Virginia data center researcher: how each of 133 counties and cities approves one, and who pays for the grid. Independent, and updated as the record changes.
Data centers in the City of Harrisonburg, Virginia
What the public record holds for this locality: how a data center gets approved and who is building.
How a data center gets approved here
A data center needs a special use permit and is allowed only in M-1 General Industrial. The ordinance defines the use, and no size or power threshold appears in the definition (§ 10-3-24) or the M-1 listing (§ 10-3-97(17)). The body that decides the permit was not read.
Before 2025, a staff memorandum of Jan. 14, 2025 says, a data center was interpreted to be permitted within the broader warehousing and storage use. That made it by right in M-1 and in B-2 up to 20,000 square feet, and by special use permit in B-2 above that size and in B-1. The Planning Commission recommended the amendment 6-0 on Dec. 11, 2024. City Council approved it on first reading Jan. 14, 2025, by five yes votes, and on second reading Jan. 28, 2025. The warehousing lines were left as they were. The register follows the position in a staff memorandum and the Planning Commission minutes that the amendment calls data centers out as their own use. The executed ordinance is a scan and was not read.
A zoning ordinance update is in public review. Its draft of Oct. 7, 2026, marked not adopted, lists data centers in its use table, and comments close Nov. 30, 2026. One existing data center, at 139 Tyco Street, is zoned M-1, according to the staff memorandum.
- State site assessment
- Triggered. Approval here generates a rezoning, special exception or special use permit.
The register entry this is drawn from, in the dataset's own shorthand
- Position
- SPECIAL USE PERMIT (deciding body not read; Art. V term-searched only)
- Where
- M-1 General Industrial only, by special use permit. Term search of all 37 articles of Title 10 Ch. 3 (codified through Supp. No. 60, Update No. 2) finds 'data centers' only in § 10-3-24 and § 10-3-97; the B-1 and B-2 use sections were read only at their warehousing lines, other districts' use lists were not read one by one
- What the ordinance calls the use
- Data centers (defined, § 10-3-24)
- Provision
- City Code Title 10 Ch. 3 § 10-3-97(17) (M-1, 'permitted by special use permit only'); def § 10-3-24
- If the use is not listed
- CONFORMITY, § 10-3-12(1) (no use 'except in conformity with the regulations herein specified for the district'); Board of Zoning Appeals classifies 'any use not specifically named', in keeping with uses specifically permitted in the district (§ 10-3-135(4)). Use expressly listed, rule not reached
- Adopted
- Legistar ID 24-432: approved on first reading 1-14-2025 (five Yes), approved on second reading 1-28-2025 (no roll call shown in Legistar); codified history 'Ord. of 1-28-25(2)'. Planning Commission recommended approval 12-11-2024 (6-0 per staff memorandum). Executed ordinance is a scan, not read
- Changes and status
- Before: staff memorandum of 1-14-2025 says a data center was 'interpreted to be permitted within a broader “warehousing and storage” use' category: by right in M-1 (§ 10-3-96(2)), by right in B-2 with a 20,000 square foot limit, by SUP in B-2 without a size limit and by SUP in B-1. The amendment added the definition and listed data centers only in the M-1 special use list; the warehousing lines (§§ 10-3-85(10), 10-3-90(12), 10-3-91(2), 10-3-96(2)) were left as they were. Asked at the Planning Commission 12-11-2024 whether the amendment removed the B-1, B-2 and M-1 readings or whether they needed to be removed explicitly, Mr. Fletcher 'said this calls it out as its own use' (extract of the Planning Commission minutes of 12-11-2024); the memorandum states the purpose as adding data centers 'to only be allowed by special use permit' in M-1. Row follows that documented position (rule 5); it rests on those two statements. No size or megawatt threshold in § 10-3-24 or § 10-3-97(17). One existing data center, 139 Tyco Street, zoned M-1 (staff memorandum). PENDING: Zoning Ordinance Update Project, public review draft with a running header dated October 7, 2026 and marked 'NOT ADOPTED', whose use table row 'Data Center' shows one 'S' cell (column not read); comment period ends November 30, 2026. Legistar legislation search, All Years, 11-14-2026: 'data centers' returns only ID 24-432; council and commission minutes for 2025 and 2026 not opened
- Route before the change
- By right under a general use
- Date of the change
- 2025-01-28
- Still to read
- executed ordinance, Legistar ID 24-432, second reading 1-28-2025 (a scan, not read)
- Confidence in this reading
- Medium. The position is established but one element is unresolved: the adopting ordinance, the scope, how current the text is, or the type of source.
- Source as read
- Municode 'Codified through Ordinance of August 11, 2026 (2). (Supp. No. 60, Update No. 2)', read through the codifier's content service because the library page did not load; City 'Recently Adopted Ordinances' page lists 'Supplemental 60 Update 3' items, none naming data centers by title (files not opened). Read Nov. 14, 2026.
By right means the ordinance permits the use with no rezoning and no special permit. The state site assessment is the one in Va. Code § 15.2-2209.5. It applies to a new facility expected to need 100 megawatts or more when the approval is a rezoning, special exception or special use permit. This is a dated reading, current through Nov. 19, 2026. Ordinances change; read the cited provision before relying on it. From the dataset Virginia Data Center Entitlement Route Register, version 1.1, a record of how each of Virginia's 133 counties and independent cities, and five of its towns, approve a data center.
Who is building here: the public record
1 data center site in the permit record for the City of Harrisonburg, grouped by site only where the records themselves link them, so one campus can appear as more than one site.
Data center sites found in the free state and federal records searched for the City of Harrisonburg, and utility filings placed in the same locality, current through Nov. 22, 2026. Records are grouped under one site only where their own text links them: a site code, street address, project or campus name, notice number or named company. A record with no such link is listed on its own. Names are as each record prints them. A site missing here may still be planned: these sources miss projects that have no permit yet and code names no record ties to a company. From the dataset Who Is Building It: Virginia Data Center Sites in the Public Permit Record, which has every record, the grouping rules and what the sources do not show.
ROCKINGHAM MEMORIAL HOSPITAL DATA CENTER 1 record
- Air permit VA0000005166000167 · ROCKINGHAM MEMORIAL HOSPITAL DATA CENTER
City-wide records
Filings that name no site, state grants, and State Corporation Commission cases placed in this locality.
- SCC case PUR-2024-00074 · Virginia Electric and Power Company - For Approval and Certification of Electric Transmission Facilities: Dooms-Harrisonburg 230 kV Lines #260 and #272 Rebuild Project · VIRGINIA ELECTRRIC AND POWER C
Sources: DEQ's active construction stormwater list, EPA ECHO (water and air), Virginia Permit Transparency, Corps of Engineers Norfolk District public notices, State Corporation Commission dockets and VEDP incentive reports.
This page covers only what these sources contain. A locality with little here may still have data center activity.