Data centers in the City of Norfolk, Virginia
What the public record holds for this locality: how a data center gets approved, who is building, and what to read.
Approval Who is building What to read
How a data center gets approved here
A data center is allowed by right where "Office" is permitted, because the city classes its existing data centers as offices. The planning director told City Council on Nov. 10, 2026 that two colocation data centers, about 35,000 and 8,000 square feet in space shared with other tenants, exist under the office use in BC-I and BC-O, and that large-scale data centers with significant impacts do not. Office is permitted in many districts, including I-L and I-G, and not in I-W or I-DW. Whether it reaches a stand-alone large facility is not settled on the record.
A text amendment to define the data center use is pending. The Planning Commission initiated it 6-0 on Aug. 27, 2026 and recommended approval 4-0 on Oct. 22, 2026. Per the director's slides, a small-scale data center (30,000 square feet or less, or under 25 megawatts) would be by right in O, BC-I, BC-O, I-L, I-G and IN-C, and a larger one would need a conditional use permit in I-G, I-DW and BC-O and a fourth district printed as "BI - I". No Council hearing or vote was found through the Nov. 10, 2026 agenda, and the draft text was not read.
- State site assessment
- Not triggered on at least one route. A data center can be approved here, in at least one district or set of parcels, with no rezoning, special exception or special use permit. Other routes in the same locality may require one.
The register entry this is drawn from, in the dataset's own shorthand
- Position
- BY RIGHT as 'Office' (City's stated practice for two small colocation facilities); data center text amendment pending
- Where
- 'Office' is P in C-N, C-C, C-R, O, BC-O, BC-I; D-W, D-BC, D-MU, D-AD, D-FN, D-SP; I-L, I-G; HC-G3, HC-WF1, HC-WF2, HC-EF; IN, IN-C, A, MW, EBH, TOD-C, TOD-S, G-1; the five PCO overlays; C in MF-AC and MF-HR; blank in I-W and I-DW. City record places the two existing facilities in BC-I and BC-O
- What the ordinance calls the use
- Office (definition lists 'data processing facilities'). Pending: 'Data Center, Small Scale' and 'Data Center, Large Scale'
- Provision
- Zoning Ord. § 4.2.3.F(6)(t) (Office); Tables 3.3.9, 3.4.11, 3.5.7, 3.6.11, 3.7.13, 3.9.23, 3.2.12; § 3.1.4.A(1); § 2.4.17; site plan §§ 2.4.18, 2.3.9
- If the use is not listed
- DEFAULT PROHIBITION with ZA INTERPRETATION (§ 3.1.4.A(1): 'Any use that is not listed in a use table is prohibited.'; § 2.4.17.D(2): a use interpretation may permit only a use 'substantially similar to other uses permitted in the district', conditioned on a CUP where the nearest use is conditional). Not reached in practice: the City classes its existing data centers as Office
- Adopted
- Zoning Ordinance effective 3-1-2018 (§ 1.7.1); no data center amendment adopted (Council minutes 1-14-2025 to 10-27-2026 searched for the term; three files not covered; two term hits, 2-24 and 4-28-2026, not read in context, both before the Commission initiated the amendment on 8-27-2026)
- Changes and status
- Planning Director to City Council 11-10-2026: colocation 'data centers exist in the City under the “office” use' (two, about 35,000 sf in BC-I and 8,000 sf in BC-O, each in space shared with other tenants); 'large - scale data centers with significant impacts do not' (spacing as extracted). Row follows that practice (codebook rule 5); whether Office reaches a stand-alone large facility is not settled on the record. PENDING: CPC initiated a text amendment 'to define the Data Center use and apply applicable performance standards' 8-27-2026 (6-0) and recommended approval 10-22-2026 (4-0). Per the Director's slides: Small Scale (30,000 sf or less, or under 25 MW) by right in O, BC-I, BC-O, I-L, I-G, IN-C; Large Scale (over 30,000 sf, or 25 MW or more) by CUP in I-G, I-DW, 'BI - I' (as printed), BC-O. No Council hearing or vote found through the 11-10-2026 agenda; draft text not read. Site plans are approved administratively by the ZA (§ 2.3.9)
- Still to read
- draft text amendment defining the Data Center use (Commission recommended approval 10-22-2026; text not read)
- Confidence in this reading
- Medium. The position is established but one element is unresolved: the adopting ordinance, the scope, how current the text is, or the type of source.
- Source as read
- City HTML edition prints no codified-through line; § 1.7.1 effective March 1, 2018; latest date in the text June 1, 2026; ordinance files dated 19 Oct 2026 (server file date). Read Nov. 14, 2026.
By right means the ordinance permits the use with no rezoning and no special permit. The state site assessment is the one in Va. Code § 15.2-2209.5. It applies to a new facility expected to need 100 megawatts or more when the approval is a rezoning, special exception or special use permit. This is a dated reading, current through Nov. 19, 2026. Ordinances change; read the cited provision before relying on it. From the dataset Virginia Data Center Entitlement Route Register, version 1.1, a record of how each of Virginia's 133 counties and independent cities, and five of its towns, approve a data center.
Who is building here: the public record
1 data center site in the permit record for the City of Norfolk, grouped by site only where the records themselves link them, so one campus can appear as more than one site.
Data center sites found in the free state and federal records searched for the City of Norfolk, and utility filings placed in the same locality, current through Nov. 22, 2026. Records are grouped under one site only where their own text links them: a site code, street address, project or campus name, notice number or named company. A record with no such link is listed on its own. Names are as each record prints them. A site missing here may still be planned: these sources miss projects that have no permit yet and code names no record ties to a company. From the dataset Who Is Building It: Virginia Data Center Sites in the Public Permit Record, which has every record, the grouping rules and what the sources do not show.
EDGE CONNEX DATA CENTER 1 record
- Air permit VA0000005171000297 · EDGE CONNEX DATA CENTER
Sources: DEQ's active construction stormwater list, EPA ECHO (water and air), Virginia Permit Transparency, Corps of Engineers Norfolk District public notices, State Corporation Commission dockets and VEDP incentive reports.
What to read
- Report: Two Systems, One Drought. Virginia's coastal aquifer is capacity-bound; its river system is drought-stressed. The Commonwealth is solving a problem in one by adding to the other, and the data-center buildout is arriving before that trade has been priced.
This page covers only what these sources contain. A locality with little here may still have data center activity.