Data centers in James City County, Virginia

What the public record holds for this locality: how a data center gets approved and what to read.

Approval What to read

How a data center gets approved here

Permit requiredA discretionary permit is required: a conditional or special use permit, a special exception or a provisional use permit.

A data center needs a special use permit and is allowed only in M-2 General Industrial. A Board policy adopted Nov. 12, 2025 guides permit applications. It calls for a site inside the Primary Service Area, 1,000 feet from occupied dwellings, public water with no wells and closed-loop cooling. Neither the ordinance nor the policy sets a megawatt, square-footage or acreage figure.

Before Sept. 9, 2025 data centers were not defined and were permitted by right in M-1, M-2, MU and EO as data processing centers, according to a staff memo. The Board changed that 4-1 on Sept. 9, 2025 (Ord. No. 31A-364), after a 6-1 Planning Commission recommendation. RT keeps data processing centers as an accessory use, and staff said no land is zoned RT.

A pending amendment, ORD-26-0009, would make the policy a submittal requirement for a permit and changes no use list. The Planning Commission recommended it 7-0 on Oct. 7, 2026, and the Board's hearing is scheduled for Nov. 17, 2026.

State site assessment
Triggered. Approval here generates a rezoning, special exception or special use permit.
The register entry this is drawn from, in the dataset's own shorthand
Position
SPECIAL USE PERMIT
Where
M-2 General Industrial (SUP); not listed in any other district. 'Data processing centers' removed from M-1, M-2, MU and EO on 9-9-2025; RT keeps 'Data processing centers as an accessory use to other permitted uses' (staff 9-9-2025: no land zoned RT)
What the ordinance calls the use
Data center
Provision
Ch. 24 Sec. 24-436 (M-2 use list, Industrial: 'Data centers SUP'); def Sec. 24-2; Board 'Data Facilities Policy' (resolution 11-12-2025) guides SUP applications
If the use is not listed
DEFAULT PROHIBITION, text-amendment route (Sec. 24-4: 'If a use is not specified in a zoning district, it shall be prohibited in that district'); M-1, M-2 and RT lead-ins add 'or similar uses'; use named, rule not reached
Adopted
Ord. No. 31A-364 (case ORD-24-0002), 9-9-2025, 4-1
Changes and status
Before 9-9-2025, staff memo: 'Data Centers are not defined in the Ordinance and are permitted by-right' in M-1, M-2, MU and EO (under 'data processing centers'). Planning Commission 6-1 (staff memo; public hearing on its 7-2-2025 agenda; Commission minutes not read). Board policy adopted 11-12-2025: guidance for SUPs (inside Primary Service Area; 1,000 ft from occupied dwellings; 55 dB or ambient; public water, no wells; closed-loop cooling); no megawatt, square-footage or acreage figure in ordinance or policy. PENDING: ORD-26-0009 would add Sec. 24-23(e) making the policy an SUP submittal requirement (HB 153, 2026); Planning Commission 7-0 on 10-7-2026; Board public hearing SCHEDULED 11-17-2026, not adopted as of 11-14-2026; it changes no use list. Agenda titles of Board, Planning Commission, Policy Committee and DRC, 1-2025 to 11-18-2026 (94 sheets): no data center SUP application and no moratorium. Prime Storage Norge conceptual plan (press lead): not in those agendas; parcel zoning and staff outcome not reached
Route before the change
By right under a general use
Date of the change
2025-09-09
Confidence in this reading
High. Ordinance text read directly, citation verified, the position unambiguous.
Source as read
County enCodePlus portal prints no currency line; latest history notes in Ch. 24 are Ord. Nos. 31A-366, 31A-367, 31A-368 (7-14-26); Ord. No. 31A-369 (9-8-2026, signs) adopted and not yet in the text. Read Nov. 14, 2026.

By right means the ordinance permits the use with no rezoning and no special permit. The state site assessment is the one in Va. Code § 15.2-2209.5. It applies to a new facility expected to need 100 megawatts or more when the approval is a rezoning, special exception or special use permit. This is a dated reading, current through Nov. 19, 2026. Ordinances change; read the cited provision before relying on it. From the dataset Virginia Data Center Entitlement Route Register, version 1.1, a record of how each of Virginia's 133 counties and independent cities, and five of its towns, approve a data center.

What to read

This page covers only what these sources contain. A locality with little here may still have data center activity.