Virginia data center researcher: how each of 133 counties and cities approves one, and who pays for the grid. Independent, and updated as the record changes.
Data centers in Gloucester County, Virginia
What the public record holds for this locality: how a data center gets approved.
How a data center gets approved here
A data center needs a conditional use permit from the Board of Supervisors, after Planning Commission review and a public hearing, and it is allowed only in the I-1 Industrial District. The ordinance defines the use, and no size, acreage or power figure appears in the definition, the use table rows or Sec. 14-3; Article 9B was not opened, and its headings name no data center section. An amendment adopted Feb. 3, 2026 provides that the storage or transformation of digital data shall not be considered manufacturing and is regulated as a data center.
On the record read, the use entered the ordinance with the zoning ordinance update adopted Sept. 3, 2024, which replaced the zoning appendix in its entirety according to the codifier's note. Planning Commission minutes of July 6, 2023 record the Commission directing staff to allow data centers in I-1 with a conditional use permit. The ordinance of Sept. 3, 2024 and the Board minutes of that date were not read.
A technology overlay for the Glenns area was dropped in 2025. The Planning Commission voted 6-0 on June 5, 2025 to stop work on it, and the Board agreed by consensus on July 15, 2025, according to draft minutes, to leave things as they were.
- State site assessment
- Triggered. Approval here generates a rezoning, special exception or special use permit.
The register entry this is drawn from, in the dataset's own shorthand
- Position
- CONDITIONAL USE PERMIT (Board of Supervisors, after Planning Commission review and public hearing)
- Where
- I-1 Industrial District, by conditional use permit. The term appears twice in Article 5 (every district section and every Sec. 5-70 table, rendered text searched): in the I-1 use table, Sec. 5-60.1(2)e (P and SE cells blank, CUP cell checked), and in the Sec. 5-70.4 row 'Data Center' (read cell by cell: blank in C-1, RC-1, RC-2, C-2, SC-1, SF-1, MF-1, MH-1, B-2, B-1 and B-4, CUP in I-1). PUD-1: uses are fixed by the ordinance establishing each district (Sec. 8-3), and Article 8 names no data center use
- What the ordinance calls the use
- Data center (defined, Sec. 2-2)
- Provision
- App. B Zoning: Sec. 5-70.4 (use table); Sec. 5-60.1(2)e (I-1 use table); def. Sec. 2-2 ('Data center'; 'Manufacture and/or manufacturing'); CUP procedure Sec. 14-3
- If the use is not listed
- DEFAULT PROHIBITION with a text-amendment request (Sec. 4-2(2): 'In any district, uses not specifically permitted shall not be allowed'; a person may 'request the planning commission or board of supervisors to consider an amendment to the ordinance'). Use expressly listed, rule not reached
- Adopted
- Ord. of 9-3-2024(1), the Zoning Ordinance Update that replaced App. B in its entirety (Municode editor's note and history notes; the ordinance text and the Board's vote of that date were not read). Ord. of 2-3-2026(1) amended the Manufacturing definition (draft Board minutes: roll call, seven members voting yes; Planning Commission 6-0 (1 absent) after its December 4, 2025 hearing). Ord. of 5-5-2026(1) is also in the I-1 and Sec. 2-2 history notes; its text was not read (the May 5, 2026 hearing item was mobile food vendors)
- Changes and status
- On the record read the 2024 update added the use: Planning Commission minutes of July 6, 2023 record staff presenting 'the option of adding Data Centers to the Zoning Ordinance update' and the Commission directing staff to allow it in I-1 'without any supplemental regulations , but require a CUP', and an ordinance adopted Sept. 3, 2024 then replaced App. B in its entirety (Municode editor's note). The adopted ordinance and Board minutes of that date and the former App. B were not read. The 2-3-2026 amendment added that storage or transformation of digital data 'shall not be considered manufacturing' and is regulated as a data center. Technology Overlay District for the Glenns area: Planning Commission, June 5, 2025, voted '6 - 0 in favor of the recommendation' to stop all current efforts; Board, July 15, 2025 (draft minutes), 'agreed by consensus' to leave things as they were; no technology overlay in App. B as codified through the Ordinance of June 2, 2026 ('technology overlay' 0 hits in Arts. 2 and 5; no such article heading). No size, acreage or megawatt figure in the Data center definition, in either table row (supplemental regulation cells blank) or in Sec. 14-3; Article 9B text was not opened (its headings name no data center section). I-1 minimum lot area 'One (1) acre'. Meeting portal (eScribe) search for 'data center' (singular only; 'data centers' and 'technology overlay' not searched): 24 results; 11 packages opened and read at their hits, 2 opened for a pattern search only, 11 not opened. In the Board packets of September 1, November 4 and November 17, 2026 (the November 17 meeting is scheduled) and the Planning Commission packets of August 6 and September 3, 2026 the term appears only in minutes (public comment and questions), a staff legislative update and bill summaries, not in a zoning item (image pages of those packets are not searchable)
- Route before the change
- not addressed
- Date of the change
- 2024-09-03
- Still to read
- Ord. of 9-3-2024(1) and the Board minutes of 9-3-2024 (not read)
- Confidence in this reading
- Medium. The position is established but one element is unresolved: the adopting ordinance, the scope, how current the text is, or the type of source.
- Source as read
- Municode: 'Codified through Ordinance of June 2, 2026. (Supp. No. 22)'; version banner Oct 13, 2026; no adopted-not-codified list seen on the code's title page. Read Nov. 14, 2026.
By right means the ordinance permits the use with no rezoning and no special permit. The state site assessment is the one in Va. Code § 15.2-2209.5. It applies to a new facility expected to need 100 megawatts or more when the approval is a rezoning, special exception or special use permit. This is a dated reading, current through Nov. 19, 2026. Ordinances change; read the cited provision before relying on it. From the dataset Virginia Data Center Entitlement Route Register, version 1.1, a record of how each of Virginia's 133 counties and independent cities, and five of its towns, approve a data center.
This page covers only what these sources contain. A locality with little here may still have data center activity.