Virginia data center researcher: how each of 133 counties and cities approves one, and who pays for the grid. Independent, and updated as the record changes.
Data centers in the City of Roanoke, Virginia
What the public record holds for this locality: how a data center gets approved and what to read.
How a data center gets approved here
A data center needs a special exception and is allowed only in IPUD, a planned unit development district that has to be reached by rezoning. City Council added the use, its definition and its standards on July 6, 2026 (Ord. No. 43434). The standards cover public water and sewer, closed-loop cooling, setbacks and an infrastructure impact study.
A separate use, "Data processing facility," covers data processed by employees. It is permitted in I-1, INPUD and IPUD and needs a special exception in CG, CLS, D, UF and UC.
The Council vote was unanimous according to press reports. The tally was not confirmed from minutes.
- State site assessment
- Triggered. Approval here generates a rezoning, special exception or special use permit.
The register entry this is drawn from, in the dataset's own shorthand
- Position
- SPECIAL EXCEPTION, IPUD only (PUD district reached by rezoning)
- Where
- IPUD only (S); not permitted in any other district (Article 3 use tables: one "data cent" hit, the IPUD row)
- What the ordinance calls the use
- Data center
- Provision
- Ch.36.2 Sec. 36.2-327 use table (IPUD 'S'); stds Sec. 36.2-407.3; def App. A
- If the use is not listed
- DEFAULT PROHIBITION (table legends Secs. 36.2-311, 36.2-322: 'any use not listed in this table is not permitted') - use listed, rule not reached
- Adopted
- Ord. No. 43434, 7-6-2026 (from the Municode history notes; adopting ordinance and Council minutes not read)
- Changes and status
- Use, definition and standards (public water/sewer, closed-loop cooling, setbacks, infrastructure impact study) added 7-6-2026 in the Council Member Initiatives package; PC staff report 4-13-2026 said the use was not adequately defined in the existing code. Separate 'Data processing facility' (data processed by employees) is P in I-1, INPUD, IPUD and S in CG, CLS, D, UF, UC. Council vote tally not confirmed from minutes (press: unanimous)
- Route before the change
- not addressed
- Date of the change
- 2026-07-06
- Still to read
- Council minutes of 7-6-2026 (vote tally not retrieved)
- Confidence in this reading
- Medium. The position is established but one element is unresolved: the adopting ordinance, the scope, how current the text is, or the type of source.
- Source as read
- Ordinance No. 43434, enacted July 6, 2026 (Supp. No. 94). Read Nov. 4, 2026.
By right means the ordinance permits the use with no rezoning and no special permit. The state site assessment is the one in Va. Code § 15.2-2209.5. It applies to a new facility expected to need 100 megawatts or more when the approval is a rezoning, special exception or special use permit. This is a dated reading, current through Nov. 19, 2026. Ordinances change; read the cited provision before relying on it. From the dataset Virginia Data Center Entitlement Route Register, version 1.1, a record of how each of Virginia's 133 counties and independent cities, and five of its towns, approve a data center.
What to read
- Report: Who Showed Up. A census of the organizations around data center siting in Virginia, 2014 to 2026.
- Report: Botetourt County case study. On June 24, 2025, Botetourt County announced that Google had bought 312.55 acres of the county's flagship business park at Greenfield for $14,055,406.37, plus $4 million for county initiatives.
This page covers only what these sources contain. A locality with little here may still have data center activity.