Virginia data center researcher: how each of 133 counties and cities approves one, and who pays for the grid. Independent, and updated as the record changes.
Data centers in the City of Franklin, Virginia
What the public record holds for this locality: how a data center gets approved.
How a data center gets approved here
The city's zoning ordinance, as posted through July 14, 2025, carries no data center term; a file attached to it, 'Attachment 1 - District Regulations', was not opened. When someone applies for a use that is not specifically permitted in a district, the zoning administrator refers it to the Planning Commission as a special use permit, and after hearings City Council may issue one, for a temporary period or permanently. That permit would trigger the state site assessment. The M-1 and M-2 lists carry no data center line, and Industry, Type 1, by right in both, does not list data centers. Whether the city would apply another listed use to a data center is not known.
The register rests on the ordinance text as posted through July 14, 2025. City Council and Planning Commission minutes from Jan. 1, 2025 to Nov. 14, 2026 were not read because the city website could not be opened, and the register rates this entry low confidence. A separate Technology Zones chapter, Ch. 28.5, was not opened.
- State site assessment
- Triggered. Approval here generates a rezoning, special exception or special use permit.
The register entry this is drawn from, in the dataset's own shorthand
- Position
- SPECIAL USE PERMIT for a use not provided for (City Council, after Planning Commission and Council public hearings)
- Where
- n/a by name; any district via App. D Sec. 28.9. M-1 (Secs. 11.2, 11.3) and M-2 (Secs. 12.2, 12.3) lists read: no data center, data processing, computer or server line. The residential, planned unit development, B-1, B-2, B-3 and RC lists were not read line by line; they are covered by a whole-appendix term search (all 31 'data' hits read, none a use). 'Attachment 1 - District Regulations', a file attached to App. D, was not opened. Whether any land is zoned M-1 or M-2 not checked (zoning map not opened)
- What the ordinance calls the use
- (none)
- Provision
- City Code App. D (Zoning Ordinance) Sec. 28.9(1): 'If, in any district established under this ordinance, a use is not specifically permitted and an application is made to the zoning administrator for such use, the zoning administrator shall refer the application to the planning commission as a special use permit'; M-1 Sec. 11.2; M-2 Sec. 12.2; def Sec. 29.1 'INDUSTRY, TYPE 1'
- If the use is not listed
- SPECIAL USE PERMIT ROUTE (App. D Sec. 28.9(1): referral to the Planning Commission 'as a special use permit'; after its hearing and recommendation and a Council hearing, the City Council may 'issue a special use permit for said use for a temporary period or permanently')
- Adopted
- Zoning Ordinance adopted 4-11-1994 (eCode360 note to App. D). Sec. 28.9 is marked 'Amended by Ord. 9-25-2023'; that ordinance was not read and what it changed is not established. No data center provision in the codified text
- Changes and status
- No data center term in App. D (eCode360 print view of the whole appendix, 426,789 characters: 'data cent' 0, 'datacenter' 0, 'data processing' 0, 'server' 0, 'technolog' 0, 'megawatt' 0; all 31 'data' hits read, every one flood-map or application data; the one 'computer' hit is 'Office of computer programmers' in a list of offices). 'Industry, Type 1', by right in M-1 and M-2, is defined as processing, manufacturing, assembly or fabrication of materials and products and does not list data centers; whether the City applies 'Warehousing and distribution' or 'Public utility, community' to a data center is not known; no City Council, Planning Commission or staff document was read. City Council and Planning Commission agendas and minutes from 1-1-2025 to 11-14-2026 were not read (the city website, franklinva.com, could not be opened on 11-14-2026); the row rests on the ordinance text as read (App. D as posted on eCode360 through 07-14-2025). Ordinances adopted after 07-14-2025 were not checked against a city list. City Code Ch. 28.5 'Technology Zones' is a separate chapter outside App. D and was not opened. No megawatt, square-footage or acreage threshold for data centers (App. D has no data center provision)
- Still to read
- City Council and Planning Commission minutes, 1-1-2025 to 11-14-2026 (not read; city website did not open)
- Confidence in this reading
- Low. An interpretive question is unanswered on the record.
- Source as read
- eCode360: 'Includes legislation through 07-14-2025.'; 'New Laws (0)'; latest amendment note in App. D dated 6-24-2024 ('2025' 0 hits in the appendix text); city ordinance list not read. Read Nov. 14, 2026.
By right means the ordinance permits the use with no rezoning and no special permit. The state site assessment is the one in Va. Code § 15.2-2209.5. It applies to a new facility expected to need 100 megawatts or more when the approval is a rezoning, special exception or special use permit. This is a dated reading, current through Nov. 19, 2026. Ordinances change; read the cited provision before relying on it. From the dataset Virginia Data Center Entitlement Route Register, version 1.1, a record of how each of Virginia's 133 counties and independent cities, and five of its towns, approve a data center.
This page covers only what these sources contain. A locality with little here may still have data center activity.