Virginia data center researcher: how each of 133 counties and cities approves one, and who pays for the grid. Independent, and updated as the record changes.
Data centers in Madison County, Virginia
What the public record holds for this locality: how a data center gets approved.
How a data center gets approved here
The zoning ordinance names no data center use. A use not specifically permitted is prohibited, and a request for one goes to the Planning Commission and the Board for a text amendment or rezoning, or a denial. The M-1 and M-2 districts also allow by special use permit an "other ... industrial use of a similar nature not specifically enumerated." Whether those lines reach a data center is undetermined, and no county statement on it was found in the county Agenda Center search for 'data center' from Jan. 1, 2025 to Nov. 14, 2026 (8 results, 3 packets opened; minutes not read). The county's planning and zoning administrator wrote in an email of Nov. 17, 2026: "My preliminary view is that a data center would be treated as a use not specifically provided for under Article 14, rather than presumed eligible for a special use permit under Sections 9-2-7 or 10-2-8. This is an initial opinion, not a formal zoning determination." The administrator added that the county "has very little industrially zoned land" and that a data center "would therefore likely also require rezoning." The register follows that view and rates this entry medium confidence.
A 2025 annual report of the county's Economic Development Committee, in the Board packet of Jan. 28, 2026, says data centers were researched and that there was no serious interest in locating one in Madison. That was a study, and no amendment followed in the records read. Seven zoning ordinances adopted from Jan. 7, 2026 to Oct. 7, 2026 are not yet codified; none is titled for data centers, and their texts were not read.
- State site assessment
- Does not arise. No approval route currently exists.
The register entry this is drawn from, in the dataset's own shorthand
- Position
- TEXT AMENDMENT REQUIRED for a use not specifically permitted (Secs. 2-4, 14-7); the M-1 and M-2 special use permit lines for an 'other ... industrial use of a similar nature not specifically enumerated' are not shown on any county record read to reach a data center
- Where
- n/a: no district names the use in App. 1 as codified through Supp. No. 6 (M-1, M-2 and B-1 lists read; C-1, A-1, R-1, R-2 and R-3 covered by a whole-appendix term search only; an R-4 district set up by ordinances not yet codified was not read). Residual special use permit lines for similar industrial uses: M-1 (Sec. 9-2-7) and M-2 (Sec. 10-2-8)
- What the ordinance calls the use
- (none)
- Provision
- Code App. 1 (Zoning) Secs. 2-4, 9-2-7, 10-2-8, 14-3, 14-7-1 to 14-7-3
- If the use is not listed
- DEFAULT PROHIBITION (Secs. 2-4, 14-7-1: a use not specifically permitted 'is prohibited') with referral to the Planning Commission and Board for a text amendment (by right or by special use permit), a rezoning or denial (Secs. 14-7-1 to 14-7-3); separate SPECIAL USE PERMIT lines for an 'Other limited industrial use of a similar nature not specifically enumerated' (M-1, Sec. 9-2-7) and an 'Other general industrial use of a similar nature not specifically enumerated' (M-2, Sec. 10-2-8); no Administrator classification power found (Art. 19 'interpret' 2 hits, both the district boundary rule; terms not specifically, not listed, not provided for)
- Adopted
- App. 1 as codified through Ordinance No. 2025-ZOA-05-25-03, enacted January 7, 2026 (Supp. No. 6); the ordinance that wrote Secs. 9-2-7 and 10-2-8 not identified
- Changes and status
- No data center, data processing or computer term in App. 1 (Municode Supp. No. 6; whole appendix rendered and searched, 'industrial' 30 hits as control). No county statement found on whether a data center is an industrial use 'of a similar nature' (county Agenda Center search for 'data center', 1-1-2025 to 11-14-2026: 8 results, 3 packets opened; minutes not read). Economic Development Committee Annual Report 2025 (Board packet of 1-28-2026): data centers researched, 'Preliminary county policies regarding zoning and planning were discussed in relation to possible future data center development', 'there was no serious interest in locating a data center in Madison', the committee 'will continue to pursue this project'; a study, not an amendment. Seven zoning ordinances are on Municode's not-yet-codified list: two adopted 1-7-2026 (one of them the ordinance the codified-through line names; by agenda description they concern R-3 and Secs. 5-1-1 and 5-2-1) and five adopted 5-6-2026 to 10-7-2026; by title or agenda description they concern R-3 and R-4, definitions, site plan validity, cottage food sales and accessory dwelling units; their texts were not read. No data center case on the Joint Meeting agendas of 6-3, 9-2, 10-7 and 11-4-2026 or the Planning Commission workshop agenda of 10-21-2026 (text-layer pages only; each packet has scanned pages). No megawatt, floor-area or acreage threshold for data centers ('megawatt' appears only in the solar revenue share, Sec. 14-20). Two provisions compete: Secs. 2-4 and 14-7-1 say a use not specifically permitted 'is prohibited' and send a request for one to the Planning Commission and the Board for a text amendment, a rezoning or a denial (Secs. 14-7-1 to 14-7-3); Secs. 9-2-7 (M-1) and 10-2-8 (M-2) allow by special use permit an 'Other limited industrial use of a similar nature not specifically enumerated' and an 'Other general industrial use of a similar nature not specifically enumerated'; whether those two lines reach a data center is undetermined. Coded from the county's rule for unlisted uses (codebook rule 14); the similar-use lines are the possible route if the county treats a data center as such a use. Planning and Zoning Administrator, email of 11-17-2026: 'My preliminary view is that a data center would be treated as a use not specifically provided for under Article 14, rather than presumed eligible for a special use permit under Sections 9-2-7 or 10-2-8. This is an initial opinion, not a formal zoning determination. The appropriate approval path would require further review of a specific proposal.' He added that the county 'has very little industrially zoned land' and a data center 'would therefore likely also require rezoning'. The row follows that view
- Confidence in this reading
- Medium. The position is established but one element is unresolved: the adopting ordinance, the scope, how current the text is, or the type of source.
- Source as read
- Municode: 'Codified through Ordinance No. 2025-ZOA-05-25-03, enacted January 7, 2026. (Supp. No. 6)'; 'VERSION: APR 17, 2026 (CURRENT)'; adopted-not-codified list runs to Ordinance No. ZOA-07-26-01 (Adopted 10/7/26), none titled for data centers; the same list also carries Ordinance Nos. 2025-ZOA-05-25-03 and 2025-ZOA-05-25-01 (both 'Adopted 1/7/26'), the first of which the codified-through line names as codified. Read Nov. 14, 2026.
By right means the ordinance permits the use with no rezoning and no special permit. The state site assessment is the one in Va. Code § 15.2-2209.5. It applies to a new facility expected to need 100 megawatts or more when the approval is a rezoning, special exception or special use permit. This is a dated reading, current through Nov. 19, 2026. Ordinances change; read the cited provision before relying on it. From the dataset Virginia Data Center Entitlement Route Register, version 1.1, a record of how each of Virginia's 133 counties and independent cities, and five of its towns, approve a data center.
This page covers only what these sources contain. A locality with little here may still have data center activity.