after Planning Commission review and public hearing)
- Where
- M-1 General Industrial and M-2 Limited Industrial, by special use permit. Use lists of C-1, RR-C, A-1, RR-A, R-1, R-2, R-3, R-4, B-1 and B-2 read one by one in the codified text (eCode360, Code 2025-12-09): none lists it, and the only district sections the 6-23-2026 ordinance amends are §§ 165-18 and 165-19 (it also amends § 165-4 and adds Art. XXIII); overlay text (Art. XVIII) term-searched only
- What the ordinance calls the use
- Data Center(s) (defined, § 165-4)
- Provision
- Ch. 165 § 165-18B(3)(z) (M-1); § 165-19B(3)(e) (M-2); Art. XXIII §§ 165-178 to 165-187 (standards); def § 165-4; SUP procedure § 165-106
- If the use is not listed
- CLOSED LISTS: each district's land 'shall be for one of the following uses' (§§ 165-18B, 165-19B); § 165-116 permits only 'in harmony with the provisions of this chapter'. No separate unlisted-use section found in the 18 of 23 articles of Ch. 165 fetched (Arts. XIII, XVII, XIX, XX, XXI not fetched). Use expressly listed, rule not reached
- Adopted
- Zoning Text Amendment 26-06-01, adopted 6-23-2026 by roll call, six ayes (BOS minutes); signed ordinance carries no ordinance number in its text. Planning Commission recommended approval 6-1 on 6-4-2026 after a motion to table failed 2-5
- Changes and status
- Before 6-23-2026 the M-2 by-right list carried 'Data processing and computer service, including development, assembly, distribution, sales and service of computer hardware and software' (§ 165-19B(1)(b)), and M-1 took in all M-2 by-right uses (§ 165-18B(1)(a)); asked at the Planning Commission on 3-5-2026 whether a data center could be built on industrial land under the current ordinance, Lemuel Hancock answered 'yes, by right' (Planning Commission minutes of 3-5-2026), and staff and counsel told the Planning Commission 6-4-2026 that data centers 'could be interpreted under the current “data processing” by-right use'. The ordinance reserved that line, defined Data Center(s), listed the use by SUP in M-1 and M-2 and added Art. XXIII (55 dBA or 65 dBC at the closest nonparticipating property line; no structure within 200 feet of a residential, agriculture or conservation line; public water or closed-loop cooling unless the Board approves otherwise by SUP; community meeting before filing). No megawatt, acreage or square-footage threshold in the nine pages of the adopted ordinance. Staff 6-4-2026: less than one percent of county land is zoned industrial and a data center on other land 'would first require a rezoning, followed by a separate special use permit process'. A ban was asked for in public comment; asked about a moratorium 6-4-2026, the Director of Community Development said that 'based on his understanding of prior Attorney General and Virginia Supreme Court authority, a moratorium is unlawful'; the 6-23-2026 minutes record no Board motion to ban. PENDING: Zoning Text Amendment 26-11-01 (data center, energy and decommissioning revisions; on-site power generation to need its own SUP authorization) was on the 11-5-2026 joint Planning Commission and Board public hearing agenda; outcome not in any record read (no minutes posted 11-14-2026); the same agenda lists 'New Proposed Fees: Special Use Permits: Data Center: $15,000'. Staff 7-15-2026: no data center application pending; public comment 9-22-2026 refers to a developer's community meeting and 'the proposed data center'. Three zoning amendments adopted 10-27-2026 (accessory dwellings; SUP compliance review and revocation, § 165-106H) do not name data centers. Towns not examined
- Route before the change
- By right under a general use
- Date of the change
- 2026-06-23
- Still to read
- minutes of the 11-5-2026 joint hearing on Zoning Text Amendment 26-11-01 (not posted on 11-14-2026)
- Confidence in this reading
- High. Ordinance text read directly, citation verified, the position unambiguous.
- Source as read
- eCode360 'Code 2025-12-09' (does not yet carry the data center ordinance); eCode360 New Laws list read 11-14-2026: Zoning Amendment 2026-06-23 (data centers) and three Zoning Amendments 2026-10-27, all four read. Read Nov. 14, 2026.
By right means the ordinance permits the use with no rezoning and no special permit. The state site assessment is the one in Va. Code § 15.2-2209.5. It applies to a new facility expected to need 100 megawatts or more when the approval is a rezoning, special exception or special use permit. This is a dated reading, current through Nov. 19, 2026. Ordinances change; read the cited provision before relying on it. From the dataset Virginia Data Center Entitlement Route Register, version 1.1, a record of how each of Virginia's 133 counties and independent cities, and five of its towns, approve a data center.
Who is building here: the public record
1 data center site in the permit record for Shenandoah County, grouped by site only where the records themselves link them, so one campus can appear as more than one site.
Data center sites found in the free state and federal records searched for Shenandoah County, and utility filings placed in the same locality, current through Nov. 22, 2026. Records are grouped under one site only where their own text links them: a site code, street address, project or campus name, notice number or named company. A record with no such link is listed on its own. Names are as each record prints them. A site missing here may still be planned: these sources miss projects that have no permit yet and code names no record ties to a company. From the dataset Who Is Building It: Virginia Data Center Sites in the Public Permit Record, which has every record, the grouping rules and what the sources do not show.
Project Tallmadge Data Center Campus 2 records
- Permit filing, DEQ Stormwater Plan Review 2025-0021 · Project Tallmadge Data Center Campus · Takanock Tallmadge, LLC
- Permit filing, VDOT Land Development · Project Tallmadge Data Center Campus · Bowman for Takanock Inc
Sources: DEQ's active construction stormwater list, EPA ECHO (water and air), Virginia Permit Transparency, Corps of Engineers Norfolk District public notices, State Corporation Commission dockets and VEDP incentive reports.