Data centers in Mathews County, Virginia

What the public record holds for this locality: how a data center gets approved.

Approval

How a data center gets approved here

No approval routeThe use is unlisted and prohibited, or no route permits it.

The zoning chapter names no data center use, so a data center would need an ordinance amendment. An application for an unlisted use goes from the administrator to the Planning Commission, which recommends to the governing body an amendment or rezoning that allows the use, or a denial (§ 175-19.13). No administrator power to treat an unlisted use as similar to a listed one was found. The industrial district lists storage warehouses and business communications facilities by right, and no county statement classing a data center under those lines was found in the meeting portal's full-content search (no event dated 2025 or 2026; six earlier events not opened) or the county website search. The register rates this entry low confidence.

On Nov. 10, 2026 the Planning Commission held hearings on county text amendments, one of them to the definitions and listings of major and minor utility uses (Application #202600976). A Board staff report dated Nov. 12, 2026 records that the Commission recommended approval of that amendment on a 7-0 vote. It removes "Utility use, major" as a conditional use from C, R-1 and B-1, along with the Industrial district exemption language, and the report has no data center term. It is on the Board's Nov. 19, 2026 agenda as a staff report item, not a public hearing, and has not been adopted. How the county has applied § 175-19.13 was not searched.

State site assessment
Does not arise. No approval route currently exists.
The register entry this is drawn from, in the dataset's own shorthand
Position
TEXT AMENDMENT REQUIRED (unlisted use; the 'uses not provided for' referral ends in an ordinance amendment or a denial)
Where
n/a
What the ordinance calls the use
(none)
Provision
Code Ch. 175 (Zoning) § 175-19.13; § 175-4.1; I lists §§ 175-10.2, 175-10.3; amendments § 175-19.3
If the use is not listed
TEXT-AMENDMENT ROUTE (§ 175-19.13: the Administrator refers the application to the Commission, which recommends to the governing body whether 'To amend the ordinance to allow the unrestricted use in that district', 'To amend the ordinance to allow the use as a conditional use', 'To amend the ordinance by rezoning the district and thereby allow the use' or 'To deny the use in that district'; procedure per §§ 175-19.3 through 175-19.10)
Adopted
Ch. 175 'Adopted by the Board of Supervisors of Mathews County1-29-1987; as amended through 8-27-2013'; § 175-19.13 carries no amendment note; I by-right list 'Amended 2-23-2021; 7-28-2021; 12-19-2023' (amending ordinances not read)
Changes and status
No data center, data processing, computer or server farm term ('server' alone not searched) in Chapter 175 (full chapter text, 408,013 characters, term-searched; 'data' appears only in 'Data poles' and in survey and plan data). I, B-1, B-2 and VMU use lists read in full: generic lines only ('Wholesale businesses, storage warehouses' and 'Communications towers and facilities related to business use' by right in I; 'Office buildings and business and governmental offices' by right in B-2 and VMU; 'Utility use, major' by conditional use permit from the Board of Supervisors); no county statement classing a data center under any of them found in the CivicClerk full-content search for 'data center' and 'data centers' (no event dated 2025 or 2026; six earlier events not opened) or in the county website search for 'data center' (one result, an information technology procurement file, not opened). RU, R-1, R-2 and C lists term-searched only. No similar-use power for the Administrator found in Chapter 175 (searched: similar use, similar in, interpret, not listed, same general character, not enumerated, unlisted). Meeting portal (CivicClerk) full-content search for 'data center' and 'data centers': no event dated 2025 or 2026 (the index reaches the Planning Commission packet for November 10, 2026); individual minutes not opened. Planning Commission, November 10, 2026: public hearings listed on county text amendments to hearing procedure (Application #202600975) and to the Utility Use Major and Minor definitions and listings (Application #202600976); the Board staff report dated 11-12-2026 records that the Planning Commission recommended approval of #202600976 on a 7-0 vote (it removes 'Utility use, major' as a conditional use from C, R-1 and B-1 and the Industrial district exemption language; the report has no data center term); before the Board as a staff report item, not a public hearing, on its 11-19-2026 agenda; not adopted; the outcome on #202600975 not read. No megawatt term in Chapter 175; I district minimum lot 25,000 square feet, height up to 50 feet, above that with the administrator's approval, coverage 70%. Site development plan: approved by the agent appointed by the governing body, with appeal to the governing body (§ 175-17.6); Chesapeake Bay overlay and VMU review not read. Whether any land is zoned I not checked. Row follows the text of § 175-19.13; how the county has applied that section was not searched
Confidence in this reading
Low. An interpretive question is unanswered on the record.
Source as read
eCode360 'Includes legislation through 04-16-2026.'; New Laws page: 'There are currently no known new laws for this Code.'. Read Nov. 14, 2026.

By right means the ordinance permits the use with no rezoning and no special permit. The state site assessment is the one in Va. Code § 15.2-2209.5. It applies to a new facility expected to need 100 megawatts or more when the approval is a rezoning, special exception or special use permit. This is a dated reading, current through Nov. 19, 2026. Ordinances change; read the cited provision before relying on it. From the dataset Virginia Data Center Entitlement Route Register, version 1.1, a record of how each of Virginia's 133 counties and independent cities, and five of its towns, approve a data center.

This page covers only what these sources contain. A locality with little here may still have data center activity.