What the public record holds for this locality: how a data center gets approved.

Approval

How a data center gets approved here

No approval routeThe use is unlisted and prohibited, or no route permits it.

Data centers are defined in the zoning ordinance and listed in no district, so there is no route under the ordinance as it stands. A use not provided for goes to the Planning Commission, and the ordinance is then amended to list it. The register treats that step as a text amendment.

The Board adopted the definition on Feb. 25, 2025 (O-2024-007), with four members voting yes and one abstaining. The draft before the Board would have allowed data centers by special use permit in a new TRFD district. The Board removed them from that list, its members having unanimously expressed that they do not want data centers in Greene County, according to the signed minutes. Before then the ordinance did not define the use. At that meeting, according to the signed minutes, Mr. Frydl told the Board that data centers can be built in industrial districts without much oversight. The earlier text was not read.

Board and Planning Commission files after June 9, 2026 were not read.

State site assessment
Does not arise. No approval route currently exists.
The register entry this is drawn from, in the dataset's own shorthand
Position
DEFINED AND LISTED IN NO DISTRICT (Zoning Ordinance, Latest Revision October 27, 2026: 'data cent' 1 hit in 186 pages, the definition); TEXT AMENDMENT REQUIRED (Sec. 16-6)
Where
n/a. 'DATA CENTER' is defined in Art. 22 and listed in no district (TRFD, M-1, M-2, B-1, B-2 and B-3 use lists read; C-1, A-1, R-1, R-2, SR, PUD and FP covered by a whole-document term search only)
What the ordinance calls the use
DATA CENTER (defined, Art. 22, tagged '(2/25/2025)'; listed in no district)
Provision
Zoning Ord. (Latest Revision: October 27, 2026) Art. 22 'DATA CENTER'; Art. 10A Secs. 10A-1-1, 10A-1-2; Art. 11 Secs. 11-1-1, 11-1-2; Art. 12 Secs. 12-1-1, 12-1-2; Sec. 16-6
If the use is not listed
TEXT-AMENDMENT ROUTE (Sec. 16-6 'USES NOT PROVIDED FOR': the Administrator refers the application to the Planning Commission; 'On the recommendation of the governing body, the ordinance shall be amended to list the use as a permitted use in the district'); no Administrator power to classify an unlisted use found (whole-document search for similar use, same general character, interpret)
Adopted
O-2024-007 (OR#24-001), 'ADOPTED BY THE GREENE COUNTY BOARD OF SUPERVISORS ON FEBRUARY 25, 2025': motion Francis McGuigan, second Tim Goolsby; Catalano Yes, Durrer Yes, Lamb Abstained, Goolsby Yes, McGuigan Yes (signed ordinance, Attachment B to the signed minutes of 2-25-2025; a scan, read by OCR and the vote page checked against the page image). It approves the Article 22 and Article 10A changes 'as amended', change 2 being to 'Remove "data centers" and "manufacturing" from section 10A-1-2 USES PERMITTED BY SPECIAL USE PERMIT, leaving only warehousing'. The attachment titled 'Signed Resolution' on the 2-25-2025 meeting page is the Board's resolution of intent of June 25, 2024 to add a Technology/Flex Research and Development district, not the adopting ordinance
Changes and status
Before 2-25-2025 the ordinance did not define the use, on Mr. Frydl's statement to the Board that night and the definition's '(2/25/2025)' tag (the earlier text was not read); he told the Board data centers 'can be built in industrial districts without much oversight' (signed minutes of 2-25-2025, read by OCR). Staff memo of 2-25-2025, on the draft as proposed: 'Adding a definition and the limitation also eliminates by-right data center construction in our other zoning districts'; the limitation was the draft's special use listing in TRFD, which the Board removed, and no county statement after adoption on the industrial districts' generic lines was read. The draft before the Board listed 'Data centers, manufacturing and warehousing' as a special use in the new TRFD district; the Board's consensus was to 'remove data centers from the list of uses allowed by special use permit', the members having 'unanimously expressed, they do not want data centers in Greene County'. Ordinance as it stands: the definition remains, the TRFD special use list reads conference and event centers and warehousing, and 'data cent' appears nowhere else in its 186 pages (text layer on every page). No megawatt, floor-area or acreage threshold applies to data centers ('megawatt' 0 hits). County meeting portal search for 'data center' returns nothing dated after 6-9-2026; the hits opened in Board minutes of 11-13-2025 and 5-12-2026 are liaison reports, not zoning items; the Board files of 1-28, 3-25, 4-22, 5-27 and 9-23-2025 and a 3-24-2026 'Contract' attachment, all returned by that search, were not opened; whether the search covers files posted after 6-9-2026 was not established; Planning Commission files and Board files after 6-9-2026 not read
Route before the change
not established
Date of the change
2025-02-25
Still to read
Board and Planning Commission files after 6-9-2026 (not read)
Confidence in this reading
High. Ordinance text read directly, citation verified, the position unambiguous.
Source as read
County's own Zoning Ordinance PDF, cover 'Latest Revision: October 27, 2026' (county link text 'Zoning Ordinance (PDF) 11/9/2026'); Municode copy not opened. Read Nov. 14, 2026.

By right means the ordinance permits the use with no rezoning and no special permit. The state site assessment is the one in Va. Code § 15.2-2209.5. It applies to a new facility expected to need 100 megawatts or more when the approval is a rezoning, special exception or special use permit. This is a dated reading, current through Nov. 19, 2026. Ordinances change; read the cited provision before relying on it. From the dataset Virginia Data Center Entitlement Route Register, version 1.1, a record of how each of Virginia's 133 counties and independent cities, and five of its towns, approve a data center.