Data Centers · By locality

Data centers in Greensville County, Virginia

What the public record holds for this locality: how a data center gets approved.

Approval

How a data center gets approved here

Permit requiredA discretionary permit is required: a conditional or special use permit, a special exception or a provisional use permit.

A data center needs a special use permit in the county's Technology Overlay District, adopted June 3, 2024. The district's purpose section closely copies the purpose language of Prince William County's data center overlay.

The MayMac Tech Campus, about 466 acres, was recommended for approval in November 2024.

State site assessment
Triggered. Approval here generates a rezoning, special exception or special use permit.
The register entry this is drawn from, in the dataset's own shorthand
Position
SPECIAL USE PERMIT
Where
Technology Overlay District
What the ordinance calls the use
Data centers
Provision
§25-3
If the use is not listed
not read
Adopted
Adopted 6-3-2024 (date from the Art. 25 page footers; adopting ordinance and Board minutes not read)
Changes and status
§25-1 is a near-verbatim clone of PWC's DCOZOD purpose language. MayMac Tech Campus ~466 ac rec. approval Nov 2024
Route before the change
not established
Date of the change
2024-06-03
Still to read
Board minutes or adopting ordinance of 6-3-2024 (not read)
Confidence in this reading
Medium. The position is established but one element is unresolved: the adopting ordinance, the scope, how current the text is, or the type of source.
Source as read
County PDF 'Updated Zoning Ordiance - 10302025' (260 pp, scanned); Art. 25 footer 'Adopted June 3, 2024'. Read Nov. 4, 2026.

By right means the ordinance permits the use with no rezoning and no special permit. The state site assessment is the one in Va. Code § 15.2-2209.5. It applies to a new facility expected to need 100 megawatts or more when the approval is a rezoning, special exception or special use permit. This is a dated reading, current through Nov. 19, 2026. Ordinances change; read the cited provision before relying on it. From the dataset Virginia Data Center Entitlement Route Register, version 1.1, a record of how each of Virginia's 133 counties and independent cities, and five of its towns, approve a data center.

This page covers only what these sources contain. A locality with little here may still have data center activity.