Virginia data center researcher: how each of 133 counties and cities approves one, and who pays for the grid. Independent, and updated as the record changes.
Data centers in the City of Suffolk, Virginia
What the public record holds for this locality: how a data center gets approved, who is building, and what to read.
Approval Who is building What to read
How a data center gets approved here
Data centers are expressly prohibited in every zoning district. City Council approved the amendment 8-0 on Oct. 21, 2026. Council had directed it on June 17, 2026, and the Planning Commission held its hearing Sept. 15, 2026.
The text read for the register is the Planning Commission packet version. It carries no sunset or expiry clause, although press reports called the measure temporary. The version that went to Council sits on scanned pages and was not read. The ordinance number is not established.
- State site assessment
- Does not arise. No approval route currently exists.
The register entry this is drawn from, in the dataset's own shorthand
- Position
- EXPRESSLY PROHIBITED, ALL DISTRICTS
- Where
- none (Table 406-1 Data center row: dash in every district)
- What the ordinance calls the use
- Data center
- Provision
- UDO Sec. 31-406(c), Table 406-1 (Data center row: a dash, meaning prohibited, in every district cell); Appendix A DATA CENTER definition; TRUCKING TERMINAL and WAREHOUSING definitions amended to exclude DATA CENTER (OTA2026-008)
- If the use is not listed
- ADMIN DETERMINATION, NAICS+ITE bound (Sec. 31-406(b)) [not re-read 11-4-2026; moot now that the use is listed]
- Adopted
- OTA2026-008, Approved 8-0 by City Council 10-21-2026 (City marked agenda); ordinance number not established; minutes not posted
- Changes and status
- Council on 6-17-2026 (City staff report) directed a UDO amendment to prohibit data centers in all zoning districts. PC hearing 9-15-2026 (advertised under Va. Code 15.2-2204). Council approved OTA2026-008 8-0 on 10-21-2026. Text read is the PC-packet version; it carries no sunset or expiry clause, although press called the measure temporary. The version before Council sits on scanned packet pages and was not read.
- Route before the change
- By right on an administrator's determination
- Date of the change
- 2026-10-21
- Still to read
- OTA2026-008 as placed before Council 10-21-2026 (scanned packet pages 14 to 210, not read)
- Confidence in this reading
- Medium. The position is established but one element is unresolved: the adopting ordinance, the scope, how current the text is, or the type of source.
- Source as read
- not verified (codification of OTA2026-008 not checked). Read Nov. 4, 2026.
By right means the ordinance permits the use with no rezoning and no special permit. The state site assessment is the one in Va. Code § 15.2-2209.5. It applies to a new facility expected to need 100 megawatts or more when the approval is a rezoning, special exception or special use permit. This is a dated reading, current through Nov. 19, 2026. Ordinances change; read the cited provision before relying on it. From the dataset Virginia Data Center Entitlement Route Register, version 1.1, a record of how each of Virginia's 133 counties and independent cities, and five of its towns, approve a data center.
Who is building here: the public record
No data center site appears for the City of Suffolk in the free state and federal records searched. The records below are placed in this locality but name no data center site, current through Nov. 22, 2026. Records are grouped under one site only where their own text links them: a site code, street address, project or campus name, notice number or named company. A record with no such link is listed on its own. Names are as each record prints them. A site missing here may still be planned: these sources miss projects that have no permit yet and code names no record ties to a company. From the dataset Who Is Building It: Virginia Data Center Sites in the Public Permit Record, which has every record, the grouping rules and what the sources do not show.
City-wide records
Filings that name no site, state grants, and State Corporation Commission cases placed in this locality.
- SCC case PUR-2023-00203 · Virginia Electric and Power Company - Application for Approval and Certification of Electric Transmission Facilities: Suffolk - Structure #246/94 230 kV Line #246 Virginia Rebuild Project · VIRGINIA ELECTRIC AND POWER CO
- SCC case PUR-2025-00104 · Virginia Electric and Power Company - For approval and certification of electric transmission facilities: 500 kV Septa-Yadkin Line #579 Rebuild and 230 kV Suffolk-Thrasher Line #2110 Partial Rebuild · VIRGINIA ELECTRIC AND POWER CO
- SCC case PUR-2019-00078 · Virginia Electric and Power Company d/b/a Dominion Virginia Power - For Approval and Certification of Electric Facilities Suffolk-Swamp 230 kV Transmission Line #247 Virginia Rebuild Project · VIRGINIA ELECTRIC AND POWER CO
Sources: DEQ's active construction stormwater list, EPA ECHO (water and air), Virginia Permit Transparency, Corps of Engineers Norfolk District public notices, State Corporation Commission dockets and VEDP incentive reports.
What to read
- Report: Who Showed Up. A census of the organizations around data center siting in Virginia, 2014 to 2026.
This page covers only what these sources contain. A locality with little here may still have data center activity.