Data Centers · By locality

Data centers in the City of Galax, Virginia

What the public record holds for this locality: how a data center gets approved.

Approval

How a data center gets approved here

No approval routeThe use is unlisted and prohibited, or no route permits it.

No district lists a data center, and the district use lists are closed, so an unlisted use is prohibited. On the text read, a data center would need an amendment to the zoning chapter. One other path is possible. The definition of manufacturing lets the Planning Commission classify other activities as manufacturing, though manufacturing is not itself a use item in the M-1 or M-2 lists, and no city record read applies that clause.

The register rates this entry low confidence. City Council minutes from Jan. 13, 2025 to Nov. 10, 2025 are image scans and were not read, and no Planning Commission agendas or minutes were found. Whether the posted chapter is current is not established. Council approved an ordinance with zoning limitations on recreational substance retail establishments on April 13, 2026, and the posted chapter carries no amendment after Oct. 14, 2019.

State site assessment
Does not arise. No approval route currently exists.
The register entry this is drawn from, in the dataset's own shorthand
Position
UNLISTED = PROHIBITED (closed district use lists; no administrator similar-use power found in Ch. 160 by whole-chapter term search; the Sec. 160-11 definition of 'MANUFACTURING' lets the Planning Commission classify 'other activities' as manufacturing, a word that is not a use item in the M-1 or M-2 lists read)
Where
n/a. M-1 (Secs. 160-106, 160-107) and M-2 (Secs. 160-116, 160-117) lists and the B-2 permitted list (Sec. 160-92) read in full: no data center, data processing, computer or server line. The residential, B-1, B-3, B-4 and R-5 lists and the B-2 conditional list (Sec. 160-93) were not read line by line; they are covered by a whole-chapter term search (the single 'data' hit in Ch. 160 is a home occupation line). Whether any land is zoned M-1 or M-2 not checked (zoning map not opened)
What the ordinance calls the use
(none)
Provision
City Code Ch. 160 Sec. 160-142: 'No building, structure or land shall hereafter be used or occupied ... except in conformity with all of the regulations herein specified for the district in which it is located'; M-1 Sec. 160-106; M-2 Sec. 160-116; amendments Sec. 160-13; Sec. 160-11 'MANUFACTURING'
If the use is not listed
DEFAULT PROHIBITION (Sec. 160-142 conformity; district lists read 'Uses permitted shall be one or more of the following uses'). No administrator similar-use or classification power found in Ch. 160 (whole chapter searched: 'not listed' 0, 'unlisted' 0, 'not provided for' 0; all 26 'similar' hits displayed, none a similar-use clause; the 12 'interpret' hits are Sec. 160-5, the definitions lead-in, the district boundary rule of Sec. 160-19 and a Board of Zoning Appeals power to interpret 'the district map where there is any uncertainty as to the location of a district boundary'; Sec. 160-162 was read to subsection C and Sec. 160-165 to subsection B). Sec. 160-11 'MANUFACTURING' definition: 'Other activities may be classified as "manufacturing" upon approval of the Planning Commission'; the word 'manufacturing' is not a use item in the M-1 or M-2 lists read
Adopted
Ch. 160 adopted 11-12-1985 (chapter history line); bracketed amendment notes in the chapter run from 6-29-1987 to 10-14-2019. No data center provision in the codified text
Changes and status
No data center term in Ch. 160 (eCode360 print view of the whole chapter, 223,281 characters: 'data cent' 0, 'datacenter' 0, 'server' 0, 'technolog' 0, 'megawatt' 0; the single 'data', 'data processing' and 'computer' hit is one home occupation line, 'Computer programming, data processing, typing and word processing service'). On the text read, a data center reaches approval by an amendment to the chapter under Sec. 160-13, or, if the clause reaches such a use, by Planning Commission classification as 'manufacturing' under the Sec. 160-11 definition, a word no M-1 or M-2 use item read uses; no City record read applies that clause. No data center item in the text pages of City Council minutes of 12-8-2025 and of 1-12-2026 to 7-22-2026, or of the agendas of 5-11, 6-8, 7-13 and 10-2-2026 ('data cent' 0 in each); the minutes of 1-13-2025 to 11-10-2025 (13 files) and of 8-10-2026 and the 9-14-2026 agenda are image scans and were not read; no minutes after 8-10-2026 were listed on the 2026 minutes page on 11-14-2026; the 2025 agendas page was not opened; no Planning Commission agendas or minutes were found (the home page link list, read by WebFetch only, shows a Planning Commission schedule page, which was not opened). No city statement on how a data center would be classified was found in those documents. Council minutes of 4-13-2026 record a unanimous vote approving an ordinance on recreational substance retail establishments with 'zoning limitations'; the eCode360 chapter has 0 hits for 'substance' and no amendment note dated after 10-14-2019, so whether Ch. 160 as posted is current is not established. No megawatt, square-footage or acreage threshold for data centers (the chapter has no data center provision)
Still to read
City Council minutes of 1-13-2025 to 11-10-2025 (image scans, not read)
Confidence in this reading
Low. An interpretive question is unanswered on the record.
Source as read
eCode360: 'Includes legislation through 08-10-2026.'; 'New Laws (0)'; latest amendment note in Ch. 160 dated 10-14-2019. Read Nov. 14, 2026.

By right means the ordinance permits the use with no rezoning and no special permit. The state site assessment is the one in Va. Code § 15.2-2209.5. It applies to a new facility expected to need 100 megawatts or more when the approval is a rezoning, special exception or special use permit. This is a dated reading, current through Nov. 19, 2026. Ordinances change; read the cited provision before relying on it. From the dataset Virginia Data Center Entitlement Route Register, version 1.1, a record of how each of Virginia's 133 counties and independent cities, and five of its towns, approve a data center.

This page covers only what these sources contain. A locality with little here may still have data center activity.