Data Centers · By locality

Data centers in the City of Williamsburg, Virginia

What the public record holds for this locality: how a data center gets approved and what to read.

Approval What to read

How a data center gets approved here

By right under a general useBy right, under a general use category that is not called a data center.

On the text alone, a data center is allowed by right in the I Limited Industrial district, under an undefined "Data processing centers" line. No city statement on whether that line reaches a data center was found in the meeting portal's full-text search or in 69 Council and Planning Commission agendas from Jan. 9, 2025 to Nov. 18, 2026. Uses the chapter does not permit in any district are not allowed.

The city's zoning administrator wrote in an email of Nov. 18, 2026: "To date, the Zoning Administrator has not issued a determination on whether a 'data center' is a 'data processing center' under Sec. 21-382(2)." Use determinations, the administrator wrote, "are made case by case, based on the details of a specific proposal," and the city has not received a proposal of that kind. Because no determination has been made, the administrator is "not able to say" whether a data center would be a use not specifically permitted. Whether the state site assessment applies is unresolved. The register rates this entry low confidence.

Two parcels are zoned I, 31.51 acres by the city's parcel layer, and both are in existing use, a transit facility and a distribution warehouse. In the meeting portal's full-text searches and the 69 Council and Planning Commission agendas read from Jan. 9, 2025 to Nov. 18, 2026, data centers come up only as state legislation, and no text amendment was found.

State site assessment
Unresolved. It turns on a pending action or a determination not yet issued.
The register entry this is drawn from, in the dataset's own shorthand
Position
BY RIGHT on the text only (undefined 'Data processing centers' line; no city statement found that it reaches a data center, in the meeting portal's full-text search or in 69 Council and Planning Commission agendas, 1-9-2025 to 11-18-2026)
Where
I Limited Industrial (permitted use); the City's GIS shows two parcels zoned I, 31.51 acres by the parcel layer (7239 Pocahontas Trail and 201 Fifth Ave), both in existing use; no other district carries a data center or data processing line (Municode code-wide search, version Oct 8, 2026; district lists other than I not read)
What the ordinance calls the use
Data processing centers (undefined)
Provision
Ch. 21 Sec. 21-382(2); closed list Sec. 21-601; site plan Secs. 21-777(b), 21-780
If the use is not listed
DEFAULT PROHIBITION, text-amendment route (Sec. 21-601: 'Uses not specifically permitted in any district established by this chapter shall not be allowed')
Adopted
Ord. No. 862, 10-10-1991 (Sec. 21-382 history note also cites Ord. No. 08-23, 8-14-2008; which wrote line (2) not established); the City reprinted line (2) unchanged in its November 2024 redline of Division 11 (PCR #24-030)
Changes and status
No 'data center' term returned by Municode's code-wide search (version Oct 8, 2026); Art. I and Div. 11 read directly. Row follows the text (coding rule 5): Sec. 21-2 does not define 'data processing center', and no city determination, staff report or minutes saying a data center is or is not one was found. Meeting portal read 11-14-2026: full-text search for 'data center' (36 results), 'data processing' (23) and 'Limited Industrial', and 69 Council and Planning Commission agendas from 1-9-2025 to 11-18-2026; data centers arise only as state legislation (12-9-2024, 7-6-2026, 10-5-2026); no text amendment and no staff statement on Sec. 21-382(2). Two parcels are zoned I (31.51 acres, City parcel layer), a transit facility and a distribution warehouse. District I height limit 45 feet (Sec. 21-388). City website search for 'data center' returns no results. No megawatt, square-footage or acreage threshold in Secs. 21-381 to 21-387. Site plan: Administrator approves (Sec. 21-777(b), as amended by Ord. No. 25-12, 9-11-2025); district I is absent from the Sec. 21-780(6) list of districts whose permitted uses need a site plan. Zoning Administrator, email of 11-18-2026: 'To date, the Zoning Administrator has not issued a determination on whether a “data center” is a “data processing center” under Sec. 21-382(2)'; 'Use determinations are made case by case, based on the details of a specific proposal (for example, the scale of the facility, its operations, and its power and equipment needs). The City has not received a proposal of that kind.' Because no determination has been made, she is 'not able to say' whether a data center would be a use 'not specifically permitted' under Sec. 21-601. The row stays unresolved on the City's own account
Still to read
A written zoning determination on a specific proposal (none made; the City has received no such proposal, Zoning Administrator email of 11-18-2026)
Confidence in this reading
Low. An interpretive question is unanswered on the record.
Source as read
Municode version Oct 8, 2026; no adopted-not-codified list displayed; Sec. 21-384 as codified lacks the item (3) Council approved 12-12-2024 (PCR #24-030), so the codified Division 11 is not current to that action. Read Nov. 14, 2026.

By right means the ordinance permits the use with no rezoning and no special permit. The state site assessment is the one in Va. Code § 15.2-2209.5. It applies to a new facility expected to need 100 megawatts or more when the approval is a rezoning, special exception or special use permit. This is a dated reading, current through Nov. 19, 2026. Ordinances change; read the cited provision before relying on it. From the dataset Virginia Data Center Entitlement Route Register, version 1.1, a record of how each of Virginia's 133 counties and independent cities, and five of its towns, approve a data center.

What to read