Data centers in Middlesex County, Virginia

What the public record holds for this locality: how a data center gets approved.

Approval

How a data center gets approved here

No approval routeThe use is unlisted and prohibited, or no route permits it.

The zoning ordinance names no data center use, and any use it does not list is prohibited (Sec. 3-3). A data center therefore needs a text amendment, unless the Zoning Administrator reads it into a generic line such as service business or warehouse. No such reading was found in the Agenda Center search for 'data center' from Jan. 1, 2025 to Nov. 14, 2026 (four results, three opened); Zoning Administrator determinations were not searched. A planning staff report in the Board packet of Oct. 6, 2026, on a different use, states the same rule and shows the county handling an unlisted use by text amendment.

No data center amendment appears in the Board and Planning Commission records read through Nov. 12, 2026. An Economic Development Authority packet of Jan. 12, 2026 lists data centers among possible zoning ordinance amendments. The authority's minutes of that date are a scan and were not read.

State site assessment
Does not arise. No approval route currently exists.
The register entry this is drawn from, in the dataset's own shorthand
Position
UNLISTED = PROHIBITED (Sec. 3-3); row follows the text. A planning staff report in the Board packet of October 6, 2026, on a different use, states the same rule and shows a request to add an unlisted use by text amendment (the Board's vote on it was not read); no county statement classing a data center found in the Agenda Center search for 'data center' (01/01/2025 to 11/14/2026), the Board minutes of September 1 and October 6, 2026, the Board packet of November 4, 2026 or the Planning Commission packets of Aug 13 and Nov 12, 2026
Where
None by name. Generic lines, none tied to a data center by any county statement found in the Agenda Center search for 'data center' (1-1-2025 to 11-14-2026) or the Board minutes of September 1 and October 6, 2026, the Board packet of November 4, 2026 and the Planning Commission packets of Aug 13 and Nov 12, 2026: Light Industrial (LI) permitted 'Service Business', 'Warehouse Uses', 'Utilities', 'Research institutions and laboratories' (Sec. 12-3) and by special exception 'Office Business', 'Public and private communication facilities' (Sec. 12-4); General Business (GB) permitted 'Service business', 'Warehouses' (Sec. 11-3), with office type business also permitted (Sec. 11-3, item 4), and by special exception 'Public and Private Communications Facilities' (Sec. 11-4). LI and GB lists read in full; the other districts' lists were covered by a full-text term search, not read line by line
What the ordinance calls the use
(none)
Provision
Zoning Ordinance (county reprint, 228 pages): Sec. 3-3 Lawful Uses; Secs. 12-3, 12-4 (LI); Secs. 11-3, 11-4 (GB); Sec. 19-8; Art. 22 definitions 'BUSINESS, SERVICE TYPE', 'COMMUNICATIONS FACILITIES, PUBLIC', 'WAREHOUSE', 'UTILITIES'
If the use is not listed
DEFAULT PROHIBITION (Sec. 3-3: 'All other uses which do not constitute non - conforming uses shall be prohibited'), applied by the county through text amendment (staff report, Board packet of October 6, 2026). No clause letting the Zoning Administrator class an unlisted use as similar to a listed one was found (searched: not listed, not specifically, unlisted, not provided for, not expressly; the 30 pages carrying 'similar' were not each read). Sec. 19-8 sends 'all questions of interpretation' first to the Zoning Administrator
Adopted
n/a: no data center provision. Zoning Ordinance title page: 'Reprinted: September 1 , 2026 , to include revisions'
Changes and status
No data center, data processing, data storage, server farm or computing term in the reprint (228 pages, text layer on every page; 'computer' once, in the adult book store definition). Staff report on a request to amend the Zoning Ordinance to 'allow Tattoo & Piercing Salon as a Special Exception use in the General Business District', Board packet of October 6, 2026: 'Middlesex County’s Zoning Ordinance is a permissive ordinance, meaning that only land uses specifically listed as allowed in a district are permitted and anything not expressly listed is strictly prohibited.' That report concerned a different use and states the general rule; it does not show how the county would class a data center, and the row follows the text of Sec. 3-3. A data center therefore needs a text amendment unless the Zoning Administrator reads it into a generic line; no such reading or determination was found (Agenda Center search for 'data center', 01/01/2025 to 11/14/2026: four results, three opened, none of those a zoning item; the Broadband Authority file of July 16, 2026 not opened; the Economic Development Authority minutes of January 12, 2026 are a scan and were not read; scanned packet pages are not searchable). Zoning Administrator determinations are not among the Agenda Center's categories and were not searched elsewhere. Mentions only: a staff activity report in the Board packet of February 4, 2025 ('Attended meeting with Timmons to discuss possible data center projects'); a list item in the Economic Development Authority packet of January 12, 2026 ('Zoning Ordinance Amendments ... (SUP Process, Airport Overlay District, Data Centers)'); a suggestion recorded in minutes carried in the Broadband Authority packet of October 15, 2026 (that the County 'proactively prepare for potential data center development by establishing appropriate zoning provisions'). No data center amendment drafted, initiated or set for hearing in the Board minutes of September 1 and October 6, 2026, the Board packet of November 4, 2026, or the Planning Commission packets of Aug 13 and Nov 12, 2026 (text pages; image pages not searchable). No data center size threshold, because the reprint has no data center provision ('megawatt' 0 hits); an LI district must be not less than 'twenty - five (25) acres' unless it is a logical extension of an existing LI district (Sec. 12-2)
Still to read
Economic Development Authority minutes of January 12, 2026 (a scan, not read)
Confidence in this reading
Medium. The position is established but one element is unresolved: the adopting ordinance, the scope, how current the text is, or the type of source.
Source as read
County reprint: 'Reprinted: September 1 , 2026 , to include revisions' (the county Ordinances page dates the file July 8, 2025). Municode Appendix D stands at 'codified through an ordinance adopted April 20, 2023' and was not used. Read Nov. 14, 2026.

By right means the ordinance permits the use with no rezoning and no special permit. The state site assessment is the one in Va. Code § 15.2-2209.5. It applies to a new facility expected to need 100 megawatts or more when the approval is a rezoning, special exception or special use permit. This is a dated reading, current through Nov. 19, 2026. Ordinances change; read the cited provision before relying on it. From the dataset Virginia Data Center Entitlement Route Register, version 1.1, a record of how each of Virginia's 133 counties and independent cities, and five of its towns, approve a data center.