Data centers in King George County, Virginia

What the public record holds for this locality: how a data center gets approved, who is building, and what to read.

Case study: Fredericksburg Ring, read from local packets, minutes, ordinances and agreements.

Approval Who is building What to read

How a data center gets approved here

Permit requiredA discretionary permit is required: a conditional or special use permit, a special exception or a provisional use permit.

A data center needs a special exception in C-2, I-1 and I. It was by right in the I district under an ordinance of June 18, 2019. The Board changed that in an ordinance of Dec. 19, 2023, effective Jan. 1, 2024. A consultant had recommended no change, and the Board adopted the stricter option.

State site assessment
Triggered. Approval here generates a rezoning, special exception or special use permit.
The register entry this is drawn from, in the dataset's own shorthand
Position
SPECIAL EXCEPTION
Where
C-2, I-1, I
What the ordinance calls the use
Data Centers
Provision
App.A Art.VI Div.3 Tbl VI-1; stds §7-6-5
If the use is not listed
Administrator determination, App. A § 6-2-1(B) (most similar use type); otherwise default prohibition, § 6-2-1(A) and (C)
Adopted
Ord. of 12-19-2023(1), eff. 1-1-2024
Changes and status
Was BY RIGHT in 'I' under Ord. of 6-18-2019. Consultant recommended NO change; Board adopted the stricter option
Route before the change
By right
Date of the change
2023-12-19
Still to read
Ord. of 12-19-2023(1) (not read)
Confidence in this reading
Medium. The position is established but one element is unresolved: the adopting ordinance, the scope, how current the text is, or the type of source.
Source as read
Ordinances of December 2, 2025 (Supp. No. 12); not-yet-codified list (through O-11-26, 10-6-2026) holds no Appendix A ordinance. Read Nov. 4, 2026.

By right means the ordinance permits the use with no rezoning and no special permit. The state site assessment is the one in Va. Code § 15.2-2209.5. It applies to a new facility expected to need 100 megawatts or more when the approval is a rezoning, special exception or special use permit. This is a dated reading, current through Nov. 19, 2026. Ordinances change; read the cited provision before relying on it. From the dataset Virginia Data Center Entitlement Route Register, version 1.1, a record of how each of Virginia's 133 counties and independent cities, and five of its towns, approve a data center.

Who is building here: the public record

1 data center site in the permit record for King George County, grouped by site only where the records themselves link them, so one campus can appear as more than one site.

Data center sites found in the free state and federal records searched for King George County, and utility filings placed in the same locality, current through Nov. 22, 2026. Records are grouped under one site only where their own text links them: a site code, street address, project or campus name, notice number or named company. A record with no such link is listed on its own. Names are as each record prints them. A site missing here may still be planned: these sources miss projects that have no permit yet and code names no record ties to a company. From the dataset Who Is Building It: Virginia Data Center Sites in the Public Permit Record, which has every record, the grouping rules and what the sources do not show.

Sources: DEQ's active construction stormwater list, EPA ECHO (water and air), Virginia Permit Transparency, Corps of Engineers Norfolk District public notices, State Corporation Commission dockets and VEDP incentive reports.