Virginia data center researcher: how each of 133 counties and cities approves one, and who pays for the grid. Independent, and updated as the record changes.
Data centers in Richmond County, Virginia
What the public record holds for this locality: how a data center gets approved.
How a data center gets approved here
A data center needs a conditional rezoning to M-1. The M-1 district has no list of permitted uses: new areas are zoned industrial conditionally for the use intended, and a change of use on an industrial site takes a conditional rezoning of that property. The Board of Supervisors decides after a Planning Commission hearing. Because approval takes a rezoning, it triggers the state site assessment. The code names no data center use.
Planning Commission minutes of Oct. 6, 2025 record the County Administrator saying a data center would have to be on a parcel rezoned or already zoned M-1 and would also need a special exception. The code as read lists one special exception use in M-1, wireless telecommunications facilities, so the register follows the text on whether land already zoned M-1 needs a rezoning. Minutes of June 8, 2026 record her saying the county has an order in to the Berkley Group for changes to the ordinance on data centers and has no applications. The codified text runs only through Feb. 11, 2021, and Board minutes from 2021 to 2026 are scans and were not read.
- State site assessment
- Triggered on the rezoning. The district must be reached by map amendment.
The register entry this is drawn from, in the dataset's own shorthand
- Position
- CONDITIONAL REZONING to M-1 'for the use intended' (M-1 has no list of permitted uses; each industrial parcel is conditionally zoned for its own use; the one special exception use listed is wireless telecommunications facilities)
- Where
- M-1 (Industrial, General), reached parcel by parcel by conditional rezoning; the M-1 section has no list of permitted uses. No data center term in any district section ('data cent' 0 in §§ 157.001 to 157.109). B-1 has no list of permitted uses either (its intent names 'retail stores, business offices, banks' and like uses) and 'is not intended for activities which require extensive warehousing'. A-1 use lists read in full; R-3 read around its industrial clause; R-1 and R-2 term-searched only. Whether and where land is zoned M-1 not checked
- What the ordinance calls the use
- (none; Planning Commission minutes of 10-6-2025 record the County Administrator saying a data center 'is generally considered an industrial use')
- Provision
- Code of Ordinances Ch. 157 (Zoning): § 157.041(B), (C), (F) (M-1); § 157.040 (B-1); § 157.046(B); § 157.021; § 157.064; § 157.060(B)(2); § 157.077
- If the use is not listed
- REZONING OR TEXT AMENDMENT (§ 157.046(B): 'Any modification of the use and density provisions may be accomplished only through a rezoning of the property in question or an amendment to this subchapter; both of which are approved by the Board of Supervisors'). The Land Use Administrator may settle 'the meaning of a word, phrase, or sentence' (§ 157.021). No similar-use power in §§ 157.021, 157.040, 157.041, 157.046, 157.060, 157.064 or 157.073 as read; 'similar' 51 hits elsewhere in Ch. 157, one read
- Adopted
- § 157.041 history note: 'Ord. passed 11-9-1995; Ord. passed 11-8-2001' (neither ordinance read). No data center amendment found; none could be confirmed or excluded from Board minutes, which are scans without text
- Changes and status
- § 157.041(B): 'New areas may be zoned Industrial, conditionally for the use intended, as the need may arise. A change in use for any industrial site may be accomplished by means of conditional rezoning for the individual property.' Rezoning is decided by the Board of Supervisors after a Planning Commission hearing (§§ 157.060(B)(2), 157.077). No data center, data processing, computer center or server farm term in Ch. 157 (66 sections fetched; term search over §§ 157.001 to 157.109; 'server' alone not searched). Planning Commission minutes 10-6-2025 record the County Administrator (so titled in those minutes) saying the Board 'has asked the Planning Commission to research Data Centers', that she has no application, that 'for a Data Center to be built it would have to be on an industrial parcel, so in order for it to be built the parcel would have to be rezoned or already zoned M - 1 and then they would also have to go through the special exception process', after suggesting the Commission 'consider limiting the usage as a special exception in the industrial use parcels'; the M-1 section as codified through 2-11-2021 lists one special exception use, wireless telecommunications facilities, so the row follows the text of § 157.041(B) on whether a parcel already zoned M-1 needs a rezoning; no motion in the passage read. Minutes 6-8-2026 record her saying 'they have an order into the Berkley Group to make some changes in the ordinance on data centers' and that the county 'does not have any applications for data centers at this time'; no motion. No draft, initiating resolution or hearing notice for a data center amendment found (county public notice pages read 11-14-2026: 'data cent' 0 hits). Not read, because they are scans without text: every Board of Supervisors minutes file 2021 to 2026, the twelve Board packets from 12-11-2025 to 11-12-2026, and Planning Commission minutes of 5-5-2025, 2-9-2026 and 4-6-2026; the eleven Board packets of January to November 2025 were not opened; no Planning Commission minutes are posted after 6-8-2026. M-1 height 45 feet, no minimum lot area (§ 157.041(D), (F)); no megawatt term in §§ 157.001 to 157.109. Site plans: Land Use Administrator for a final major site plan under 10 acres; Board of Supervisors for a preliminary major site plan over 10 acres and for a major site plan over 10 acres (§ 157.077); Ch. 153 (Site Plan) not read
- Still to read
- Board of Supervisors minutes, 2021 to 2026 (scans without a text layer, not read)
- Confidence in this reading
- Medium. The position is established but one element is unresolved: the adopting ordinance, the scope, how current the text is, or the type of source.
- Source as read
- American Legal '2021 S-3 (current)'; 'Local legislation current through an ordinance passed 2-11-2021'; zoning amendments adopted after that date, if any, not established. Read Nov. 14, 2026.
By right means the ordinance permits the use with no rezoning and no special permit. The state site assessment is the one in Va. Code § 15.2-2209.5. It applies to a new facility expected to need 100 megawatts or more when the approval is a rezoning, special exception or special use permit. This is a dated reading, current through Nov. 19, 2026. Ordinances change; read the cited provision before relying on it. From the dataset Virginia Data Center Entitlement Route Register, version 1.1, a record of how each of Virginia's 133 counties and independent cities, and five of its towns, approve a data center.
This page covers only what these sources contain. A locality with little here may still have data center activity.