How a data center gets approved here
A data center is allowed by right in LM Light Manufacturing and GM General Manufacturing. The LM list names data centers without defining them, and GM takes in the LM uses. In LM a single building of 400,000 square feet or more needs a conditional use permit, and multiple buildings of one enterprise count as a single building. GM has no size limit, so in GM a data center of any size is approved with no permit that triggers the state site assessment.
No change was found in 45 City Council files from 2025 and 2026 or in the Planning Commission's files for those years. The ordinance that wrote the data center line was not established. Two earlier ordinances in the section's history, of Nov. 13, 1997 and Jan. 13, 2008, were not read. Whether any land is zoned LM or GM was not checked.
- State site assessment
- Not triggered on at least one route. A data center can be approved here, in at least one district or set of parcels, with no rezoning, special exception or special use permit. Other routes in the same locality may require one.
The register entry this is drawn from, in the dataset's own shorthand
- Position
- BY RIGHT under a building-size cap in LM (Sec. 506.00: 'Single large buildings meeting or exceeding the size limits set forth below must receive a conditional use permit'; 'Light Manufacturing LM 400,000 square feet'); GM carries no size limit ('General Manufacturing GM Unlimited square feet')
- Where
- LM Light Manufacturing (Sec. 610.02-18); GM General Manufacturing (Sec. 611.02-1 takes in 'All uses permitted in the Light Manufacturing District (LM) except' a list of named uses that does not include call centers or data centers). No other district section carries the term ('data cent' 1 hit in Art. 6, 262,402 characters; other district lists not read line by line). Whether any land is zoned LM or GM not checked (zoning map not opened)
- What the ordinance calls the use
- Call centers; data centers (undefined)
- Provision
- Land Development Regulations (City Code Part III): Sec. 610.02-18; Sec. 611.02-1; Sec. 506.00; Sec. 501.01; Sec. 610.05-1; Sec. 1504.01
- If the use is not listed
- DISTRICT CONFORMITY (Sec. 501.00: no use 'except in conformity with the regulations, herein specified for the district'); in LM a conditional use line for 'Other uses of the same general character and compatible with the foregoing permitted and conditional uses' (Sec. 610.03-10, City Council). Use expressly listed, rule not reached. No zoning administrator similar-use clause in Art. 8 ('interpret', 'similar' and 'not listed' 0 hits)
- Adopted
- Ordinance that wrote line 610.02-18 not established. Sec. 610 history note: 'Ord. of 11-13-1997; Ord. of 1-13-2008; Ord. No. 21-01, Exh. A, 3-3-2021'. Council minutes of March 4, 2021 describe ORD 21-01 as a text amendment on temporary buildings incidental to construction (the history note dates it 3-3-2021; its Exhibit A and the vote were not read); the 1997 and 2008 ordinances were not read
- Changes and status
- No change found: 'data cent' appears once in 45 City Council files dated 1.2.2025 to 11.5.2026 (minutes of 10.16.2025, a report on a Virginia Municipal League conference noting 'the growing role of data centers in local economies'; no zoning item) and not at all in the 18 files of 2025 and 2026 on the Planning Commission page (450 pages, 89 of them images). The 2026 zoning text amendment read in those council files concerns accessory dwelling units (Section 702, approved in the 7.16.2026 minutes); other text-amendment hits not read. Municode is codified through an ordinance of September 18, 2025 and lists no later ordinances; minutes after 9.17.2026 are not posted as files. No city statement or application on a data center found in those files. The ordinance that wrote line 610.02-18 was not identified: of the three ordinances in the Sec. 610 history note, the 'Ord. of 11-13-1997' and the 'Ord. of 1-13-2008' were not read, and 'Ord. No. 21-01' was read only as described in the Council minutes of March 4, 2021 (its Exhibit A and the vote were not read). Size threshold: a single building 'meeting or exceeding' 400,000 square feet in LM needs a conditional use permit (Sec. 506.00); GM is 'Unlimited square feet'; 'Multiple buildings in connection with a common commercial enterprise shall be treated as a single building' (Sec. 506.01). No megawatt threshold ('megawatt' 0 hits in Arts. 3 and 6). Site plan: 'shall be approved by the zoning administrator and planning commission' after city manager review (Sec. 1504.01); LM plans go to the zoning administrator, who 'may refer these plans to the planning commission for recommendation' (Sec. 610.05-1)
- Still to read
- Ord. of 11-13-1997 and Ord. of 1-13-2008 in the Sec. 610 history note (not read)
- Confidence in this reading
- Medium. The position is established but one element is unresolved: the adopting ordinance, the scope, how current the text is, or the type of source.
- Source as read
- Municode: 'Codified through Ordinance of September 18, 2025. (Supp. No. 12)'; page also prints 'VERSION: AUG 20, 2026 (CURRENT)'; Municode OrdBank shows no ordinances; City Council files to 11.5.2026 searched for later amendments. Read Nov. 14, 2026.
By right means the ordinance permits the use with no rezoning and no special permit. The state site assessment is the one in Va. Code § 15.2-2209.5. It applies to a new facility expected to need 100 megawatts or more when the approval is a rezoning, special exception or special use permit. This is a dated reading, current through Nov. 19, 2026. Ordinances change; read the cited provision before relying on it. From the dataset Virginia Data Center Entitlement Route Register, version 1.1, a record of how each of Virginia's 133 counties and independent cities, and five of its towns, approve a data center.