Tommy N. Turner

Virginia data center researcher: how each of 133 counties and cities approves one, and who pays for the grid. Independent, and updated as the record changes.

Portrait of Tommy N. Turner
Data Center LedgerFilings, minutes, orders and transcripts, logged as they are readLatest, Nov. 25: new report version →

Data Centers · By locality

Data centers in Rappahannock County, Virginia

What the public record holds for this locality: how a data center gets approved.

Approval

How a data center gets approved here

No approval routeThe use is unlisted and prohibited, or no route permits it.

The zoning chapter names no data center use, and any use not expressly permitted in a district is prohibited. The county's zoning administrator wrote in an email of Nov. 17, 2026: "Since it is not a listed use, it is not allowed." The nearest generic line, "Industrial uses other than heavy industrial uses," is by right in the I district only. It is undefined, and no county statement applying it to a data center was found in the county's BoardDocs records (77 search results; fifteen documents read). The register rates this entry high confidence.

A draft provision saying no permitted or special use includes data centers was on the Planning Commission agenda of Jan. 15, 2025, and the Commission removed it from the agenda. Board draft minutes of July 6, 2026 and Aug. 3, 2026 record the county attorney reviewing the data center matter and a member asking for an update on a proposed data center ordinance. No later draft or hearing date for an amendment appears in the titles of the 77 BoardDocs search results or the fifteen documents read; several 2025 and 2026 results were not opened, and Board minutes after Aug. 3, 2026 were not read.

State site assessment
Does not arise. No approval route currently exists.
The register entry this is drawn from, in the dataset's own shorthand
Position
UNLISTED = PROHIBITED (no row of the § 170-36 use charts A to H, legislation through 05-04-2026, names a data center, data processing, computer, server or technology use; questions of interpretation go to the Zoning Administrator, § 170-127). The Zoning Administrator stated on 11-17-2026: 'Since it is not a listed use, it is not allowed' (Michelle L. Somers, Zoning Administrator, email)
Where
n/a by name. Nearest generic line: 'Industrial uses other than heavy industrial uses' is P (by right, site plan required) in the I district only and blank in the other nine districts (§ 170-36 chart F, cells read from the HTML table); zoning map not opened, so whether any land is zoned I was not checked
What the ordinance calls the use
(none: 0 hits in the full text of Ch. 170, legislation through 05-04-2026, for data cent, data processing, data storage, computer, server and technology)
Provision
County Code Ch. 170 (Zoning) § 170-16.A to C; § 170-36 charts A to H; § 170-67.C; § 170-127; § 170-124.L; Zoning Administrator email of 11-17-2026
If the use is not listed
DEFAULT PROHIBITION (§ 170-16.A: 'any use not expressly indicated as a permitted use in a separate zoning district is prohibited, except as qualified in §§ 170-17 and 170-18'), with uncertainties 'directed to the Zoning Administrator' (§ 170-16.A; § 170-127; appeal to the BZA). No clause admitting an unlisted use by similarity found in § 170-16; § 170-16.B makes the more specific listed use govern
Adopted
Ch. 170 adopted 12-1-1986; § 170-36 history note runs to 3-2-2026 (none of the listed amendments read). No adopted data center amendment found in Ch. 170 (legislation through 05-04-2026; 0 hits for data cent) or in the county's BoardDocs records as searched (quoted phrase 'data center', 77 results, latest dated 10-21-2026; fifteen documents read): a draft adding § 170-38.A(9), 'No permitted or special use shall be construed to incorporate “data center(s)” into its meaning.', was on the Planning Commission agenda of 1-15-2025, and the Commission 'decided to remove this item from the agenda' (minutes, no tally printed)
Changes and status
The codified § 170-38.A ('Includes legislation through 05-04-2026') has items (1) to (8) and no item (9). 'Industrial uses other than heavy industrial uses' has no definition in § 170-8 (term-name scan of the section), and no county statement applying it to a data center was found in the county's BoardDocs records (quoted-phrase search 'data center', 77 results, all dates; fifteen documents read, dated 1-15-2025 to 9-16-2026). Planning Commission 8-20-2025 discussed electrical generating plant rules as 'one way to address data centers without adding them to the ordinance'. Board draft minutes 7-6-2026: the County Administrator 'would direct the county attorney to further review the data center matter'; a Piedmont Environmental Council representative told the Board the county's 'current zoning ordinance already disallowed the unlisted use' (a public speaker's statement). Board draft minutes 8-3-2026: a member 'requested an update on the proposed data center ordinance', the County Attorney 'was researching the issue', and a member asked for the matter on a future joint Board/Planning Commission agenda. A speaker on 7-6-2026 referred to 'the recently presented petition seeking zoning ordinance amendment regarding data centers' (petition not read). After the 1-15-2025 draft, no draft, initiation or hearing date for a data center amendment appears in the titles of the 77 search results (latest dated 10-21-2026) or in the fifteen documents read; several results dated 2025 or 2026 were not opened (among them 'Zoning Report for Jan 2025.pdf', 'June 30 2025 PC Outreach Meeting Flint Hill.pdf' and three Piedmont Environmental Council files); Board minutes after 8-3-2026 not read. No size or megawatt threshold exists because Ch. 170 as read has no data center provision. Site plan for a permitted use: § 170-124.L(2) sets 30 days for approval 'by the Zoning Administrator, in the case of permitted uses requiring a site plan'; § 170-124.L(1) has site plans 'approved or modified by the Board or BZA following the recommendation of the Commission' and does not say which uses it covers; overlay district provisions not read
Confidence in this reading
High. Ordinance text read directly, citation verified, the position unambiguous.
Source as read
eCode360 Version Information: 'Includes legislation through 05-04-2026.' 'Uploaded on: 07-17-2026'; the site's New Laws list shows 'Laws (0)'. Read Nov. 14, 2026.

By right means the ordinance permits the use with no rezoning and no special permit. The state site assessment is the one in Va. Code § 15.2-2209.5. It applies to a new facility expected to need 100 megawatts or more when the approval is a rezoning, special exception or special use permit. This is a dated reading, current through Nov. 19, 2026. Ordinances change; read the cited provision before relying on it. From the dataset Virginia Data Center Entitlement Route Register, version 1.1, a record of how each of Virginia's 133 counties and independent cities, and five of its towns, approve a data center.

This page covers only what these sources contain. A locality with little here may still have data center activity.