Data centers in Chesterfield County, Virginia

What the public record holds for this locality: how a data center gets approved, who is building, and what to read.

Case study: Chesterfield County, read from local packets, minutes, ordinances and agreements.

Approval Who is building What to read

How a data center gets approved here

Permit requiredA discretionary permit is required: a conditional or special use permit, a special exception or a provisional use permit.

A data center is a conditional use in the EC and EG districts only. It is not permitted in the other 12 districts in the use table. The rule took effect Jan. 1, 2026 under an ordinance adopted Sept. 17, 2025.

Under the old zoning chapter the use was by right in I-2 and C-5. The new ordinance expressly carves data centers out of its transition grandfathering. A later amendment effective Aug. 26, 2026 left the data center row unchanged as read on Nov. 4, 2026.

State site assessment
Triggered. Approval here generates a rezoning, special exception or special use permit.
The register entry this is drawn from, in the dataset's own shorthand
Position
CONDITIONAL USE
Where
EC, EG only (C); not permitted (blank) in the other 12 districts of Table 19.2-29.1
What the ordinance calls the use
Data Center
Provision
Ch.19.2 §19.2-29, Table 19.2-29.1
If the use is not listed
CONDITIONAL USE PERMIT route on Planning Director similarity finding, else not permitted (Sec. 19.2-28.E)
Adopted
Ord. 2025-18, 9-17-2025, eff. 1-1-2026
Changes and status
Was by right in I-2 and C-5 under superseded Ch.19.1. Expressly carved out of transition grandfathering. ZO-2026-003 (eff. 8-26-2026) amended Sec. 19.2-29; data center row unchanged as read 11-4-2026
Route before the change
By right
Date of the change
2025-09-17
Still to read
Board minutes of 9-17-2025 adopting Ord. 2025-18 (not read)
Confidence in this reading
Medium. The position is established but one element is unresolved: the adopting ordinance, the scope, how current the text is, or the type of source.
Source as read
Amendment History Table through SO-2026-002, eff. 10-28-2026 (no codified-through line printed). Read Nov. 4, 2026.

By right means the ordinance permits the use with no rezoning and no special permit. The state site assessment is the one in Va. Code § 15.2-2209.5. It applies to a new facility expected to need 100 megawatts or more when the approval is a rezoning, special exception or special use permit. This is a dated reading, current through Nov. 19, 2026. Ordinances change; read the cited provision before relying on it. From the dataset Virginia Data Center Entitlement Route Register, version 1.1, a record of how each of Virginia's 133 counties and independent cities, and five of its towns, approve a data center.

Who is building here: the public record

6 data center sites in the permit record for Chesterfield County, grouped by site only where the records themselves link them, so one campus can appear as more than one site.

Data center sites found in the free state and federal records searched for Chesterfield County, and utility filings placed in the same locality, current through Nov. 22, 2026. Records are grouped under one site only where their own text links them: a site code, street address, project or campus name, notice number or named company. A record with no such link is listed on its own. Names are as each record prints them. A site missing here may still be planned: these sources miss projects that have no permit yet and code names no record ties to a company. From the dataset Who Is Building It: Virginia Data Center Sites in the Public Permit Record, which has every record, the grouping rules and what the sources do not show.

County-wide records

Filings that name no site, state grants, and State Corporation Commission cases placed in this locality.

Sources: DEQ's active construction stormwater list, EPA ECHO (water and air), Virginia Permit Transparency, Corps of Engineers Norfolk District public notices, State Corporation Commission dockets and VEDP incentive reports.

What to read

This page covers only what these sources contain. A locality with little here may still have data center activity.