Virginia data center researcher: how each of 133 counties and cities approves one, and who pays for the grid. Independent, and updated as the record changes.
Data centers in the City of Waynesboro, Virginia
What the public record holds for this locality: how a data center gets approved.
How a data center gets approved here
A data center can be allowed only if the Zoning Administrator, under the similar use determination procedure, assigns it to a use category. No use table row names a data center, so the outcome turns on the category chosen. "Data processing" appears once in the zoning chapter, undefined, as an example in the Offices category, whose business and professional offices row is permitted in R-MX, R-MF, R-O, L-B, H-B, MX-B, C-B and L-1. The row "All light industrial service uses not listed below" is permitted in MX-B, L-1 and H-1. Whether the state site assessment applies is unresolved.
No written interpretation for a data center was found in 70 City Council and Planning Commission files of 2026, and Municode's 2026 ordinance list, through Ord. No. 2026-22 of Oct. 14, 2026, shows none amending the zoning chapter. The 2025 Council and Planning Commission files were not read.
- State site assessment
- Unresolved. It turns on a pending action or a determination not yet issued.
The register entry this is drawn from, in the dataset's own shorthand
- Position
- ZONING ADMINISTRATOR SIMILAR USE DETERMINATION (Sec. 98-10.2.1.C); no Use Table row names a data center, data processing, computer or server use (Ch. 98 as codified through Ordinance No. 2026-13; use-type labels of the Public and Civic, Commercial, Industrial and Other groups read); undefined 'Data processing' is an example in the Offices use category (Sec. 98-10.2.9.C), not a Use Table row; no written interpretation for a data center found in 70 City Council and Planning Commission files of 2026 or by the city Agenda Center search for 1-1-2025 to 11-14-2026
- Where
- No district names the use; the outcome turns on the use category the Zoning Administrator assigns. Offices category, 'Business and professional offices' row: P in R-MX, R-MF, R-O, L-B, H-B, MX-B, C-B and L-1; blank in RS-12, RS-7, RS-5, RG-5 and H-1 (Use Table read cell by cell). No Use Table row names a data center. 'All light industrial service uses not listed below': P in MX-B, L-1, H-1. 'All other heavy industrial': P in H-1. Planned and overlay districts (Art. 3) not opened. Whether any land is zoned L-1, H-1 or MX-B not checked (zoning map not opened)
- What the ordinance calls the use
- (none); 'Data processing' (undefined) appears once in Ch. 98 as searched, as an example in the Offices use category, Sec. 98-10.2.9.C; not a Use Table row
- Provision
- City Code Ch. 98: Sec. 98-10.2.9.C (Offices); Sec. 98-2.4 Use Table; Sec. 98-2.4.1; Sec. 98-2.4.4; Sec. 98-10.2.1.C; Sec. 98-10.2.4; Sec. 98-7.1
- If the use is not listed
- ADMIN SIMILAR USE DETERMINATION (Sec. 98-2.4.4.B: 'Uses not listed may be allowed pursuant to the similar use determination procedure of Sec. 98-10.2.1.C'; Sec. 98-10.2.1.C.1: 'Determination of the appropriate category for a proposed principal use shall be made by the Zoning Administrator'). Sec. 98-2.4.1.C: 'A blank cell in the Use Table indicates that a use is not allowed in the respective district'
- Adopted
- Not established. Use Table history note lists 13 ordinances, Ord. No. 2012-31 (6-8-12) to Ord. No. 2025-01 (12-9-24), none read; the history note for Sec. 98-10.2.9 was not read
- Changes and status
- No change found: 'data cent' 0 hits in 70 City Council and Planning Commission files of 2026 (Council Jan 12 to Nov 9; Planning Commission Jan 20 to Nov 17; 2,783 pages, of which 828 are image pages). The city Agenda Center search for 1-1-2025 to 11-14-2026 returns no result for 'data center' or 'data centers', but its index does not reach the later 2026 meetings; 2025 files were not read. Municode's 2026 ordinance list (four ordinances, the latest Ordinance No. 2026-22 adopted 10/14/26) shows none amending Ch. 98. No city statement, written interpretation or application classifying a data center was found in those files. Municode whole-code search: 'data center' 0 results, 'data centers' 0 results, 'data processing' 2 results (Sec. 22-74(23), a business license class, and Sec. 98-10.2.9). Arts. 1, 3, 5, 6, 8 and 9 of Ch. 98 and Secs. 98-7.2 to 98-7.16 are covered by that search only. No megawatt term in Arts. 2, 4 and 10 ('megawatt' 0 hits in each); the chapter as searched has no data center provision to carry a size threshold; district dimensional standards not read. Site plan: the Zoning Administrator decides minor and major site plans, and the Site Review Team reviews major ones (Sec. 98-7.1 table; the minor and major definitions in Sec. 98-7.7 not read); a Certificate of Appropriateness, where one applies, is decided by the Planning Commission (same table)
- Still to read
- 2025 City Council and Planning Commission files (not read)
- Confidence in this reading
- Medium. The position is established but one element is unresolved: the adopting ordinance, the scope, how current the text is, or the type of source.
- Source as read
- Municode: 'Codified through Ordinance No. 2026-13, enacted June 8, 2026. (Supp. No. 71, Update 1)'; page also prints 'VERSION: JUL 23, 2026 (CURRENT)'; Municode 2026 ordinance list through Ordinance No. 2026-22 (adopted 10/14/26), none amending Ch. 98. Read Nov. 14, 2026.
By right means the ordinance permits the use with no rezoning and no special permit. The state site assessment is the one in Va. Code § 15.2-2209.5. It applies to a new facility expected to need 100 megawatts or more when the approval is a rezoning, special exception or special use permit. This is a dated reading, current through Nov. 19, 2026. Ordinances change; read the cited provision before relying on it. From the dataset Virginia Data Center Entitlement Route Register, version 1.1, a record of how each of Virginia's 133 counties and independent cities, and five of its towns, approve a data center.
This page covers only what these sources contain. A locality with little here may still have data center activity.