Data Centers · By locality

Data centers in Isle of Wight County, Virginia

What the public record holds for this locality: how a data center gets approved and what to read.

Approval What to read

How a data center gets approved here

Permit requiredA discretionary permit is required: a conditional or special use permit, a special exception or a provisional use permit.

Any proposed data center would have to file a special use permit application, in any district. The zoning ordinance's own unlisted-use provision, App. B Sec. 1-1018(A), read Nov. 16, 2026, has the zoning administrator refer an application for a use not specifically permitted to the Planning Commission as a special use permit. County planning staff state the same route in the Planning Report in the Planning Commission packets of Oct. 27 and Nov. 10, 2026, which says the zoning ordinance does not include a data center use type definition or standards. Sec. 3-1001(A) also lets the administrator determine the appropriate use type, or find a proposed use different enough from every listed use type that it will require a text amendment, with appeal to the Board of Zoning Appeals; no such determination for a data center was found. The Sec. 4-1005 use table was not opened, and the adopted ordinance was not re-read Nov. 4, 2026. Because approval runs through a special use permit, it triggers the state site assessment.

The county is drafting its own data center rules, and nothing has been adopted. The draft revised Oct. 20, 2026 would allow data centers by conditional use permit in LI, GI, GIC and PD-IP. It draws on York County, Fairfax and Chesapeake models.

The Planning Commission directed revisions at a work session on Sept. 8, 2026 and discussed the October revision on Oct. 27 and Nov. 10, 2026, when staff said no action was required. The Nov. 10, 2026 minutes had not been posted as of Nov. 15, 2026. No data center item was found on the five Board agendas from Aug. 20 through Nov. 5, 2026; their text was searched and the packets were not.

State site assessment
Triggered. Approval here generates a rezoning, special exception or special use permit.
The register entry this is drawn from, in the dataset's own shorthand
Position
SPECIAL USE PERMIT for an unlisted use, on the county planning staff's statement that 'Any proposed data center facility would be required to file a special use permit application' (Planning Report, PC packets of 10-27 and 11-10-2026); the ordinance neither defines nor lists data centers
Where
Any district, by special use permit, on the county planning staff's statement (Planning Report, PC packets of 10-27 and 11-10-2026); draft: LI, GI, GIC and PD-IP by conditional use permit (DRAFT STRAWMAN Rev. 10/20/26)
What the ordinance calls the use
(none)
Provision
Not found defined or listed in the adopted ordinance (term search of August 2026; adopted ordinance not re-read 11-4-2026); App. B Secs. 1-1018(A) and 3-1001(A)-(C) (Municode, read 11-16-2026)
If the use is not listed
SPECIAL USE PERMIT (App. B Sec. 1-1018(A): 'If, in any district established under this ordinance, a use is not specifically permitted and an application is made to the zoning administrator for such use, the zoning administrator shall refer the application to the planning commission as a special use permit'), the route the county planning staff also states (Planning Report, PC packets of 10-27 and 11-10-2026). Sec. 3-1001(A) also lets the administrator 'determine the appropriate use type' or 'determine that a proposed use or activity is sufficiently different from any use type listed below and will require an amendment to the text of this ordinance' (appeal to the BZA, Sec. 3-1001(C)); no such determination for a data center found
Adopted
Draft Strawman Rev. 10/20/26, NOT ADOPTED
Changes and status
Drafted from York County, Fairfax and Chesapeake models. PC work session 9-8-2026 directed revisions; PC 10-27-2026 and 11-10-2026 discussion of Rev. 10/20/26, staff: "No action is required." (11-10-2026 minutes not posted on 11-15-2026). The Planning Report in both packets states that 'The Zoning Ordinance does not currently include a data center use type definition or standards'; the row follows the staff statement of the current route (codebook rule 5) No data center item found on the five BOS agendas 8-20 through 11-5-2026 (text layers searched; packets not searched).
Still to read
Sec. 4-1005 use table (not opened); an administrator use-type determination under Sec. 3-1001(A), if any
Confidence in this reading
Medium. The position is established but one element is unresolved: the adopting ordinance, the scope, how current the text is, or the type of source.
Source as read
Municode 'Codified through Ordinance of June 18, 2026. (Supp. No. 90-8-26)', 'VERSION: NOV 3, 2026 (CURRENT)'; the code carries 'APPENDIX B. - ZONING.*' (read 11-16-2026). Read Nov. 4, 2026.

By right means the ordinance permits the use with no rezoning and no special permit. The state site assessment is the one in Va. Code § 15.2-2209.5. It applies to a new facility expected to need 100 megawatts or more when the approval is a rezoning, special exception or special use permit. This is a dated reading, current through Nov. 19, 2026. Ordinances change; read the cited provision before relying on it. From the dataset Virginia Data Center Entitlement Route Register, version 1.1, a record of how each of Virginia's 133 counties and independent cities, and five of its towns, approve a data center.

What to read

This page covers only what these sources contain. A locality with little here may still have data center activity.