Data centers in the City of Lynchburg, Virginia

What the public record holds for this locality: how a data center gets approved and who is building.

Approval Who is building

How a data center gets approved here

Permit requiredA discretionary permit is required: a conditional or special use permit, a special exception or a provisional use permit.

A data center needs a conditional use permit in I-1, I-2, I-3 and IN-2. City Council adopted the change 7-0 on July 14, 2026 (Ord. O-26-072) and removed the use from B-1, B-3, B-4 and B-5. Before that, according to city staff, data centers were permitted by right in those four districts and in IN-2, I-1, I-2 and I-3. The Planning Commission recommended the change 7-0 on May 27, 2026.

The online code has not yet been updated. No later data center item was found in the Council agendas and minutes read for Aug. 25 to Oct. 27, 2026.

State site assessment
Triggered. Approval here generates a rezoning, special exception or special use permit.
The register entry this is drawn from, in the dataset's own shorthand
Position
CONDITIONAL USE PERMIT
Where
I-1, I-2, I-3, IN-2 (CUP); removed from B-1, B-3, B-4, B-5
What the ordinance calls the use
Data center (LBCS 4244a)
Provision
Sec. 35.2-72.29; def Sec. 35.2-113; district lists Secs. 35.2-50.2 to 35.2-53.2; App. A
If the use is not listed
ADMIN DETERMINATION (Sec. 35.2-34.2(a)): substantially similar use, else 'that use shall be prohibited'; rule not reached (use named)
Adopted
Ord. O-26-072, adopted 7-14-2026, 7-0
Changes and status
Staff summary: before O-26-072 data centers 'permitted by right under LBCS 4244' in B-1, B-3, B-4, B-5, IN-2, I-1, I-2, I-3. PC recommended 7-0 on 5-27-2026. Not yet codified on Municode (version Jul 25, 2025). No later data center item in Council agendas/minutes 8-25 to 10-27-2026 read
Route before the change
by right (form not established)
Date of the change
2026-07-14
Still to read
Enrolled, signed Ord. O-26-072 (not read)
Confidence in this reading
High. Ordinance text read directly, citation verified, the position unambiguous.
Source as read
Municode 'VERSION: JUL 25, 2025 (CURRENT)' (pre-amendment); adopted ordinance read in Council packet 7-14-2026. Read Nov. 4, 2026.

By right means the ordinance permits the use with no rezoning and no special permit. The state site assessment is the one in Va. Code § 15.2-2209.5. It applies to a new facility expected to need 100 megawatts or more when the approval is a rezoning, special exception or special use permit. This is a dated reading, current through Nov. 19, 2026. Ordinances change; read the cited provision before relying on it. From the dataset Virginia Data Center Entitlement Route Register, version 1.1, a record of how each of Virginia's 133 counties and independent cities, and five of its towns, approve a data center.

Who is building here: the public record

1 data center site in the permit record for the City of Lynchburg, grouped by site only where the records themselves link them, so one campus can appear as more than one site.

Data center sites found in the free state and federal records searched for the City of Lynchburg, and utility filings placed in the same locality, current through Nov. 22, 2026. Records are grouped under one site only where their own text links them: a site code, street address, project or campus name, notice number or named company. A record with no such link is listed on its own. Names are as each record prints them. A site missing here may still be planned: these sources miss projects that have no permit yet and code names no record ties to a company. From the dataset Who Is Building It: Virginia Data Center Sites in the Public Permit Record, which has every record, the grouping rules and what the sources do not show.

Sources: DEQ's active construction stormwater list, EPA ECHO (water and air), Virginia Permit Transparency, Corps of Engineers Norfolk District public notices, State Corporation Commission dockets and VEDP incentive reports.