Tommy N. Turner

Virginia data center researcher: how each of 133 counties and cities approves one, and who pays for the grid. Independent, and updated as the record changes.

Portrait of Tommy N. Turner
Data Center LedgerFilings, minutes, orders and transcripts, logged as they are readLatest, Nov. 25: new report version →

Data Centers · By locality

Data centers in Essex County, Virginia

What the public record holds for this locality: how a data center gets approved and what to read.

Approval What to read

How a data center gets approved here

By right under a general useBy right, under a general use category that is not called a data center.

A data center is allowed by right in I-1 Light Industrial and I-2 Industrial. The ordinance has no separate data center use. The definition of "Warehousing and distribution" lists data centers among its typical uses, and that use is by right in both districts. It is not permitted in A-1, A-2, R-1, R-2, R-3, R-4, MH-1, PUD, B-1 or B-2. No size or power threshold applies, and the zoning administrator approves the site plan unless a rezoning or conditional use permit is involved.

No county document applying the Warehousing and distribution definition by name was found in a BoardDocs phrase search, which returned no file dated 2025 or 2026. At a June 9, 2026 Board work session on a pending A-2 to I-1 rezoning, a supervisor said land zoned I could take solar and data centers, and staff confirmed that I zoning opens the uses the county permits there. The Board remanded that rezoning over the list of uses available in I-1. It was on the Nov. 4, 2026 agenda, and the outcome was not read.

State site assessment
Not triggered on at least one route. A data center can be approved here, in at least one district or set of parcels, with no rezoning, special exception or special use permit. Other routes in the same locality may require one.
The register entry this is drawn from, in the dataset's own shorthand
Position
BY RIGHT via use-type definition (Warehousing and distribution lists 'data centers' as a typical use)
Where
I-1 Light Industrial, I-2 Industrial (B, by right); not permitted in A-1, A-2, R-1, R-2, R-3, R-4, MH-1, PUD, B-1, B-2
What the ordinance calls the use
Warehousing and distribution (Sec. 36.746 definition: typical uses include 'data centers'); no stand-alone data center use
Provision
County Code Ch. 36 Zoning & Subdivision Ord.: def Sec. 36.746; use matrix Art. V (printed p. 80 of 198); Sec. 36.310(c); site plan Sec. 36.181(b)-(c); Art. VI (Secs. 36.315 to 36.423) read, no standard for the use
If the use is not listed
DEFAULT PROHIBITION (Sec. 36.310(c): 'All uses not specifically permitted or permitted with approval of a conditional use permit are prohibited'); use named inside the Warehousing and distribution definition, rule not reached
Adopted
Ch. 36 adopted 10-11-2022, effective 11-10-2022 (County PDF cover); Municode codified through Ordinance No. 22-011, enacted October 11, 2022 (whether 22-011 is the adopting ordinance not confirmed)
Changes and status
Row follows the text. The Board's record is consistent with it: at the 6-9-2026 work session, on a pending A-2 to I-1 rezoning, a supervisor said land zoned I could take solar and data centers, and staff confirmed that I zoning opens the uses the County permits in the I district. That is not a zoning administrator determination, and no County document applying the Warehousing and distribution definition by name was found (BoardDocs phrase search, no file dated 2025 or 2026). No change found: Board of Supervisors record on BoardDocs searched for 'data center' (37 results, 17 dated 2025 or 2026, 14 read): no agenda item, ordinance, resolution, moratorium or initiated amendment on data centers; the mentions are Comprehensive Plan drafting (a new energy and data center section, 2025), EDA reports on a project at West Point, and public comment. County 'Code & Ordinance Updates' page lists one adopted Ch. 36 amendment since 2022 (Sec. 36.422 short-term rentals, 4-11-2023) and a draft wireless tower amendment (PC hearing 11-2-2026). 'Data Center Symposium' 5-20-2026: an ECCA event listed on the County calendar, not a Board or Planning Commission meeting; nothing followed in the Board's record but the 6-9-2026 remark. The Board remanded that rezoning over 'the list of uses that are available in the Industrial 1 zone'; it was on the 11-4-2026 agenda, outcome not read. No size or MW threshold in the Warehousing and distribution definition or its matrix row; Article VI (Secs. 36.315 to 36.423) has no performance standard for warehousing and distribution or data centers. Site plan approved by the Zoning Administrator unless a rezoning or CUP is involved (Sec. 36.181(b)-(c))
Still to read
Board minutes of 11-4-2026 on the remanded A-2 to I-1 rezoning over the I-1 use list (outcome not read)
Confidence in this reading
Medium. The position is established but one element is unresolved: the adopting ordinance, the scope, how current the text is, or the type of source.
Source as read
County PDF 'Adopted Oct. 11, 2022 and Effective Nov. 10, 2022'; Municode 'Codified through Ordinance No. 22-011, enacted October 11, 2022. (Supp. No. 6)'; County updates page lists Sec. 36.422 (adopted 4-11-2023) as the only adopted Ch. 36 change since. Read Nov. 14, 2026.

By right means the ordinance permits the use with no rezoning and no special permit. The state site assessment is the one in Va. Code § 15.2-2209.5. It applies to a new facility expected to need 100 megawatts or more when the approval is a rezoning, special exception or special use permit. This is a dated reading, current through Nov. 19, 2026. Ordinances change; read the cited provision before relying on it. From the dataset Virginia Data Center Entitlement Route Register, version 1.1, a record of how each of Virginia's 133 counties and independent cities, and five of its towns, approve a data center.

What to read

This page covers only what these sources contain. A locality with little here may still have data center activity.