Virginia data center researcher: how each of 133 counties and cities approves one, and who pays for the grid. Independent, and updated as the record changes.
Data centers in the City of Richmond, Virginia
What the public record holds for this locality: how a data center gets approved and what to read.
How a data center gets approved here
A data center is allowed by right in the M-2 Heavy Industrial district, under a catch-all that permits any use not permitted in another district except 18 listed purposes that need City Council authorization. A data center is not among them. In M-1 it would be allowed only if found a similar use, which is not established. The code names no data center use and no city determination was read, so the register follows the text. The site plan is approved by the Director of Planning and Development Review.
The city's Code Refresh would end that. Public Review Draft #3, dated Aug. 17, 2026, defines a data center and marks it not allowed in every cell of its use-table row, and a city release that day lists the elimination of by-right data center development throughout the city. Draft #2, of Nov. 18, 2025, had allowed it by conditional use permit in IL and IH. The draft has not been introduced, and the city's page shows introduction and adoption as to be determined.
- State site assessment
- Not triggered on at least one route. A data center can be approved here, in at least one district or set of parcels, with no rezoning, special exception or special use permit. Other routes in the same locality may require one.
The register entry this is drawn from, in the dataset's own shorthand
- Position
- BY RIGHT in M-2 under a permissive catch-all (no data center use named in the code in force); follows the text, no City determination read
- Where
- M-2 Heavy Industrial (Sec. 30-454.1(2)); M-1 Light Industrial only if found a 'similar' use under Sec. 30-452.1(2) (not established)
- What the ordinance calls the use
- (none)
- Provision
- City Code Ch. 30 Zoning: Sec. 30-454.1(2) (M-2); Sec. 30-452.1 (M-1); Sec. 30-438.1 (B-3 list M-1 incorporates); Sec. 30-300; defs Sec. 30-1220 (no data term); site plan Secs. 30-1030.3, 30-1030.4(e)
- If the use is not listed
- PERMISSIVE CATCH-ALL in M-2 (Sec. 30-454.1(2): 'Any use or structure not permitted in any other district', except 18 listed purposes that need City Council authorization; a data center is not among them). Sec. 30-300 requires conformity with the district regulations; no general unlisted-use section found in Art. III. M-1 adds 'any similar uses' (Sec. 30-452.1(2)). District lists read: B-3, RP, M-1, M-2; all 347 pages of Ch. 30 in the Code adopted 7-27-2026 term-searched, no data center, data processing or computing use named in any district
- Adopted
- Sec. 30-454.1 history note runs from Code 1993 to Ord. No. 2012-234-2013-2, 1-14-2013; which enactment created the catch-all was not traced. Section carried unchanged into the Code of the City of Richmond, 2026 (Ord. No. 2026-160, introduced 6-22-2026, adopted 7-27-2026, 9-0). No data center ordinance, resolution or moratorium found in the code as codified through Ord. No. 2025-207, among the 16 adopted-not-codified titles through 10-13-2026, or in Council's Legistar record (phrases 'data center' and 'data centers', text and attachments, 2025 and 2026, searched 11-14-2026)
- Changes and status
- Row follows the text: no zoning administrator determination, staff report or Council record classifying a data center was found (Legistar phrase searches for 2025 and 2026; rva.gov site search; the Zoning Administration page lists no determinations). Council record 1-1-2025 to 11-14-2026: no data center ordinance, resolution or moratorium; one direction to staff, at the 7-13-2026 legislative retreat ('Council lobbyists and staff were directed to track federal and state developments'), which is not a zoning directive. PENDING: Code Refresh 'Public Review Draft #3' (8-17-2026) defines 'Data center' and marks it not allowed in all 21 cells of the extracted use-table row; Draft #2 (11-18-2025) had a conditional use permit in IL and IH. City release 8-17-2026 lists 'Elimination of data center development by right, throughout the City' as a first-time provision. Not introduced: City Code Refresh page read 11-14-2026 shows City Attorney review, introduction and adoption all 'TBD', and no Code Refresh ordinance is among the 63 Legistar records the phrase returned for 2026. Draft is not law. No size or MW threshold in force (Ch. 30 as adopted 7-27-2026 searched for the data terms). Site plan approved by the Director of Planning and Development Review (Sec. 30-1030.4(e)(2))
- Still to read
- Code Refresh ordinance (introduction and adoption 'TBD' on the City page read 11-14-2026)
- Confidence in this reading
- Medium. The position is established but one element is unresolved: the adopting ordinance, the scope, how current the text is, or the type of source.
- Source as read
- Municode: 'Recodification codified through Ordinance No. 2025-207, adopted October 14, 2025'. That recodification is the Code of the City of Richmond, 2026, adopted by Ord. No. 2026-160 on 7-27-2026 (read: Secs. 30-452.1 and 30-454.1 keep their numbers and text; the City Attorney's summary of updates names Chs. 2, 9, 17, 19, 21 and 26, not Ch. 30). 16 adopted-not-codified items through Ord. No. 2026-081 (10-13-2026), one title citing Ch. 30 (Ord. No. 2025-265, Sec. 30-930.9), none on data centers. Read Nov. 14, 2026.
By right means the ordinance permits the use with no rezoning and no special permit. The state site assessment is the one in Va. Code § 15.2-2209.5. It applies to a new facility expected to need 100 megawatts or more when the approval is a rezoning, special exception or special use permit. This is a dated reading, current through Nov. 19, 2026. Ordinances change; read the cited provision before relying on it. From the dataset Virginia Data Center Entitlement Route Register, version 1.1, a record of how each of Virginia's 133 counties and independent cities, and five of its towns, approve a data center.
What to read
- Book: Governing the Demand Shock. A comparison of how Virginia localities handled the arrival of data centers.
- Report: Who Showed Up. A census of the organizations around data center siting in Virginia, 2014 to 2026.
- Report: Chesterfield County case study. Chesterfield built its data-center strategy on a single number: the equipment tax rate set at $0.24/$100 in April 2019 — a deliberate undercut of Henrico's $0.40 and the lowest in Virginia. Google assembled roughly 1,640 acres, Chirisa committed $2 billion, and Commonwealth Fusion Systems selected Battery Brooke for the world's first grid-scale commercial fusion plant. The rate is locked for thirty years.
This page covers only what these sources contain. A locality with little here may still have data center activity.